On this project at 5555 San Felipe St, Houston, TX 77056 there have been 5 permits filed, 2 preliminary notices exchanged, 0 lien waivers exchanged between companies and 6 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.
5
PERMITS FILED
2
PRELIMINARY NOTICES
0
LIEN WAIVERS
6
LIEN HISTORY
11/03/2023
Contractors listed on Permit: Melissa Campos, Mmp 555 San Felipe
# 23099381
$4,400,000
Source: ConstructionMonitor
04/13/2023
Source: ConstructionMonitor
04/08/2022
Source: ConstructionMonitor
01/13/2022
Lien filed by Polk Mechanical Co | Claimant directly hired by GC
Lien filed against Mmp 555 San Felipe, Structure Tone Southwest
GC listed on lien: Structure Tone Southwest
$6,725
Source: Levelset Data
12/15/2021
Slow Payment Reported Against Mmp 555 San Felipe, Structure Tone Southwest
Less than $1,000
Source: Levelset Data
10/15/2021
Slow Payment Reported Against Mmp 555 San Felipe, Structure Tone Southwest
Less than $1,000
Source: Levelset Data
10/14/2021
Lien filed by Polk Mechanical Co | Claimant directly hired by GC
Lien filed against Mmp 555 San Felipe, Structure Tone Southwest
GC listed on lien: Structure Tone Southwest
$71,404
Source: Levelset Data
09/15/2021
Slow Payment Reported Against Mmp 555 San Felipe, Structure Tone Southwest
Less than $1,000
Source: Levelset Data
09/15/2021
Slow Payment Reported Against Mmp 555 San Felipe, Structure Tone
Over $5,000
Source: Levelset Data
08/17/2021
Lien filed by Polk Mechanical Co | Claimant directly hired by GC
Lien filed against Mmp 555 San Felipe, Structure Tone Southwest
GC listed on lien: Structure Tone Southwest
$72,133
Source: Levelset Data
07/15/2021
Slow Payment Reported Against Mmp 555 San Felipe, Structure Tone
Over $5,000
Source: Levelset Data
07/15/2021
Slow Payment Reported Against Camarata Masonry Systems LTD, Sterling Infrastructure, Inc dba Sterling Construction Co.
Over $10,000
Source: Levelset Data
07/15/2021
Slow Payment Reported Against Mmp 555 San Felipe, Structure Tone Southwest
Less than $1,000
Source: Levelset Data
07/15/2021
Lien filed by Elliott Electric Supply, Inc
Lien filed against Mccune Electrical Services, Mmp 555 San Felipe, Structure Tone Southwest
GC listed on lien: Structure Tone Southwest
$37,373
Source: Levelset Data
06/15/2021
Slow Payment Reported Against Camarata Masonry Systems LTD, Sterling Infrastructure, Inc dba Sterling Construction Co.
Over $10,000
Source: Levelset Data
04/12/2021
Source: ConstructionMonitor
04/12/2021
Source: ConstructionMonitor
03/15/2021
Slow Payment Reported Against Polk Mechanical Co
Over $1,000
Source: Levelset Data
02/12/2021
Slow Payment Reported Against Mmp 555 San Felipe, Structure Tone Southwest
Less than $1,000
Source: Levelset Data
11/13/2020
Slow Payment Reported Against Mmp 555 San Felipe, Structure Tone Southwest
Less than $1,000
Source: Levelset Data
10/15/2020
Slow Payment Reported Against Camarata Masonry Systems LTD, Mmp 555 San Felipe, Sterling Infrastructure, Inc dba Sterling Construction Co.
Over $10,000
Source: Levelset Data
10/15/2020
Slow Payment Reported Against Mmp 555 San Felipe, Polk Mechanical Co, Structure Tone Southwest
Over $5,000
Source: Levelset Data
10/15/2020
Slow Payment Reported Against Polk Mechanical Co, Structure Tone Southwest
Over $5,000
Source: Levelset Data
09/15/2020
Slow Payment Reported Against Mmp 555 San Felipe, Structure Tone
Over $10,000
Source: Levelset Data
07/15/2020
Lien filed by Structural Concrete Systems LLC (TX) | Claimant directly hired by GC
Lien filed against Mmp 555 San Felipe, Structure Tone Southwest
GC listed on lien: Structure Tone Southwest
$106,876
Source: Levelset Data
06/12/2020
Lien filed by AmeriTex Imaging And Services LLC | Claimant directly hired by GC
Lien filed against Mmp 555 San Felipe, Structure Tone Southwest
GC listed on lien: Structure Tone Southwest
$43,746
Source: Levelset Data
05/15/2020
Slow Payment Reported Against Structure Tone
Less than $1,000
Source: Levelset Data
04/15/2020
Slow Payment Reported Against Mmp 555 San Felipe, Txp1929 Tx Project Management And Construction
Over $1,000
Source: Levelset Data
03/13/2020
Slow Payment Reported Against Burleson Construction (TX), Mmp 555 San Felipe, Superior Drywall Inc
Over $1,000
Source: Levelset Data
02/14/2020
Slow Payment Reported Against Mmp 555 San Felipe, Superior Drywall Inc
Over $1,000
Source: Levelset Data
02/14/2020
Slow Payment Reported Against Superior Drywall Inc
Over $1,000
Source: Levelset Data
01/15/2020
Slow Payment Reported Against Superior Drywall Inc
Over $1,000
Source: Levelset Data
10/16/2018
Slow Payment Reported Against Mmp 555 San Felipe, Superior Drywall Inc
Less than $1,000
Source: Levelset Data
04/24/2018
Slow Payment Reported Against Gallant Builders LLC, Spus6 Mot
Less than $1,000
Source: Levelset Data
04/24/2018
Slow Payment Reported Against Spus6 Mot
Less than $1,000
Source: Levelset Data