Menu
A map for the project located in LEANDER, Texas.
Commercial Construction Project at

260 S Brook Dr 261

LEANDER, TX 78641

  • Last known event: 11/15/2021
  • First known event: 05/15/2020

Property Details


PROJECT TYPE

Commercial

PROPERTY OWNER

Unknown

CITY

LEANDER

Key Facts

The project located at 260 S Brook Dr 261, LEANDER, Texas 78641 has had 11 companies do work over the last 5 years.

Lien History

There has been 0 liens at this address with a reported total value of $0.

Project History


On this project at 260 S Brook Dr 261, LEANDER, TX 78641 there have been 0 permits filed, 0 preliminary notices exchanged, 0 lien waivers exchanged between companies and 0 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.

Overview

0

PERMITS FILED

0

PRELIMINARY NOTICES

0

LIEN WAIVERS

0

LIEN HISTORY

Payment Timeline

11/15/2021

Slow Payment Reported

Slow Payment Reported Against Allied Construction Management, Allied Orion Group, HR Mechanical

Less than $1,000


Source: Levelset Data

11/15/2021

Slow Payment Reported

Slow Payment Reported Against Allied Orion Group, Meridian Drywall, The Retreat At Oak Creek

Over $10,000


Source: Levelset Data

11/15/2021

Slow Payment Reported

Slow Payment Reported Against Allied Orion Group, Meridian Drywall

Over $10,000


Source: Levelset Data

10/15/2021

Slow Payment Reported

Slow Payment Reported Against Allied Construction Management, Allied Orion Group, HR Mechanical

Less than $1,000


Source: Levelset Data

10/15/2021

Slow Payment Reported

Slow Payment Reported Against Allied Construction Management, Allied Orion Group, HR Mechanical, The Retreat At Oak Creek

Less than $1,000


Source: Levelset Data

10/15/2021

Slow Payment Reported

Slow Payment Reported Against Allied Orion Group, Meridian Drywall

Over $10,000


Source: Levelset Data

09/15/2021

Slow Payment Reported

Slow Payment Reported Against Aog Granary Gc Dba Allied Construction Services, Hayes Concrete Services LLC, The Retreat At Oak Creek

Over $10,000


Source: Levelset Data

09/15/2021

Slow Payment Reported

Slow Payment Reported Against Aog Granary Gc Dba Allied Construction Services, Hayes Concrete Services LLC

Over $10,000


Source: Levelset Data

09/15/2021

Slow Payment Reported

Slow Payment Reported Against Allied Construction Management, Allied Orion Group, HR Mechanical

Less than $1,000


Source: Levelset Data

08/13/2021

Slow Payment Reported

Slow Payment Reported Against Aog Granary Gc Dba Allied Construction Services, Hayes Concrete Services LLC, The Retreat At Oak Creek

Over $10,000


Source: Levelset Data

08/13/2021

Slow Payment Reported

Slow Payment Reported Against Aog Granary Gc Dba Allied Construction Services, Hayes Concrete Services LLC

Over $10,000


Source: Levelset Data

08/13/2021

Slow Payment Reported

Slow Payment Reported Against Allied Orion Group, HR Mechanical

Less than $1,000


Source: Levelset Data

07/15/2021

Slow Payment Reported

Slow Payment Reported Against Allied Orion Group, HR Mechanical

Less than $1,000


Source: Levelset Data

07/15/2021

Slow Payment Reported

Slow Payment Reported Against Allied Orion Group, HR Mechanical, The Retreat At Oak Creek

Less than $1,000


Source: Levelset Data

07/15/2021

Slow Payment Reported

Slow Payment Reported Against Aog Granary Gc Dba Allied Construction Services, Hayes Concrete Services LLC

Over $10,000


Source: Levelset Data

07/15/2021

Slow Payment Reported

Slow Payment Reported Against Aog Granary Gc Dba Allied Construction Services, Hayes Concrete Services LLC, The Retreat At Oak Creek

