On this project at 16803 Katy Fwy, Houston, TX 77094 there have been 3 permits filed, 3 preliminary notices exchanged, 2 lien waivers exchanged between companies and 0 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.
3
PERMITS FILED
3
PRELIMINARY NOTICES
2
LIEN WAIVERS
0
LIEN HISTORY
05/15/2024
Slow Payment Reported Against CW Mechanical, SPD Construction LLC
Less than $1,000
Source: Levelset Data
05/15/2024
Slow Payment Reported Against Edco Air, SPD Construction LLC
Over $5,000
Source: Levelset Data
04/15/2024
Slow Payment Reported Against Edco Air, SPD Construction LLC
Over $5,000
Source: Levelset Data
03/15/2024
Slow Payment Reported Against CW Mechanical, SPD Construction LLC
Over $10,000
Source: Levelset Data
03/15/2024
Slow Payment Reported Against CW Mechanical, SPD Construction LLC
Less than $1,000
Source: Levelset Data
02/15/2024
Slow Payment Reported Against Edco Air, SPD Construction LLC
Over $5,000
Source: Levelset Data
02/15/2024
Slow Payment Reported Against BKCK, Ltd , CW Mechanical, SPD Construction LLC
Over $60,000
Source: Levelset Data
02/15/2024
Slow Payment Reported Against SPD Construction LLC
Over $60,000
Source: Levelset Data
02/15/2024
Slow Payment Reported Against CW Mechanical, SPD Construction LLC
Over $60,000
Source: Levelset Data
01/12/2024
Slow Payment Reported Against CW Mechanical, SPD Construction LLC
Over $60,000
Source: Levelset Data
12/15/2023
Slow Payment Reported Against SPD Construction LLC
Over $60,000
Source: Levelset Data
12/15/2023
Slow Payment Reported Against CW Mechanical, SPD Construction LLC
Less than $1,000
Source: Levelset Data
12/15/2023
Slow Payment Reported Against CW Mechanical, SPD Construction LLC
Over $60,000
Source: Levelset Data
12/15/2023
Slow Payment Reported Against Edco Air, SPD Construction LLC
Over $1,000
Source: Levelset Data
11/15/2023
Slow Payment Reported Against Edco Air, SPD Construction LLC
Over $1,000
Source: Levelset Data
11/15/2023
Slow Payment Reported Against BKCK, Ltd , Edco Air, SPD Construction LLC
Over $5,000
Source: Levelset Data
11/15/2023
Slow Payment Reported Against CW Mechanical, SPD Construction LLC
Over $60,000
Source: Levelset Data
11/15/2023
Slow Payment Reported Against SPD Construction LLC
Over $60,000
Source: Levelset Data
11/15/2023
Slow Payment Reported Against Edco Air, SPD Construction LLC
Over $5,000
Source: Levelset Data
11/15/2023
Slow Payment Reported Against BKCK, Ltd , Edco Air, SPD Construction LLC
Over $1,000
Source: Levelset Data
10/13/2023
Slow Payment Reported Against CW Mechanical, SPD Construction LLC
Over $10,000
Source: Levelset Data
10/13/2023
Slow Payment Reported Against Edco Air, SPD Construction LLC
Over $1,000
Source: Levelset Data
10/13/2023
Slow Payment Reported Against CW Mechanical, SPD Construction LLC
Over $60,000
Source: Levelset Data
10/13/2023
Slow Payment Reported Against SPD Construction LLC
Over $60,000
Source: Levelset Data
10/13/2023
Slow Payment Reported Against Edco Air, SPD Construction LLC
Over $1,000
Source: Levelset Data
09/15/2023
Slow Payment Reported Against CW Mechanical, SPD Construction LLC
Over $10,000
Source: Levelset Data
09/15/2023
Slow Payment Reported Against CW Mechanical, SPD Construction LLC
Less than $1,000
Source: Levelset Data
08/15/2023
Slow Payment Reported Against CW Mechanical, SPD Construction LLC
Less than $1,000
Source: Levelset Data
08/15/2023
Slow Payment Reported Against CW Mechanical, SPD Construction LLC
Over $60,000
Source: Levelset Data
08/15/2023
Slow Payment Reported Against Edco Air, SPD Construction LLC
Over $1,000
Source: Levelset Data
08/15/2023
Slow Payment Reported Against SPD Construction LLC
Over $60,000
Source: Levelset Data
07/14/2023
Slow Payment Reported Against CW Mechanical, SPD Construction LLC
Over $60,000
Source: Levelset Data
07/14/2023
Slow Payment Reported Against Edco Air
Over $1,000
Source: Levelset Data
07/14/2023
Slow Payment Reported Against BKCK, Ltd
Over $10,000
Source: Levelset Data
06/25/2023
Source: ConstructionMonitor
06/15/2023
Slow Payment Reported Against BKCK, Ltd
Over $60,000
Source: Levelset Data
06/15/2023
Slow Payment Reported Against CW Mechanical, SPD Construction LLC
Less than $1,000
Source: Levelset Data
06/15/2023
Slow Payment Reported Against CW Mechanical, SPD Construction LLC
Over $60,000
Source: Levelset Data
05/16/2023
Slow Payment Reported Against Advanced Glass Solutions
Less than $1,000
Source: Levelset Data
05/15/2023
Slow Payment Reported Against BKCK, Ltd
Over $60,000
Source: Levelset Data
04/14/2023
Slow Payment Reported Against CW Mechanical, SPD Construction LLC
Over $10,000
Source: Levelset Data
04/14/2023
Slow Payment Reported Against BKCK, Ltd
Over $60,000
Source: Levelset Data
01/11/2023
Source: ConstructionMonitor
12/01/2022
Source: ConstructionMonitor
Companies
In this section, you can find all 17 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.
Levelset will pay for your materials.
You pay us back up to 120 days later.