On this project at 5500 Queenston Blvd, Houston, TX 77084 there have been 7 permits filed, 0 preliminary notices exchanged, 0 lien waivers exchanged between companies and 0 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.
7
PERMITS FILED
0
PRELIMINARY NOTICES
0
LIEN WAIVERS
0
LIEN HISTORY
11/15/2024
Slow Payment Reported Against Capital Builders & Designers Inc., JB Pinnacle Group, Laxmi South Queenston, Nova Asset Management
Over $10,000
Source: Levelset Data
08/15/2024
Slow Payment Reported Against Andrade Concrete And Construction, Capital Builders & Designers Inc.
Over $10,000
Source: Levelset Data
05/15/2024
Slow Payment Reported Against Capital Builders & Designers Inc., Laxmi South Queenston
Over $1,000
Source: Levelset Data
05/15/2024
Slow Payment Reported Against Capital Builders & Designers Inc., Laxmi South Queenston
Less than $1,000
Source: Levelset Data
05/15/2024
Slow Payment Reported Against Capital Builders & Designers Inc., Laxmi South Queenston
Over $1,000
Source: Levelset Data
05/15/2024
Slow Payment Reported Against Capital Builders & Designers Inc., Laxmi South Queenston
Less than $1,000
Source: Levelset Data
05/15/2024
Slow Payment Reported Against Capital Builders & Designers Inc., Laxmi South Queenston
Less than $1,000
Source: Levelset Data
05/15/2024
Slow Payment Reported Against Capital Builders & Designers Inc., Laxmi South Queenston
Less than $1,000
Source: Levelset Data
02/15/2024
Slow Payment Reported Against Capital Builders & Designers Inc., Derby Drywall
Over $5,000
Source: Levelset Data
12/15/2023
Slow Payment Reported Against Capital Builders & Designers Inc., Derby Drywall
Over $10,000
Source: Levelset Data
12/15/2023
Slow Payment Reported Against Capital Builders & Designers Inc., Derby Drywall, Laxmi South Queenston
Over $10,000
Source: Levelset Data
11/15/2023
Slow Payment Reported Against Capital Builders & Designers Inc., Ebenezer Construction, Laxmi South Queenston
Over $1,000
Source: Levelset Data
11/15/2023
Slow Payment Reported Against Capital Builders & Designers Inc., JB Pinnacle Group, Laxmi South Queenston, Nova Asset Management
Over $5,000
Source: Levelset Data
11/15/2023
Slow Payment Reported Against Capital Builders & Designers Inc., Derby Drywall
Over $10,000
Source: Levelset Data
10/13/2023
Slow Payment Reported Against Capital Builders & Designers Inc., JB Pinnacle Group
Over $5,000
Source: Levelset Data
10/13/2023
Slow Payment Reported Against Capital Builders & Designers Inc., Ebenezer Construction
Over $10,000
Source: Levelset Data
09/15/2023
Slow Payment Reported Against Capital Builders & Designers Inc., Derby Drywall
Over $10,000
Source: Levelset Data
07/14/2023
Slow Payment Reported Against Andrade Concrete And Construction, Capital Builders & Designers Inc.
Over $10,000
Source: Levelset Data
05/15/2023
Slow Payment Reported Against Capital Builders & Designers Inc., Ebenezer Construction
Over $10,000
Source: Levelset Data
02/21/2022
Source: ConstructionMonitor
02/21/2022
Source: ConstructionMonitor
02/21/2022
Source: ConstructionMonitor
02/21/2022
Source: ConstructionMonitor
09/28/2021
Source: ConstructionMonitor
09/28/2021
Source: ConstructionMonitor
08/04/2021
Source: ConstructionMonitor
Companies
In this section, you can find all 7 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.