Menu
A map for the project located in Houston, Texas.
Commercial Construction Project at

14710 JFK BOULEVARD

Houston, TX 77032

  • Last known event: 08/15/2023
  • First known event: 01/31/2020
LevelsetProjectsTexasHouston14710 JFK BOULEVARD

Property Details


PROJECT TYPE

Commercial

PROPERTY OWNER

Liberty Property LP

CITY

Houston

Key Facts

The project located at 14710 JFK BOULEVARD, Houston, Texas 77032 has had 45 companies do work over the last 5 years.

Lien History

There has been 6 liens at this address with a reported total value of $283,347.68.

Project History


On this project at 14710 JFK BOULEVARD, Houston, TX 77032 there have been 1 permit filed, 2 preliminary notices exchanged, 1 lien waiver exchanged between companies and 6 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.

Overview

1

PERMITS FILED

2

PRELIMINARY NOTICES

1

LIEN WAIVERS

6

LIEN HISTORY

Payment Timeline

08/15/2023

Slow Payment Reported

Slow Payment Reported Against CFM Mechanical, Farmer Construction, Interwood Distribution Center Lp

Over $1,000


Source: Levelset Data

07/14/2023

Slow Payment Reported

Slow Payment Reported Against CFM Mechanical, Farmer Construction

Over $1,000


Source: Levelset Data

05/15/2023

Slow Payment Reported

Slow Payment Reported Against Farmer Construction, O S Interior Systems

Over $1,000


Source: Levelset Data

03/15/2022

Slow Payment Reported

Slow Payment Reported Against CFM Mechanical, Farmer Construction, Interwood Distribution Center Lp

Over $10,000


Source: Levelset Data

03/15/2022

Slow Payment Reported

Slow Payment Reported Against CFM Mechanical, Farmer Construction

Over $10,000


Source: Levelset Data

02/15/2022

Slow Payment Reported

Slow Payment Reported Against Farmer Construction, Strategic Builders LLC (TX)

Over $10,000


Source: Levelset Data

02/15/2022

Slow Payment Reported

Slow Payment Reported Against CFM Mechanical, Farmer Construction

Over $10,000


Source: Levelset Data

12/15/2021

Slow Payment Reported

Slow Payment Reported Against CFM Mechanical, Farmer Construction

Over $10,000


Source: Levelset Data

11/15/2021

Slow Payment Reported

Slow Payment Reported Against Eagles Brothers Constructors, Farmer Construction

Over $1,000


Source: Levelset Data

10/15/2021

Slow Payment Reported

Slow Payment Reported Against Eagles Brothers Constructors, Farmer Construction

Over $10,000


Source: Levelset Data

10/13/2021

Slow Payment Reported

Slow Payment Reported Against Eagles Brothers Constructors, Farmer Construction

Over $10,000


Source: Levelset Data

09/15/2021

Slow Payment Reported

Slow Payment Reported Against Farmer Construction, Interwood Distribution Center Lp

Over $5,000


Source: Levelset Data

09/15/2021

Slow Payment Reported

Slow Payment Reported Against Eagles Brothers Constructors, Farmer Construction, Interwood Distribution Center Lp

Over $10,000


Source: Levelset Data

09/15/2021

Slow Payment Reported

Slow Payment Reported Against Eagles Brothers Constructors, Farmer Construction

Over $10,000


Source: Levelset Data

09/15/2021

Slow Payment Reported

Slow Payment Reported Against CFM Mechanical, Farmer Construction

Over $5,000


Source: Levelset Data

09/15/2021

Slow Payment Reported

Slow Payment Reported Against Eagles Brothers Constructors

Over $10,000


Source: Levelset Data

09/15/2021

Slow Payment Reported

Slow Payment Reported Against CFM Mechanical, Farmer Construction, Interwood Distribution Center Lp

Over $5,000


Source: Levelset Data

09/15/2021

Slow Payment Reported

Slow Payment Reported Against Eagles Brothers Constructors, Farmer Construction, Interwood Distribution Center Lp

Over $10,000


Source: Levelset Data

09/14/2021

Slow Payment Reported

Slow Payment Reported Against Interwood Distribution Center Lp

Less than $1,000


Source: Levelset Data

08/13/2021

Slow Payment Reported

Slow Payment Reported Against Eagles Brothers Constructors, Farmer Construction

Over $10,000


Source: Levelset Data

08/13/2021

Slow Payment Reported

Slow Payment Reported Against CFM Mechanical, Farmer Construction

Over $5,000


Source: Levelset Data

08/13/2021

Slow Payment Reported

Slow Payment Reported Against CFM Mechanical, Farmer Construction, Interwood Distribution Center Lp

Over $5,000


Source: Levelset Data

07/15/2021

Slow Payment Reported

Slow Payment Reported Against Eagles Brothers Constructors, Farmer Construction

Over $10,000


Source: Levelset Data

07/14/2021

Slow Payment Reported

Slow Payment Reported Against Farmer Construction, Interwood Distribution Center Lp

Less than $1,000


Source: Levelset Data

06/15/2021

Slow Payment Reported

Slow Payment Reported Against Eagles Brothers Constructors, Farmer Construction

Over $5,000


Source: Levelset Data

05/14/2021

Slow Payment Reported

Slow Payment Reported Against Eagles Brothers Constructors, Farmer Construction

Over $10,000


Source: Levelset Data

04/29/2021

Mechanics Lien Filed

Lien filed by Sendero Industries | Claimant directly hired by GC

Lien filed against Arch-Con Corporation, Frontier Equity, Interwood Distribution Center Lp