Over $10,000


Source: Levelset Data

06/15/2021

Slow Payment Reported

Slow Payment Reported Against Allied Orion Group, HR Mechanical

Less than $1,000


Source: Levelset Data

06/15/2021

Slow Payment Reported

Slow Payment Reported Against Aog Granary Gc Dba Allied Construction Services, Hayes Concrete Services LLC

Over $5,000


Source: Levelset Data

05/14/2021

Slow Payment Reported

Slow Payment Reported Against Allied Orion Group, HR Mechanical

Less than $1,000


Source: Levelset Data

04/15/2021

Slow Payment Reported

Slow Payment Reported Against Allied Orion Group, HR Mechanical

Less than $1,000


Source: Levelset Data

03/15/2021

Slow Payment Reported

Slow Payment Reported Against Allied Orion Group, HR Mechanical

Less than $1,000


Source: Levelset Data

03/15/2021

Slow Payment Reported

Slow Payment Reported Against Aog Granary Gc Dba Allied Construction Services, Hayes Concrete Services LLC

Over $10,000


Source: Levelset Data

03/15/2021

Slow Payment Reported

Slow Payment Reported Against Allied Orion Group, P&M Fire Protection LLC

Over $5,000


Source: Levelset Data

02/12/2021

Slow Payment Reported

Slow Payment Reported Against Aog Granary Gc Dba Allied Construction Services, Hayes Concrete Services LLC

Over $10,000


Source: Levelset Data

01/15/2021

Slow Payment Reported

Slow Payment Reported Against Aog Granary Gc Dba Allied Construction Services, Hayes Concrete Services LLC

Over $10,000


Source: Levelset Data

01/15/2021

Slow Payment Reported

Slow Payment Reported Against HR Mechanical

Less than $1,000


Source: Levelset Data

12/15/2020

Slow Payment Reported

Slow Payment Reported Against Aog Granary Gc Dba Allied Construction Services, Hayes Concrete Services LLC

Over $10,000


Source: Levelset Data

12/15/2020

Slow Payment Reported

Slow Payment Reported Against HR Mechanical

Less than $1,000


Source: Levelset Data

12/15/2020

Slow Payment Reported

Slow Payment Reported Against P&M Fire Protection LLC

Over $60,000


Source: Levelset Data

11/13/2020

Slow Payment Reported

Slow Payment Reported Against HR Mechanical

Less than $1,000


Source: Levelset Data

11/13/2020

Slow Payment Reported

Slow Payment Reported Against P&M Fire Protection LLC

Over $60,000


Source: Levelset Data

10/15/2020

Slow Payment Reported

Slow Payment Reported Against HR Mechanical

Less than $1,000


Source: Levelset Data

10/15/2020

Slow Payment Reported

Slow Payment Reported Against Aog Granary Gc Dba Allied Construction Services, Hayes Concrete Services LLC

Over $1,000


Source: Levelset Data

10/15/2020

Slow Payment Reported

Slow Payment Reported Against P&M Fire Protection LLC

Over $60,000


Source: Levelset Data

09/15/2020

Slow Payment Reported

Slow Payment Reported Against HR Mechanical

Less than $1,000


Source: Levelset Data

08/14/2020

Slow Payment Reported

Slow Payment Reported Against HR Mechanical

Less than $1,000


Source: Levelset Data

05/15/2020

Slow Payment Reported

Slow Payment Reported Against Allied Orion Group, Tri Star Utilities

Over $10,000


Source: Levelset Data

Full Project Job Tree11

Companies


In this section, you can find all 11 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.

Lender

Unknown Company

Property Owner

Unknown Company

General Contractor (3)

Bonded by Unknown
Bonded by Unknown

Subcontractor (6)

Utilities Contractors
Subcontractor
Concrete Contractors
Drywall Contractors

Supplier (1)

LS
L&W Supply

Surety Companies

Unknown Company

Job Hierarchy


Lender

Unknown Company

Property Owner

Unknown Company

General Contractor (3)

View All
Bonded by Unknown

Subcontractor (6)

View All

Supplier (1)

LS
L&W Supply

Need cash to buy materials for this job?

Levelset will pay for your materials.

You pay us back up to 120 days later.

Apply Now