On this project at 509 Nursery Rd, Spring, TX 77380 there have been 0 permits filed, 4 preliminary notices exchanged, 3 lien waivers exchanged between companies and 2 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.
0
PERMITS FILED
4
PRELIMINARY NOTICES
3
LIEN WAIVERS
2
LIEN HISTORY
06/13/2024
Slow Payment Reported Against Strategic Construction
Over $5,000
Source: Levelset Data
05/15/2024
Slow Payment Reported Against Central Fire Protection Inc., Strategic Construction
Over $1,000
Source: Levelset Data
04/15/2024
Slow Payment Reported Against Central Fire Protection Inc., Strategic Construction
Less than $1,000
Source: Levelset Data
02/15/2024
Slow Payment Reported Against HR Mechanical, Strategic Construction, Woodlands Nursery Road Property
Less than $1,000
Source: Levelset Data
02/15/2024
Slow Payment Reported Against HR Mechanical, Strategic Construction
Less than $1,000
Source: Levelset Data
01/12/2024
Slow Payment Reported Against HR Mechanical, Strategic Construction, Woodlands Nursery Road Property
Less than $1,000
Source: Levelset Data
01/12/2024
Slow Payment Reported Against HR Mechanical, Strategic Construction
Less than $1,000
Source: Levelset Data
12/15/2023
Slow Payment Reported Against HR Mechanical, Strategic Construction
Less than $1,000
Source: Levelset Data
11/15/2023
Slow Payment Reported Against HR Mechanical, Strategic Construction
Less than $1,000
Source: Levelset Data
11/15/2023
Slow Payment Reported Against Woodlands Nursery Road Property
Over $10,000
Source: Levelset Data
11/15/2023
Slow Payment Reported Against HR Mechanical, Strategic Construction, Woodlands Nursery Road Property
Less than $1,000
Source: Levelset Data
10/13/2023
Slow Payment Reported Against HR Mechanical, Strategic Construction, Woodlands Nursery Road Property
Less than $1,000
Source: Levelset Data
10/13/2023
Lien filed by Houston Heavy Machinery
Lien filed against Sendero Industries, Strategic Construction, Woodlands Nursery Road Property
GC listed on lien: Strategic Construction
$17,779
Source: Levelset Data
10/13/2023
Slow Payment Reported Against HR Mechanical, Strategic Construction
Less than $1,000
Source: Levelset Data
09/15/2023
Slow Payment Reported Against HR Mechanical, Strategic Construction
Less than $1,000
Source: Levelset Data
08/15/2023
Slow Payment Reported Against HR Mechanical, Strategic Construction
Less than $1,000
Source: Levelset Data
07/14/2023
Slow Payment Reported Against Sli Framing Inc, Strategic Construction
Over $10,000
Source: Levelset Data
07/14/2023
Slow Payment Reported Against HR Mechanical, Strategic Construction
Less than $1,000
Source: Levelset Data
07/14/2023
Slow Payment Reported Against HR Mechanical, Strategic Construction, Woodlands Nursery Road Property
Less than $1,000
Source: Levelset Data
06/15/2023
Slow Payment Reported Against HR Mechanical, Strategic Construction, Woodlands Nursery Road Property
Less than $1,000
Source: Levelset Data
06/15/2023
Slow Payment Reported Against HR Mechanical, Strategic Construction
Less than $1,000
Source: Levelset Data
06/15/2023
Slow Payment Reported Against Reyes Retaining Walls, Strategic Construction, Woodlands Nursery Road Property
Over $5,000
Source: Levelset Data
05/25/2023
Slow Payment Reported Against Strategic Construction, Woodlands Nursery Road Property
Over $60,000
Source: Levelset Data
05/15/2023
Slow Payment Reported Against HR Mechanical, Strategic Construction
Less than $1,000
Source: Levelset Data
05/15/2023
Slow Payment Reported Against Reyes Retaining Walls, Strategic Construction
Over $5,000
Source: Levelset Data
05/15/2023
Slow Payment Reported Against Central Fire Protection Inc., Strategic Construction
Over $60,000
Source: Levelset Data
05/15/2023
Slow Payment Reported Against Sli Framing Inc, Strategic Construction
Over $10,000
Source: Levelset Data
05/15/2023
Slow Payment Reported Against HR Mechanical, Strategic Construction, Woodlands Nursery Road Property
Less than $1,000
Source: Levelset Data
04/14/2023
Slow Payment Reported Against HR Mechanical, Strategic Construction, Woodlands Nursery Road Property
Less than $1,000
Source: Levelset Data
04/14/2023
Slow Payment Reported Against Reyes Retaining Walls, Strategic Construction
Over $10,000
Source: Levelset Data
04/14/2023
Slow Payment Reported Against HR Mechanical, Strategic Construction
Less than $1,000
Source: Levelset Data
03/15/2023
Slow Payment Reported Against HR Mechanical
Less than $1,000
Source: Levelset Data
03/14/2023
Lien filed by WM Trucking & Excavating Inc.
Lien filed against Sendero Industries, Woodlands Nursery Road Property
$34,235
Source: Levelset Data
01/13/2023
Slow Payment Reported Against Reyes Retaining Walls, Strategic Construction
Over $10,000
Source: Levelset Data
01/13/2023
Slow Payment Reported Against HR Mechanical
Less than $1,000
Source: Levelset Data
Companies
In this section, you can find all 23 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.