In the last 12 months, City of Hilliard (OH) has worked 15 projects. Below you can find how they have handled payment on projects, how they compare to others in the state, and a detailed payment performance breakdown.

Project Monitoring15 Projects


project

last
12 months

state
average

national
industrial average

Protected Projects

0%

37%

55%

Unprotected Projects

100%

61%

41%

Reported Slow Payment

0%

1%

2%

Projects With Liens

0%

1%

2%

Payment Performance Summary

Lien History

20240

20230

20220

20211
20200
City of Hilliard (OH) has had 0 liens filed on projects this year and 1 in recent years.
Active Liens
  • Ohio0
Of the 1 lien filed, City of Hilliard (OH) has 0 active liens in Ohio.
Lien Value
100%
0 - 50k
0%
50 - 250k
0%
250 - 500k
0%
500k - 1 million
0%
1 million +
Of the liens filed, most of the lien values were for work between 0 - 50k.
Liens by State
  • Ohio1
The 1 lien filed in recent years was in Ohio.

City of Hilliard (OH) Project and Payment History


State / County Construction Project by Ruscilli Construction Co. Inc at

6371 Scioto Darby Rd, Hilliard, OH 43026

  • Last known event: 10/08/2024
  • First known event: 09/01/2023

State / County Construction Project by Ykk Ap at

3993 Cosgray Road, Hilliard, OH 43026

  • Last known event: 09/12/2024
  • First known event: 08/01/2023

State / County Construction Project by Complete General Construction at

Hilliard OH 43026-2206, Hilliard, OH 43026

  • Last known event: 08/02/2024
  • First known event: 08/02/2024

State / County Construction Project by J&J Schlaegel Inc. at

ALTON DARBY CK RD, Hilliard, OH 43026

  • Last known event: 08/02/2024
  • First known event: 08/02/2024

State / County Construction Project by Elford, Inc. at

3858 Alton Darby Creek Rd, Hilliard, OH 43026

  • Last known event: 08/16/2024
  • First known event: 08/16/2024

State / County Construction Project by Ruscilli Construction Co. Inc at

6287 Scioto Darby Rd, Hilliard, OH 43026

  • Last known event: 01/31/2024
  • First known event: 07/21/2023

Commercial Construction Project by Danbert Inc. at

4675 Cosgray Rd, Hilliard, OH 43026

    State / County Construction Project by Clayco Inc. at

      Construction Project by unknown general contractor at

      3680 Cosgray, Hilliard, OH 43026

      • Last known event: 07/18/2023
      • First known event: 07/18/2023

      State / County Construction Project by unknown general contractor at

      ALTON DARBY CREEK RD, Galloway, OH 43119

        State / County Construction Project by unknown general contractor at

        COSGRAY RD SCIOTO DARBY RD, Hilliard, OH 43026

        • Last known event: 09/29/2023
        • First known event: 09/29/2023

        State / County Construction Project by Ruscilli Construction Co. Inc at

        6371 MUNICIPAL WAY, Hilliard, OH 43026

        • Last known event: 08/28/2023
        • First known event: 08/28/2023

        State / County Construction Project by Ruscilli Construction Co. Inc at

        Cosgray Road Extension, Hilliard, OH 43026

        • Last known event: 07/12/2023
        • First known event: 07/12/2023

        Commercial Construction Project by Whiting-Turner at

        • Last known event: 04/24/2023
        • First known event: 03/17/2023

        State / County Construction Project by unknown general contractor at

        3800 MUNICIPAL WAY, Hilliard, OH 43026

          Commercial Construction Project by Danbert Inc. at

          4515 Cosgray Rd, Hilliard, OH 43026

            Commercial Construction Project by unknown general contractor at

            WOODSVIEW WAY COSGRAY RD, Hilliard, OH 43026

            • Last known event: 06/20/2023
            • First known event: 06/20/2023

            State / County Construction Project by unknown general contractor at

            4678 Cosgray Rd 91, Hilliard, OH 43026

              State / County Construction Project by unknown general contractor at

              LEPPERT RD, Hilliard, OH 43026

              • Last known event: 02/07/2022
              • First known event: 02/07/2022

              Commercial Construction Project by unknown general contractor at

              47850 POINT PLEASANT DRIVE, Hilliard, OH 43026

                • Last known event: 11/03/2021
                • First known event: 11/03/2021

                State / County Construction Project by unknown general contractor at

                4097 Leap Rd, Hilliard, OH 43026

                • Last known event: 06/11/2021
                • First known event: 06/11/2021

                State / County Construction Project by Complete General Construction at

                  State / County Construction Project by Complete General Construction at

                  CENTER ST, Hilliard, OH 43026

                  • Last known event: 06/11/2020
                  • First known event: 06/11/2020

                  State / County Construction Project by 2K General Company, Inc. at

                  4450 Schirtzinger Rd, Hilliard, OH 43026

                    Waiting for payment from City of Hilliard (OH)


                    Get Cash Today
                    Is your invoice taking long to get paid?

                    Send an Invoice Reminder. Other contractors send an invoice reminder 15 and 25 days after sending an invoice.

                    Have an overdue invoice?

                    Send a Notice of Intent to Lien to push for payment and avoid a mechanics lien. A notice of intent to lien results in payment on more than 95% of projects.

                    Payment History Summary


                    Recent Payment Performance

                    100% of projects in the last 12 months had no reported payment issues by other contractors.

                    Last 12 months - 100%

                    Payment Performance Over the Years

                    According to available information, 100% of projects in 2023 had no reported payment incidents.

                    2024 - 100%

                    2023 - 100%

                    2022 - 100%

                    2021 - 75%