On this project at 200 Dell Way, Round Rock, TX 78664 there have been 3 permits filed, 3 preliminary notices exchanged, 1 lien waiver exchanged between companies and 0 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.
3
PERMITS FILED
3
PRELIMINARY NOTICES
1
LIEN WAIVERS
0
LIEN HISTORY
12/13/2024
Slow Payment Reported Against 5F Mechanical Group Inc., NOVO Construction
Over $10,000
Source: Levelset Data
04/15/2024
Slow Payment Reported Against Lehne Construction, NOVO Construction
Over $1,000
Source: Levelset Data
03/15/2024
Slow Payment Reported Against C.C. Carlton Industries, Ltd., Hensel Phelps Construction Co.
Over $1,000
Source: Levelset Data
12/15/2023
Slow Payment Reported Against Lehne Construction, NOVO Construction
Over $5,000
Source: Levelset Data
10/13/2023
Slow Payment Reported Against Dell Inc., Hensel Phelps Construction Co., NOVO Construction, Rock Solid Concrete (TX), Switch
Less than $1,000
Source: Levelset Data
09/15/2023
Slow Payment Reported Against Hensel Phelps Construction Co., NOVO Construction, Rock Solid Concrete (TX)
Less than $1,000
Source: Levelset Data
08/15/2023
Slow Payment Reported Against C.C. Carlton Industries, Ltd.
Over $60,000
Source: Levelset Data
06/15/2023
Slow Payment Reported Against C.C. Carlton Industries, Ltd.
Over $60,000
Source: Levelset Data
06/15/2023
Slow Payment Reported Against Hensel Phelps Construction Co., Rock Solid Concrete (TX)
Over $1,000
Source: Levelset Data
05/15/2023
Slow Payment Reported Against C.C. Carlton Industries, Ltd.
Over $10,000
Source: Levelset Data
03/15/2023
Slow Payment Reported Against Trimbuilt Construction
Over $5,000
Source: Levelset Data
02/15/2023
Slow Payment Reported Against C.C. Carlton Industries, Ltd.
Over $10,000
Source: Levelset Data
01/13/2023
Slow Payment Reported Against C.C. Carlton Industries, Ltd.
Over $10,000
Source: Levelset Data
01/13/2023
Slow Payment Reported Against Dell Inc., SI Mechanical, Trimbuilt Construction
Over $1,000
Source: Levelset Data
12/15/2022
Slow Payment Reported Against SI Mechanical, Trimbuilt Construction
Over $1,000
Source: Levelset Data
12/15/2022
Slow Payment Reported Against C.C. Carlton Industries, Ltd.
Over $60,000
Source: Levelset Data
11/15/2022
Slow Payment Reported Against SI Mechanical, Trimbuilt Construction
Over $1,000
Source: Levelset Data
11/15/2022
Slow Payment Reported Against C.C. Carlton Industries, Ltd.
Over $60,000
Source: Levelset Data
10/14/2022
Slow Payment Reported Against C.C. Carlton Industries, Ltd.
Over $60,000
Source: Levelset Data
07/15/2022
Slow Payment Reported Against C.C. Carlton Industries, Ltd.
Over $5,000
Source: Levelset Data
03/15/2022
Slow Payment Reported Against Navejas Electric
Over $1,000
Source: Levelset Data
12/20/2021
Source: ConstructionMonitor
06/15/2021
Slow Payment Reported Against 5F Mechanical Group Inc., Dell Inc., Trimbuilt Construction
Over $1,000
Source: Levelset Data
05/14/2021
Slow Payment Reported Against 5F Mechanical Group Inc., Trimbuilt Construction
Over $5,000
Source: Levelset Data
11/18/2020
Source: ConstructionMonitor
10/28/2020
Source: ConstructionMonitor
Companies
In this section, you can find all 31 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.
Levelset will pay for your materials.
You pay us back up to 120 days later.