On this project at 1535 E Beltline Rd, Lancaster, TX 75146 there have been 11 permits filed, 6 preliminary notices exchanged, 9 lien waivers exchanged between companies and 0 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.
11
PERMITS FILED
6
PRELIMINARY NOTICES
9
LIEN WAIVERS
0
LIEN HISTORY
10/15/2024
Slow Payment Reported Against Hill & Wilkinson, Niagara Bottling LLC, Pillar Electric Group Lp, WHL Dallas 45 LLC
Over $5,000
Source: Levelset Data
09/13/2024
Slow Payment Reported Against CJ's Concrete Construction, Hill & Wilkinson
Over $10,000
Source: Levelset Data
08/15/2024
Slow Payment Reported Against G Bell Electric, Hill & Wilkinson
Over $5,000
Source: Levelset Data
08/01/2024
Source: ConstructionMonitor
07/31/2024
Source: ConstructionMonitor
07/29/2024
Source: ConstructionMonitor
07/15/2024
Slow Payment Reported Against CJ's Concrete Construction, Hill & Wilkinson
Over $10,000
Source: Levelset Data
06/14/2024
Slow Payment Reported Against Hill & Wilkinson, Rigid Constructors
Over $1,000
Source: Levelset Data
05/15/2024
Slow Payment Reported Against CJ's Concrete Construction, Hill & Wilkinson, Niagara Bottling LLC
Over $5,000
Source: Levelset Data
05/15/2024
Slow Payment Reported Against Hill & Wilkinson, Niagara Bottling LLC, Rigid Constructors
Over $10,000
Source: Levelset Data
05/15/2024
Slow Payment Reported Against Hill & Wilkinson, Rigid Constructors
Over $10,000
Source: Levelset Data
04/15/2024
Slow Payment Reported Against Hill & Wilkinson, Niagara Bottling LLC, Rigid Constructors
Over $5,000
Source: Levelset Data
04/15/2024
Slow Payment Reported Against Hill & Wilkinson, Rigid Constructors
Over $5,000
Source: Levelset Data
03/19/2024
Source: ConstructionMonitor
03/15/2024
Slow Payment Reported Against Hill & Wilkinson, Niagara Bottling LLC, Rigid Constructors
Over $10,000
Source: Levelset Data
03/15/2024
Slow Payment Reported Against Hill & Wilkinson, Rigid Constructors
Over $10,000
Source: Levelset Data
02/15/2024
Slow Payment Reported Against CJ's Concrete Construction, Hill & Wilkinson
Over $60,000
Source: Levelset Data
02/15/2024
Slow Payment Reported Against Hill & Wilkinson, Rigid Constructors
Over $5,000
Source: Levelset Data
02/15/2024
Slow Payment Reported Against SR Equipment Company
Over $10,000
Source: Levelset Data
02/15/2024
Slow Payment Reported Against Hatfield Acoustical & Drywall, Hill & Wilkinson
Over $5,000
Source: Levelset Data
01/29/2024
Lien threat sent to Choate Construction, Niagara Bottling LLC
Over $10,000
Source: Levelset Data
01/12/2024
Slow Payment Reported Against Hatfield Acoustical & Drywall
Over $5,000
Source: Levelset Data
12/15/2023
Slow Payment Reported Against Choate Construction, Niagara Bottling LLC
Over $60,000
Source: Levelset Data
12/15/2023
Slow Payment Reported Against CJ's Concrete Construction, Hill & Wilkinson, Niagara Bottling LLC
Over $1,000
Source: Levelset Data
12/15/2023
Slow Payment Reported Against SR Equipment Company
Over $10,000
Source: Levelset Data
11/27/2023
Source: ConstructionMonitor
11/15/2023
Slow Payment Reported Against Choate Construction, MIINC, L.P. Mechanical Contractors, Niagara Bottling LLC, WHL Dallas 45 LLC
Less than $1,000
Source: Levelset Data
10/13/2023
Slow Payment Reported Against Choate Construction, MIINC, L.P. Mechanical Contractors
Less than $1,000
Source: Levelset Data
10/13/2023
Slow Payment Reported Against CJ's Concrete Construction, Hill & Wilkinson
Over $60,000
Source: Levelset Data
08/15/2023
Slow Payment Reported Against Choate Construction, MIINC, L.P. Mechanical Contractors
