On this project at 4020 Hwy 380 W, Throckmorton, TX 76483 there have been 0 permits filed, 2 preliminary notices exchanged, 0 lien waivers exchanged between companies and 0 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.
0
PERMITS FILED
2
PRELIMINARY NOTICES
$2,113.58 value
0
LIEN WAIVERS
0
LIEN HISTORY
08/15/2024
Slow Payment Reported Against American Electric Power Company, Kiewit Corporation
Over $60,000
Source: Levelset Data
06/14/2024
Slow Payment Reported Against American Electric Power Company, Kiewit Corporation
Over $60,000
Source: Levelset Data
05/15/2024
Slow Payment Reported Against American Electric Power Company, Kiewit Corporation
Over $60,000
Source: Levelset Data
09/15/2023
Slow Payment Reported Against Kiewit Corporation
Over $60,000
Source: Levelset Data
06/15/2023
Slow Payment Reported Against Kiewit Corporation
Over $60,000
Source: Levelset Data
10/15/2021
Slow Payment Reported Against Enel Green Power North America, Wanzek Construction
Over $60,000
Source: Levelset Data
08/13/2021
Slow Payment Reported Against Enel Green Power North America, Wanzek Construction
Over $60,000
Source: Levelset Data
Companies
In this section, you can find all 7 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.