Property Details


PROJECT TYPE

Residential

PROPERTY OWNER

Unknown

CITY

Houston

Key Facts

The project located at 12121 Greenspoint Dr, Houston, Texas 77060 has had 34 companies do work over the last 4 years.

Lien History

There has been 18 liens at this address with a reported total value of $2,584,318.25.

Project History


On this project at 12121 Greenspoint Dr, Houston, TX 77060 there have been 2 permits filed, 4 preliminary notices exchanged, 0 lien waivers exchanged between companies and 18 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.

Overview

2

PERMITS FILED

4

PRELIMINARY NOTICES

0

LIEN WAIVERS

18

LIEN HISTORY

Payment Timeline

09/13/2024

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Thznh, Txznh

Over $10,000


Source: Levelset Data

09/13/2024

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Thznh, Txznh

Over $10,000


Source: Levelset Data

09/11/2024

Mechanics Lien Filed

Lien filed by Morsco

Lien filed against Gilbert Co, Hudson Construction Company, Txznh, Zg Companies

GC listed on lien: Hudson Construction Company

$39,005


Source: Levelset Data

08/15/2024

Slow Payment Reported

Slow Payment Reported Against Gilbert Co, Hudson Construction Company, Txznh, Zg Companies

Less than $1,000


Source: Levelset Data

07/25/2024

Lien Threatened

Lien threat sent to Hudson Construction Company, Txznh

Over $60,000


Source: Levelset Data

07/15/2024

Slow Payment Reported

Slow Payment Reported Against Gilbert Co, Hudson Construction Company

Less than $1,000


Source: Levelset Data

06/17/2024

Mechanics Lien Filed

Lien filed by Morsco

Lien filed against Hudson Construction Company, Masram Mechanical, Txznh

GC listed on lien: Hudson Construction Company

$6,142


Source: Levelset Data

06/14/2024

Slow Payment Reported

Slow Payment Reported Against Gilbert Co, Hudson Construction Company, Txznh, Zg Companies

Less than $1,000


Source: Levelset Data

06/14/2024

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Masram Mechanical, Txznh

Less than $1,000


Source: Levelset Data

05/15/2024

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Masram Mechanical, Txznh

Less than $1,000


Source: Levelset Data

05/15/2024

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Masram Mechanical

Less than $1,000


Source: Levelset Data

05/15/2024

Slow Payment Reported

Slow Payment Reported Against Gilbert Co, Hudson Construction Company

Less than $1,000


Source: Levelset Data

05/15/2024

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Txznh, Zgnhp2

Over $1,000


Source: Levelset Data

05/15/2024

Slow Payment Reported

Slow Payment Reported Against Gilbert Co, Hudson Construction Company, Txznh, Zg Companies

Less than $1,000


Source: Levelset Data

05/14/2024

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Masram Mechanical, Txznh

Over $10,000


Source: Levelset Data

04/18/2024

Mechanics Lien Filed

Lien filed by Brian Rodel | Claimant directly hired by GC

Lien filed against , Hudson Construction Company

GC listed on lien: Hudson Construction Company

$350


Source: Levelset Data

04/15/2024

Mechanics Lien Filed

Lien filed by Gulf Coast Flooring & Services | Claimant directly hired by GC

Lien filed against Hudson Construction Company, Txznh

GC listed on lien: Hudson Construction Company

$96,559


Source: Levelset Data

04/15/2024

Mechanics Lien Filed

Lien filed by Gilbert Plumbing Company LP | Claimant directly hired by GC

Lien filed against Hudson Construction Company, Txznh

GC listed on lien: Hudson Construction Company

$111,982


Source: Levelset Data

04/15/2024

Mechanics Lien Filed

Lien filed by Commercial Services of Corey Construction Commercial Services | Claimant directly hired by GC

Lien filed against Hudson Construction Company, Txznh

GC listed on lien: Hudson Construction Company

$86,418


Source: Levelset Data

04/15/2024

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Txznh, Zgnhp2

Over $1,000


Source: Levelset Data

04/15/2024

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Masram Mechanical, Txznh

Over $5,000


Source: Levelset Data

04/15/2024

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Masram Mechanical

Less than $1,000


Source: Levelset Data

04/15/2024

Slow Payment Reported

Slow Payment Reported Against Gilbert Co, Hudson Construction Company

Less than $1,000


Source: Levelset Data

04/15/2024

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Txznh

Over $5,000


Source: Levelset Data

04/12/2024

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Masram Mechanical

Over $10,000


Source: Levelset Data

04/12/2024

Lien Threatened

Lien threat sent to Hudson Construction Company, Masram Mechanical, Txznh

Over $5,000


Source: Levelset Data

04/12/2024

Slow Payment Reported

Slow Payment Reported Against Masram Mechanical, Txznh

Over $10,000


Source: Levelset Data

04/05/2024

Mechanics Lien Filed

Lien filed by TK ELEVATOR CORPORATION | Claimant directly hired by GC

Lien filed against Hudson Construction Company, Txznh

GC listed on lien: Hudson Construction Company

$130,199


Source: Levelset Data

03/22/2024

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Txznh

Over $60,000


Source: Levelset Data

03/19/2024

Lien Threatened

Lien threat sent to Hudson Construction Company, Txznh

Over $60,000


Source: Levelset Data

03/15/2024

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Txznh

Over $5,000


Source: Levelset Data

03/15/2024

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Masram Mechanical, Txznh

Over $5,000


Source: Levelset Data

03/15/2024

Mechanics Lien Filed

Lien filed by Iriaquez Ironworks, LLC | Claimant directly hired by GC

Lien filed against Hudson Construction Company, Txznh

GC listed on lien: Hudson Construction Company

$16,816


Source: Levelset Data

03/15/2024

Mechanics Lien Filed

Lien filed by Advanced Concrete Surfaces | Claimant directly hired by GC

Lien filed against Hudson Construction Company, Txznh

GC listed on lien: Hudson Construction Company

$5,221


Source: Levelset Data

03/15/2024

Slow Payment Reported

Slow Payment Reported Against Gilbert Co, Hudson Construction Company, Txznh, Zg Companies

