On this project at 1721 8th St, Seguin, TX 78155 there have been 3 permits filed, 0 preliminary notices exchanged, 0 lien waivers exchanged between companies and 2 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.
3
PERMITS FILED
0
PRELIMINARY NOTICES
0
LIEN WAIVERS
2
LIEN HISTORY
06/27/2024
Contractors listed on Permit: MW Builders, Inc., Vme United Alloy Thomas R Baer
# BCOM0524-1113
$301,000
Source: ConstructionMonitor
12/18/2023
Contractors listed on Permit: MW Builders, Inc., Vme United Alloy Thomas R Baer
# BCOM1023-0600
$920,000
Source: ConstructionMonitor
07/14/2023
Slow Payment Reported Against Air Craft Inc., MW Builders, Inc., Vme United Alloy Thomas R Baer
Over $5,000
Source: Levelset Data
06/15/2023
Slow Payment Reported Against Air Craft Inc., MW Builders, Inc.
Over $5,000
Source: Levelset Data
04/14/2023
Slow Payment Reported Against MW Builders, Inc., Osburn Contractors
Over $1,000
Source: Levelset Data
03/15/2023
Slow Payment Reported Against MW Builders, Inc., Osburn Contractors
Over $5,000
Source: Levelset Data
03/15/2023
Slow Payment Reported Against MW Builders, Inc., Osburn Contractors, Vme United Alloy Thomas R Baer
Over $5,000
Source: Levelset Data
03/15/2023
Slow Payment Reported Against MW Builders, Inc., Osburn Contractors
Over $1,000
Source: Levelset Data
02/15/2023
Slow Payment Reported Against MW Builders, Inc.
Over $10,000
Source: Levelset Data
02/15/2023
Slow Payment Reported Against MW Builders, Inc., Osburn Contractors
Over $5,000
Source: Levelset Data
02/15/2023
Slow Payment Reported Against Air Craft Inc., MW Builders, Inc.
Over $5,000
Source: Levelset Data
02/15/2023
Slow Payment Reported Against Air Craft Inc., MW Builders, Inc., Vme United Alloy Thomas R Baer
Over $5,000
Source: Levelset Data
02/15/2023
Slow Payment Reported Against MW Builders, Inc., Osburn Contractors
Over $5,000
Source: Levelset Data
02/15/2023
Slow Payment Reported Against MW Builders, Inc., Vme United Alloy Thomas R Baer
Over $10,000
Source: Levelset Data
01/13/2023
Slow Payment Reported Against MW Builders, Inc., Osburn Contractors, Vme United Alloy Thomas R Baer
Over $10,000
Source: Levelset Data
01/13/2023
Slow Payment Reported Against MW Builders, Inc., Osburn Contractors
Over $10,000
Source: Levelset Data
01/13/2023
Slow Payment Reported Against MW Builders, Inc.
Over $10,000
Source: Levelset Data
01/13/2023
Slow Payment Reported Against MW Builders, Inc., Osburn Contractors
Over $10,000
Source: Levelset Data
01/13/2023
Slow Payment Reported Against Air Craft Inc., MW Builders, Inc.
Over $60,000
Source: Levelset Data
12/15/2022
Slow Payment Reported Against Air Craft Inc., MW Builders, Inc.
Over $60,000
Source: Levelset Data
12/15/2022
Slow Payment Reported Against MW Builders, Inc., Vme United Alloy Thomas R Baer
Over $10,000
Source: Levelset Data
12/15/2022
Slow Payment Reported Against American Underground, D And S Concrete Contractors
Over $5,000
Source: Levelset Data
12/15/2022
Slow Payment Reported Against MW Builders, Inc.
Over $10,000
Source: Levelset Data
12/15/2022
Slow Payment Reported Against Air Craft Inc., MW Builders, Inc., Vme United Alloy Thomas R Baer
Over $60,000
Source: Levelset Data
12/13/2022
Slow Payment Reported Against MW Builders, Inc., Osburn Contractors
Over $10,000
Source: Levelset Data
12/09/2022
Lien filed by Mohawk Concrete Pumping
Lien filed against MW Builders, Inc., Osburn Contractors, Vme United Alloy Thomas R Baer
GC listed on lien: MW Builders, Inc.
$32,915
Source: Levelset Data
11/15/2022
Slow Payment Reported Against Air Craft Inc., MW Builders, Inc.
Over $10,000
Source: Levelset Data
11/15/2022
Slow Payment Reported Against American Underground, D And S Concrete Contractors
Over $5,000
Source: Levelset Data
11/15/2022
Slow Payment Reported Against MW Builders, Inc., Vme United Alloy Thomas R Baer
Over $10,000
Source: Levelset Data
11/15/2022
Slow Payment Reported Against MW Builders, Inc.
Over $10,000
Source: Levelset Data
11/15/2022
Lien filed by Opifex
Lien filed against MW Builders, Inc., Osburn Contractors, Vme United Alloy Thomas R Baer
GC listed on lien: MW Builders, Inc.
$23,873
Source: Levelset Data
11/14/2022
Slow Payment Reported Against MW Builders, Inc., Osburn Contractors
Over $10,000
Source: Levelset Data
10/14/2022
Slow Payment Reported Against MW Builders, Inc.
Over $10,000
Source: Levelset Data
10/14/2022
Slow Payment Reported Against American Underground, D And S Concrete Contractors
Over $5,000
Source: Levelset Data
01/15/2021
Slow Payment Reported Against Airco Mechanical (TX), MW Builders, Inc., Tom Baer, Vme United Alloy Thomas R Baer
Over $1,000
Source: Levelset Data
11/13/2020
Slow Payment Reported Against Arch Insurance Company, MW Builders, Inc., Osburn Contractors
Over $1,000
Source: Levelset Data
11/13/2020
Slow Payment Reported Against MW Builders, Inc., Osburn Contractors
Over $1,000
Source: Levelset Data
10/15/2020
Slow Payment Reported Against MW Builders, Inc., Osburn Contractors
Over $1,000
Source: Levelset Data
10/15/2020
Slow Payment Reported Against Airco Mechanical (TX), MW Builders, Inc., Tom Baer, Vme United Alloy Thomas R Baer
Over $10,000
Source: Levelset Data
09/15/2020
Slow Payment Reported Against MW Builders, Inc., Osburn Contractors
Over $10,000
Source: Levelset Data
09/15/2020
Slow Payment Reported Against Airco Mechanical (TX), MW Builders, Inc., Tom Baer
Over $10,000
Source: Levelset Data
08/14/2020
Slow Payment Reported Against MW Builders, Inc., Osburn Contractors
Over $10,000
Source: Levelset Data
07/15/2020
Slow Payment Reported Against MW Builders, Inc., Osburn Contractors
Over $60,000
Source: Levelset Data
06/15/2020
Slow Payment Reported Against MW Builders, Inc., Osburn Contractors
Over $60,000
Source: Levelset Data
03/11/2020
Contractors listed on Permit: Seguin Economic Development Corporation, MW Builders, Inc.
# BCOM-000609-2020
$12,131,500
Source: ConstructionMonitor
Companies
In this section, you can find all 16 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.
Levelset will pay for your materials.
You pay us back up to 120 days later.
Apply Now