On this project at 1200 E Kelly Ave, PHARR, TX 78577 there have been 0 permits filed, 0 preliminary notices exchanged, 0 lien waivers exchanged between companies and 1 lien filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.
0
PERMITS FILED
0
PRELIMINARY NOTICES
0
LIEN WAIVERS
1
LIEN HISTORY
03/15/2023
Slow Payment Reported Against Holchemont Ltd
Over $1,000
Source: Levelset Data
02/13/2023
Lien filed by 1st FP Services, LLC | Claimant directly hired by GC
Lien filed against Holchemont Ltd, Vanguard Academy Charter School
GC listed on lien: Holchemont Ltd
Property Owner: Vanguard Academy Charter School
$5,908
Source: Levelset Data
01/13/2023
Slow Payment Reported Against Erico Building Systems, Holchemont Ltd, Vanguard Academy Charter School
Over $1,000
Source: Levelset Data
12/15/2022
Slow Payment Reported Against Erico Building Systems, Holchemont Ltd
Over $1,000
Source: Levelset Data
11/07/2022
Slow Payment Reported Against Vanguard Academy Charter School
Over $5,000
Source: Levelset Data
09/15/2022
Slow Payment Reported Against Erico Building Systems, Holchemont Ltd
Over $10,000
Source: Levelset Data
08/15/2022
Slow Payment Reported Against Erico Building Systems, Holchemont Ltd
Over $10,000
Source: Levelset Data
06/15/2022
Slow Payment Reported Against Atlantic Specialty Ins Company, Holchemont Ltd, Sant Construction LLC
Over $1,000
Source: Levelset Data
05/13/2022
Slow Payment Reported Against Holchemont Ltd, Sant Construction LLC
Over $1,000
Source: Levelset Data