On this project at 513 1st Ave N, Seattle, WA 98109 there have been 3 permits filed, 3 preliminary notices exchanged, 0 lien waivers exchanged between companies and 5 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.
3
PERMITS FILED
3
PRELIMINARY NOTICES
0
LIEN WAIVERS
5
LIEN HISTORY
02/27/2024
Lien filed by Steeler, Inc.
Lien filed against 513b Niwa, Great Northern Enterprises, LLC Dba Ryan Pacific Construction
$5,396
Source: Levelset Data
02/06/2024
Lien filed by Great Northern Enterprises, LLC Dba Ryan Pacific Construction | Claimant directly hired by GC
Lien filed against 513b Niwa, Pavilion Construction
GC listed on lien: Pavilion Construction
$137,504
Source: Levelset Data
01/30/2024
Lien filed by GTS Interior Supply | Claimant directly hired by GC
Lien filed against 513b Niwa, Pavilion Construction
GC listed on lien: Pavilion Construction
$7,893
Source: Levelset Data
12/09/2022
Contractors listed on Permit: Phil Lam, Nos Narin
# 6903332-CN
$300,000
Source: ConstructionMonitor
10/03/2022
Lien filed by Nucor Harris Rebar Seattle Fka Harris Rebar Seattle
Lien filed against 513b Niwa, Junior G. Concrete Design LLC
$192,494
Source: Levelset Data
09/15/2022
Lien filed by Junior G. Concrete Design LLC | Claimant directly hired by GC
Lien filed against 513b Niwa, Pavilion Construction
GC listed on lien: Pavilion Construction
$325,255
Source: Levelset Data
07/03/2020
Contractors listed on Permit: Steven E Bohlman
# 6686496-CN
$21,400,000
Permit Description
Construct A Mixed-use Structure
Source: ConstructionMonitor
Companies
In this section, you can find all 9 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.
Lender
Unknown Company
Property Owner
Unknown Company
General Contractor (1)
Subcontractor (6)
View AllSupplier (1)
Levelset will pay for your materials.
You pay us back up to 120 days later.
Apply Now