On this project at 19201 Hamish Rd, Tomball, TX 77377 there have been 3 permits filed, 2 preliminary notices exchanged, 0 lien waivers exchanged between companies and 5 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.
3
PERMITS FILED
2
PRELIMINARY NOTICES
0
LIEN WAIVERS
5
LIEN HISTORY
09/13/2024
Slow Payment Reported Against Harvey Builders, Lit Interchange 249 Business Park
Over $10,000
Source: Levelset Data
04/15/2024
Slow Payment Reported Against D.E. Harvey Builders dba Harvey-Cleary Builders, Lit Interchange 249 Business Park, RDI Mechanical Inc
Over $10,000
Source: Levelset Data
04/15/2024
Slow Payment Reported Against D.E. Harvey Builders dba Harvey-Cleary Builders, RDI Mechanical Inc
Over $10,000
Source: Levelset Data
03/15/2024
Slow Payment Reported Against D.E. Harvey Builders dba Harvey-Cleary Builders, RDI Mechanical Inc
Over $5,000
Source: Levelset Data
02/15/2024
Lien filed by N C Pipe
Lien filed against Lovett Industrial, Sendero Industries
$1,061
Source: Levelset Data
01/17/2024
Lien filed by WM Trucking & Excavating Inc.
Lien filed against D.E. Harvey Builders dba Harvey-Cleary Builders, Lovett Industrial
GC listed on lien: D.E. Harvey Builders dba Harvey-Cleary Builders
$6,750
Source: Levelset Data
07/14/2023
Slow Payment Reported Against D.E. Harvey Builders dba Harvey-Cleary Builders, Lit Interchange 249 Business Park, Lit Interchange 249 Hanks Owner, Sendero Industries
Over $1,000
Source: Levelset Data
07/14/2023
Lien threat sent to Sendero Industries
Over $10,000
Source: Levelset Data
07/13/2023
Slow Payment Reported Against Axcon Corporation, Inc., D.E. Harvey Builders dba Harvey-Cleary Builders, Lit Interchange 249 Business Park, Macy's Distribution Center
Over $10,000
Source: Levelset Data
07/11/2023
Lien filed by Billd Exchange
Lien filed against Lit Interchange 249 Business Park Lit Interchange 249 Phase 1, Prosegur Security Usa, Vetcore Technology
$7,707
Source: Levelset Data
06/15/2023
Lien filed by Rock Solid Precast Lp
Lien filed against Lit Interchange 249 Business Park Lit Interchange 249 Phase 1, Sendero Industries
$96,048
Source: Levelset Data
06/13/2023
Slow Payment Reported Against D.E. Harvey Builders dba Harvey-Cleary Builders, Sendero Industries
Over $1,000
Source: Levelset Data
05/15/2023
Lien filed by N C Pipe
Lien filed against Lovett Industrial, Sendero Industries
$11,569
Source: Levelset Data
05/15/2023
Slow Payment Reported Against D.E. Harvey Builders dba Harvey-Cleary Builders, Lit Interchange 249 Hanks Owner, Sendero Industries
Over $1,000
Source: Levelset Data
05/08/2023
Slow Payment Reported Against D.E. Harvey Builders dba Harvey-Cleary Builders, Sendero Industries
Over $1,000
Source: Levelset Data
04/07/2023
Slow Payment Reported Against D.E. Harvey Builders dba Harvey-Cleary Builders, Sendero Industries
Over $1,000
Source: Levelset Data
03/07/2023
Slow Payment Reported Against D.E. Harvey Builders dba Harvey-Cleary Builders, Sendero Industries
Over $1,000
Source: Levelset Data
02/01/2023
Slow Payment Reported Against D.E. Harvey Builders dba Harvey-Cleary Builders, Sendero Industries
Over $1,000
Source: Levelset Data
02/01/2023
Slow Payment Reported Against D.E. Harvey Builders dba Harvey-Cleary Builders, Lit Interchange 249 Hanks Owner, Sendero Industries
Over $1,000
Source: Levelset Data
01/04/2023
Slow Payment Reported Against D.E. Harvey Builders dba Harvey-Cleary Builders, Sendero Industries
Over $1,000
Source: Levelset Data
11/03/2022
Slow Payment Reported Against D.E. Harvey Builders dba Harvey-Cleary Builders, Lit Interchange 249 Hanks Owner, Sendero Industries
Over $10,000
Source: Levelset Data
11/03/2022
Slow Payment Reported Against D.E. Harvey Builders dba Harvey-Cleary Builders, Sendero Industries
Over $10,000
Source: Levelset Data
11/03/2022
Contractors listed on Permit: Ansco & Associates
# 202202978
$500,000
Source: ConstructionMonitor
10/14/2022
Slow Payment Reported Against D.E. Harvey Builders dba Harvey-Cleary Builders, Sendero Industries
Over $10,000
Source: Levelset Data
09/15/2022
Source: ConstructionMonitor
05/24/2022
Source: ConstructionMonitor
Companies
In this section, you can find all 25 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.