Menu
A map for the project located in TEXAS CITY, Texas.
Commercial Construction Project at

3301 5th Ave S

TEXAS CITY, TX 77590

  • Last known event: 01/13/2023
  • First known event: 09/15/2018

Property Details


PROJECT TYPE

Commercial

PROPERTY OWNER

Dow Chemical Company

CITY

TEXAS CITY

Key Facts

The project located at 3301 5th Ave S, TEXAS CITY, Texas 77590 has had 19 companies do work over the last 7 years.

Lien History

There has been 1 lien at this address with a reported total value of $10,543,281.54.

Project History


On this project at 3301 5th Ave S, TEXAS CITY, TX 77590 there have been 0 permits filed, 0 preliminary notices exchanged, 0 lien waivers exchanged between companies and 1 lien filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.

Overview

0

PERMITS FILED

0

PRELIMINARY NOTICES

0

LIEN WAIVERS

1

LIEN HISTORY

Payment Timeline

01/13/2023

Slow Payment Reported

Slow Payment Reported Against Air Products, Mountaineer Fabricators, Praxair

Over $10,000


Source: Levelset Data

12/15/2022

Slow Payment Reported

Slow Payment Reported Against Mountaineer Fabricators

Over $10,000


Source: Levelset Data

09/15/2022

Slow Payment Reported

Slow Payment Reported Against Air Products, Mountaineer Fabricators, Praxair

Over $10,000


Source: Levelset Data

09/15/2022

Slow Payment Reported

Slow Payment Reported Against Mountaineer Fabricators

Over $10,000


Source: Levelset Data

08/15/2022

Slow Payment Reported

Slow Payment Reported Against Air Products, Mountaineer Fabricators, Praxair

Over $60,000


Source: Levelset Data

08/15/2022

Slow Payment Reported

Slow Payment Reported Against Mountaineer Fabricators

Over $60,000


Source: Levelset Data

07/15/2022

Slow Payment Reported

Slow Payment Reported Against Air Products, Mountaineer Fabricators, Praxair

Over $60,000


Source: Levelset Data

07/15/2022

Slow Payment Reported

Slow Payment Reported Against Mountaineer Fabricators

Over $60,000


Source: Levelset Data

06/15/2022

Slow Payment Reported

Slow Payment Reported Against Air Products, Mountaineer Fabricators, Praxair

Over $60,000


Source: Levelset Data

06/15/2022

Slow Payment Reported

Slow Payment Reported Against Mountaineer Fabricators

Over $60,000


Source: Levelset Data

05/13/2022

Slow Payment Reported

Slow Payment Reported Against Mountaineer Fabricators

Over $60,000


Source: Levelset Data

03/15/2022

Slow Payment Reported

Slow Payment Reported Against Mountaineer Fabricators

Over $10,000


Source: Levelset Data

03/15/2022

Slow Payment Reported

Slow Payment Reported Against Air Products, Mountaineer Fabricators, Praxair

Over $10,000


Source: Levelset Data

02/15/2022

Slow Payment Reported

Slow Payment Reported Against Mountaineer Fabricators

Over $60,000


Source: Levelset Data

01/14/2022

Slow Payment Reported

Slow Payment Reported Against Mountaineer Fabricators

Over $60,000


Source: Levelset Data

12/15/2021

Slow Payment Reported

Slow Payment Reported Against Mountaineer Fabricators

Over $10,000


Source: Levelset Data

09/11/2019

Mechanics Lien Filed

Lien filed by Elite Piping And Civil

Lien filed against Dow Chemical Company, Union Carbide Corporation

Property Owner: Dow Chemical Company

$5,271,641


Source: Levelset Data

03/16/2019

Slow Payment Reported

Slow Payment Reported Against ATS Industrial dba ATS Construction, Dow Chemical Company, Group Contractors

Less than $1,000


Source: Levelset Data

02/16/2019

Slow Payment Reported

Slow Payment Reported Against ATS Industrial dba ATS Construction, Dow Chemical Company, Group Contractors

Less than $1,000


Source: Levelset Data

02/16/2019

Slow Payment Reported

Slow Payment Reported Against ATS Industrial dba ATS Construction, Group Contractors

Less than $1,000


Source: Levelset Data

01/18/2019

Lien Threatened


Source: Levelset Data

01/16/2019

Slow Payment Reported

Slow Payment Reported Against ATS Industrial dba ATS Construction, Dow Chemical Company, Group Contractors

Less than $1,000


Source: Levelset Data

01/16/2019

Slow Payment Reported

Slow Payment Reported Against ATS Industrial dba ATS Construction, Group Contractors

Less than $1,000


Source: Levelset Data

12/15/2018

Slow Payment Reported

Slow Payment Reported Against ATS Industrial dba ATS Construction, Dow Chemical Company, Group Contractors

Less than $1,000


Source: Levelset Data

12/15/2018

Slow Payment Reported

Slow Payment Reported Against ATS Industrial dba ATS Construction, Group Contractors

Less than $1,000


Source: Levelset Data

11/16/2018

Slow Payment Reported

Slow Payment Reported Against ATS Industrial dba ATS Construction, Dow Chemical Company, Group Contractors

Less than $1,000


Source: Levelset Data

11/16/2018

Slow Payment Reported

Slow Payment Reported Against ATS Industrial dba ATS Construction, Group Contractors

Less than $1,000


Source: Levelset Data

10/16/2018

Slow Payment Reported

Slow Payment Reported Against ATS Industrial dba ATS Construction, Group Contractors

Less than $1,000


Source: Levelset Data

09/15/2018

Slow Payment Reported

Slow Payment Reported Against Dow Chemical Company, The Brock Group

Less than $1,000


Source: Levelset Data

Full Project Job Tree19

Companies


In this section, you can find all 19 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.

Lender

Unknown Company

Property Owner

Bonded by Unknown

General Contractor (2)

Bonded by Unknown
Bonded by Unknown

Subcontractor (9)

Subcontractor
Subcontractor
Subcontractor
Utilities Contractors
Subcontractor

Supplier (7)

ED
Equipment Depot
FE
Ferguson Enterprises, LLC
AR
Ahern Rentals, Inc.

Surety Companies

Unknown Company

Job Hierarchy


Lender

Unknown Company

Property Owner

Bonded by Unknown

General Contractor (2)

View All
Bonded by Unknown

Subcontractor (9)

View All

Supplier (7)

View All

Need cash to buy materials for this job?

Levelset will pay for your materials.

You pay us back up to 120 days later.

Apply Now