GC listed on lien: Arch-Con Corporation

$147,533


Source: Levelset Data

04/14/2021

Mechanics Lien Filed

Lien filed by OGD Equipment Company | Claimant directly hired by GC

Lien filed against Arch-Con Corporation, Interwood Distribution Center Lp

GC listed on lien: Arch-Con Corporation

$6,252


Source: Levelset Data

03/19/2021

Slow Payment Reported

Slow Payment Reported Against Arch-Con Corporation, Frontier Equity, Interwood Distribution Center Lp

Over $60,000


Source: Levelset Data

03/15/2021

Slow Payment Reported

Slow Payment Reported Against Farmer Construction, Strategic Builders LLC (TX)

Over $10,000


Source: Levelset Data

03/15/2021

Slow Payment Reported

Slow Payment Reported Against Arch-Con Corporation

Over $5,000


Source: Levelset Data

03/12/2021

Mechanics Lien Filed

Lien filed by ParkUSA

Lien filed against Arch-Con Corporation, Frontier Equity, Interwood Distribution Center Lp

GC listed on lien: Arch-Con Corporation

$12,402


Source: Levelset Data

02/12/2021

Slow Payment Reported

Slow Payment Reported Against Arch-Con Corporation, Frontier Equity, Sendero Industries

Over $10,000


Source: Levelset Data

01/15/2021

Slow Payment Reported

Slow Payment Reported Against Arch-Con Corporation, Sendero Industries

Over $10,000


Source: Levelset Data

01/15/2021

Mechanics Lien Filed

Lien filed by Houston Heavy Machinery

Lien filed against Arch-Con Corporation, Frontier Equity, Interwood Distribution Center Lp

GC listed on lien: Arch-Con Corporation

$59,616


Source: Levelset Data

01/14/2021

Slow Payment Reported

Slow Payment Reported Against 950 Berkshire Ln Ste 900, Interwood Distribution Center Lp, Sendero Industries

Over $60,000


Source: Levelset Data

12/15/2020

Slow Payment Reported

Slow Payment Reported Against Arch-Con Corporation, Sendero Industries

Over $1,000


Source: Levelset Data

12/15/2020

Slow Payment Reported

Slow Payment Reported Against Arch-Con Corporation, Frontier Equity, Interwood Distribution Center Lp

Over $60,000


Source: Levelset Data

11/13/2020

Slow Payment Reported

Slow Payment Reported Against Arch-Con Corporation, Classic Construction Company

Over $10,000


Source: Levelset Data

11/13/2020

Slow Payment Reported

Slow Payment Reported Against Arch-Con Corporation, Frontier Equity, Interwood Distribution Center Lp

Over $60,000


Source: Levelset Data

10/15/2020

Slow Payment Reported

Slow Payment Reported Against 950 Berkshire Ln Ste 900, Interwood Distribution Center Lp, Sendero Industries

Over $10,000


Source: Levelset Data

10/07/2020

Lien Threatened

Lien threat sent to Sendero Industries

Over $10,000


Source: Levelset Data

09/15/2020

Slow Payment Reported

Slow Payment Reported Against Arch-Con Corporation, Interwood Distribution Center Lp, Sendero Industries

Over $1,000


Source: Levelset Data

09/15/2020

Slow Payment Reported

Slow Payment Reported Against 950 Berkshire Ln Ste 900, Sendero Industries

Over $10,000


Source: Levelset Data

09/14/2020

Mechanics Lien Filed

Lien filed by Doggett

Lien filed against Liberty Limited Partnership, Liberty Property LP, Sendero Industries

Property Owner: Liberty Property LP

$17,928


Source: Levelset Data

08/14/2020

Slow Payment Reported

Slow Payment Reported Against Arch-Con Corporation, Sendero Industries

Over $1,000


Source: Levelset Data

07/17/2020

Mechanics Lien Filed

Lien filed by N C Pipe

Lien filed against Frontier Equity, Sendero Industries

$39,618


Source: Levelset Data

01/31/2020

Permit Filed

Permit Approved 

Contractors listed on Permit: Arch-Con Corporation

# 19109242

$3,388,010


Permit Description

High Pile Shell Building


Source: ConstructionMonitor

Full Project Job Tree45

Companies


In this section, you can find all 45 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.

Lender

Unknown Company

Property Owner

Bonded by Unknown

General Contractor (5)

Bonded by American Contractors Indemnity Company
Bonded by American Contractors Indemnity Company, State National Insurance Company Inc
Bonded by Unknown
Bonded by Unknown

Subcontractor (20)

Subcontractor
Painters
Subcontractor

Supplier (19)

Surety Companies

Unknown Company

Job Hierarchy


Lender

Unknown Company

Property Owner

Bonded by Unknown

General Contractor (5)

View All
Bonded by American Contractors Indemnity Company

Subcontractor (20)

View All
Subcontractor

Supplier (19)

View All

Need cash to buy materials for this job?

Levelset will pay for your materials.

You pay us back up to 120 days later.

Apply Now