On this project at 21603 Spring Plaza Drive, Spring, TX 77388 there have been 0 permits filed, 1 preliminary notice exchanged, 0 lien waivers exchanged between companies and 1 lien filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.
0
PERMITS FILED
1
PRELIMINARY NOTICES
0
LIEN WAIVERS
1
LIEN HISTORY
11/15/2019
Lien filed by Morsco
Lien filed against Crp Maple Spring Owner Lp, Maple Multi Family TX Contractor LLC
GC listed on lien: Maple Multi Family TX Contractor LLC
$20,139
Source: Levelset Data
10/15/2019
Slow Payment Reported Against Crp Maple Spring Owner Lp, Maple Multi Family TX Contractor LLC, Masram Mechanical
Less than $1,000
Source: Levelset Data
09/13/2019
Slow Payment Reported Against Maple Multi Family TX Contractor LLC, Masram Mechanical
Over $10,000
Source: Levelset Data
09/13/2019
Slow Payment Reported Against Crp Maple Spring Owner Lp, Maple Multi Family TX Contractor LLC, Masram Mechanical
Over $10,000
Source: Levelset Data
08/15/2019
Slow Payment Reported Against Masram Mechanical
Over $10,000
Source: Levelset Data
07/12/2019
Slow Payment Reported Against Spring Phase I, Trammell Crow Company (TCC)
Over $1,000
Source: Levelset Data
06/14/2019
Slow Payment Reported Against Maple Multi Family TX Contractor LLC, Masram Mechanical
Over $10,000
Source: Levelset Data
05/15/2019
Slow Payment Reported Against Spring Phase I, Trammell Crow Company (TCC)
Over $1,000
Source: Levelset Data
05/15/2019
Slow Payment Reported Against Maple Multi Family TX Contractor LLC, Masram Mechanical
Over $10,000
Source: Levelset Data
02/16/2019
Slow Payment Reported Against Trammell Crow Company (TCC)
Less than $1,000
Source: Levelset Data
02/15/2019
Slow Payment Reported Against Maple Multi Family TX Contractor LLC, Masram Mechanical
Over $10,000
Source: Levelset Data
01/16/2019
Slow Payment Reported Against Trammell Crow Company (TCC)
Less than $1,000
Source: Levelset Data
01/15/2019
Slow Payment Reported Against Maple Multi Family TX Contractor LLC, Masram Mechanical
Over $10,000
Source: Levelset Data
12/14/2018
Slow Payment Reported Against Maple Multi Family TX Contractor LLC, Masram Mechanical
Over $10,000
Source: Levelset Data
Companies
In this section, you can find all 7 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.
Levelset will pay for your materials.
You pay us back up to 120 days later.
Apply Now