On this project at 2401 W Pflugerville Pkwy, Round Rock, TX 78664 there have been 0 permits filed, 0 preliminary notices exchanged, 0 lien waivers exchanged between companies and 10 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.
0
PERMITS FILED
0
PRELIMINARY NOTICES
0
LIEN WAIVERS
10
LIEN HISTORY
09/15/2021
Slow Payment Reported Against Hollybrook Ranch
Less than $1,000
Source: Levelset Data
06/11/2021
Lien filed by Shipman Fire
Lien filed against CIP Construction, Hollybrook Ranch
GC listed on lien: CIP Construction
$1,876
Source: Levelset Data
06/10/2021
Slow Payment Reported Against CIP Construction, Hollybrook Ranch
Over $1,000
Source: Levelset Data
05/14/2021
Slow Payment Reported Against Hollybrook Ranch
Over $1,000
Source: Levelset Data
02/01/2021
Lien filed by Buffalo Framing & Truss LLC | Claimant directly hired by GC
Lien filed against CIP Construction, Hollybrook Ranch
GC listed on lien: CIP Construction
$193,200
Source: Levelset Data
08/14/2020
Lien filed by Choate USA Landscape Construction | Claimant directly hired by GC
Lien filed against CIP Construction, Hollybrook Ranch
GC listed on lien: Choate USA Landscape Construction
$4,080
Source: Levelset Data
06/15/2020
Lien filed by Champion Site Prep, Inc. | Claimant directly hired by GC
Lien filed against CIP Construction, Hollybrook Ranch
GC listed on lien: CIP Construction
$329,856
Source: Levelset Data
05/11/2020
Lien filed by Granite By Andrew
Lien filed against CIP Construction, Hollybrook Ranch, Premier Surfaces Acquisition LLC
GC listed on lien: CIP Construction
$7,694
Source: Levelset Data
04/15/2020
Lien filed by Choate USA Landscape Construction | Claimant directly hired by GC
Lien filed against CIP Construction, Hollybrook Ranch
GC listed on lien: Choate USA Landscape Construction
$11,623
Source: Levelset Data
03/13/2020
Lien filed by Choate USA Landscape Construction | Claimant directly hired by GC
Lien filed against CIP Construction, Hollybrook Ranch
GC listed on lien: Choate USA Landscape Construction
$1,070
Source: Levelset Data
11/15/2019
Slow Payment Reported Against Hollybrook Ranch
Less than $1,000
Source: Levelset Data
10/15/2019
Slow Payment Reported Against Alex Jr. Construction Services, CIP Construction, Hollybrook Ranch
Over $60,000
Source: Levelset Data
10/15/2019
Slow Payment Reported Against Alex Jr. Construction Services, CIP Construction
Over $60,000
Source: Levelset Data
10/15/2019
Slow Payment Reported Against Hollybrook Ranch
Less than $1,000
Source: Levelset Data
09/13/2019
Slow Payment Reported Against Alex Jr. Construction Services, CIP Construction
Over $60,000
Source: Levelset Data
09/09/2019
Lien filed by Allstate Gutter Holdings, LLC
Lien filed against Hollybrook Ranch, Tip Top Roofing
Property Owner: Allstate Gutter Holdings, LLC
$29,393
Source: Levelset Data
08/15/2019
Slow Payment Reported Against Alex Jr. Construction Services, CIP Construction
Over $60,000
Source: Levelset Data
08/12/2019
Lien filed by ABC Supply Co. Inc. (American Builders & Contractors Supply)
Lien filed against Hollybrook Ranch, Tip Top Roofing
$70,877
Source: Levelset Data
07/15/2019
Slow Payment Reported Against Alex Jr. Construction Services, CIP Construction
Over $60,000
Source: Levelset Data
06/14/2019
Slow Payment Reported Against Alex Jr. Construction Services, CIP Construction
Over $60,000
Source: Levelset Data
05/15/2019
Slow Payment Reported Against CIP Construction
Over $60,000
Source: Levelset Data
04/15/2019
Slow Payment Reported Against CIP Construction, Got U Covered LLC, Hollybrook Ranch
Over $5,000
Source: Levelset Data
04/15/2019
Slow Payment Reported Against CIP Construction
Over $60,000
Source: Levelset Data
03/16/2019
Slow Payment Reported Against CIP Construction
Less than $1,000
Source: Levelset Data
02/16/2019
Slow Payment Reported Against CIP Construction
Less than $1,000
Source: Levelset Data