Less than $1,000
Source: Levelset Data
07/14/2023
Slow Payment Reported Against Artemis Business Solutions, Choate Construction
Over $60,000
Source: Levelset Data
07/14/2023
Contractors listed on Permit: Southwest John Mcdonough Material Handling, WHL Dallas 45 LLC
# CSP-23-2564
$880,133
Source: ConstructionMonitor
06/15/2023
Slow Payment Reported Against Choate Construction, MIINC, L.P. Mechanical Contractors
Less than $1,000
Source: Levelset Data
05/15/2023
Slow Payment Reported Against Choate Construction, Moss Utilities, LLC
Over $5,000
Source: Levelset Data
05/15/2023
Slow Payment Reported Against Choate Construction, MIINC, L.P. Mechanical Contractors
Over $1,000
Source: Levelset Data
05/15/2023
Slow Payment Reported Against Artemis Business Solutions
Over $60,000
Source: Levelset Data
04/14/2023
Slow Payment Reported Against Artemis Business Solutions
Over $60,000
Source: Levelset Data
04/14/2023
Slow Payment Reported Against Choate Construction, MIINC, L.P. Mechanical Contractors
Less than $1,000
Source: Levelset Data
04/14/2023
Slow Payment Reported Against Choate Construction
Over $10,000
Source: Levelset Data
03/15/2023
Slow Payment Reported Against Artemis Business Solutions
Over $60,000
Source: Levelset Data
03/15/2023
Slow Payment Reported Against Choate Construction, Niagara Bottling LLC
Over $60,000
Source: Levelset Data
02/27/2023
Source: ConstructionMonitor
02/15/2023
Slow Payment Reported Against Artemis Business Solutions
Over $60,000
Source: Levelset Data
02/15/2023
Slow Payment Reported Against Choate Construction, Moss Utilities, LLC
Over $60,000
Source: Levelset Data
01/13/2023
Slow Payment Reported Against Choate Construction, Moss Utilities, LLC
Over $60,000
Source: Levelset Data
01/13/2023
Slow Payment Reported Against Artemis Business Solutions
Over $60,000
Source: Levelset Data
12/15/2022
Slow Payment Reported Against Choate Construction, Moss Utilities, LLC
Over $60,000
Source: Levelset Data
12/15/2022
Slow Payment Reported Against Artemis Business Solutions
Over $60,000
Source: Levelset Data
12/15/2022
Slow Payment Reported Against Choate Construction, MIINC, L.P. Mechanical Contractors
Over $1,000
Source: Levelset Data
10/20/2022
Source: ConstructionMonitor
10/14/2022
Slow Payment Reported Against Artemis Business Solutions
Over $60,000
Source: Levelset Data
10/14/2022
Slow Payment Reported Against Choate Construction, Moss Utilities, LLC
Over $10,000
Source: Levelset Data
09/28/2022
Source: ConstructionMonitor
09/22/2022
Source: ConstructionMonitor
09/15/2022
Slow Payment Reported Against Choate Construction, Moss Utilities, LLC
Over $5,000
Source: Levelset Data
09/15/2022
Slow Payment Reported Against Artemis Business Solutions
Over $60,000
Source: Levelset Data
08/15/2022
Slow Payment Reported Against Artemis Business Solutions
Over $60,000
Source: Levelset Data
07/15/2022
Slow Payment Reported Against Choate Construction, Moss Utilities, LLC
Over $60,000
Source: Levelset Data
07/15/2022
Slow Payment Reported Against Artemis Business Solutions
Over $60,000
Source: Levelset Data
07/15/2022
Slow Payment Reported Against Choate Construction, Moss Utilities, LLC
Over $60,000
Source: Levelset Data
06/15/2022
Slow Payment Reported Against Choate Construction, Moss Utilities, LLC
Over $60,000
Source: Levelset Data
05/13/2022
Slow Payment Reported Against Choate Construction, Moss Utilities, LLC
Over $60,000
Source: Levelset Data
Companies
In this section, you can find all 36 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.
Levelset will pay for your materials.