Less than $1,000


Source: Levelset Data

03/15/2024

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, TLC Construction Contract Services, Txznh

Over $5,000


Source: Levelset Data

03/15/2024

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Masram Mechanical

Over $5,000


Source: Levelset Data

03/14/2024

Lien Threatened


Source: Levelset Data

03/14/2024

Mechanics Lien Filed

Lien filed by J Torres Construction | Claimant directly hired by GC

Lien filed against Hudson Construction Company, Txznh

GC listed on lien: Hudson Construction Company

$521,031


Source: Levelset Data

03/13/2024

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Sendero Industries, Txznh

Over $60,000


Source: Levelset Data

03/13/2024

Mechanics Lien Filed

Lien filed by TLC Construction Contract Services | Claimant directly hired by GC

Lien filed against Hudson Construction Company, Txznh

GC listed on lien: TLC Construction Contract Services

$238,208


Source: Levelset Data

03/13/2024

Slow Payment Reported

Slow Payment Reported Against Masram Mechanical, Txznh

Over $10,000


Source: Levelset Data

03/13/2024

Slow Payment Reported

Slow Payment Reported Against Masram Mechanical

Over $10,000


Source: Levelset Data

02/15/2024

Slow Payment Reported

Slow Payment Reported Against Gilbert Co, Hudson Construction Company, Txznh, Zg Companies

Less than $1,000


Source: Levelset Data

02/15/2024

Slow Payment Reported

Slow Payment Reported Against Gilbert Co, Hudson Construction Company

Less than $1,000


Source: Levelset Data

02/15/2024

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Masram Mechanical

Over $5,000


Source: Levelset Data

02/09/2024

Slow Payment Reported

Slow Payment Reported Against Masram Mechanical

Over $10,000


Source: Levelset Data

02/09/2024

Slow Payment Reported

Slow Payment Reported Against Masram Mechanical, Txznh

Over $10,000


Source: Levelset Data

02/08/2024

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Sendero Industries, Txznh

Over $60,000


Source: Levelset Data

02/08/2024

Slow Payment Reported

Slow Payment Reported Against Sendero Industries

Over $60,000


Source: Levelset Data

01/18/2024

Mechanics Lien Filed

Lien filed by Corey Construction | Claimant directly hired by GC

Lien filed against Hudson Construction Company, Txznh

GC listed on lien: Hudson Construction Company

$214,996


Source: Levelset Data

01/12/2024

Slow Payment Reported

Slow Payment Reported Against Sendero Industries

Over $60,000


Source: Levelset Data

01/12/2024

Slow Payment Reported

Slow Payment Reported Against Gilbert Co, Hudson Construction Company, Txznh, Zg Companies

Less than $1,000


Source: Levelset Data

01/12/2024

Slow Payment Reported

Slow Payment Reported Against Masram Mechanical

Over $10,000


Source: Levelset Data

01/12/2024

Slow Payment Reported

Slow Payment Reported Against Gilbert Co, Hudson Construction Company

Less than $1,000


Source: Levelset Data

01/12/2024

Mechanics Lien Filed

Lien filed by Advanced Concrete Surfaces

Lien filed against Hudson Construction Company, Txznh

GC listed on lien: Hudson Construction Company

$10,973


Source: Levelset Data

01/12/2024

Mechanics Lien Filed

Lien filed by J Torres Construction | Claimant directly hired by GC

Lien filed against Hudson Construction Company, Txznh

GC listed on lien: Hudson Construction Company

$464,605


Source: Levelset Data

01/11/2024

Mechanics Lien Filed

Lien filed by Morrell Masonry Supply

Lien filed against Hudson Construction Company, Imprimis Construction, Txznh

GC listed on lien: Hudson Construction Company

$54,683


Source: Levelset Data

12/15/2023

Slow Payment Reported

Slow Payment Reported Against Gilbert Co, Hudson Construction Company, Txznh, Zg Companies

Less than $1,000


Source: Levelset Data

12/15/2023

Slow Payment Reported

Slow Payment Reported Against Gilbert Co, Hudson Construction Company

Less than $1,000


Source: Levelset Data

11/20/2023

Mechanics Lien Filed

Lien filed by Cabinet Edge | Claimant directly hired by GC

Lien filed against Hudson Construction Company, Txznh

GC listed on lien: Hudson Construction Company

$251,966


Source: Levelset Data

11/15/2023

Mechanics Lien Filed

Lien filed by TLC Construction Contract Services | Claimant directly hired by GC

Lien filed against Hudson Construction Company, Txznh

GC listed on lien: TLC Construction Contract Services

$322,662


Source: Levelset Data

11/15/2023

Slow Payment Reported

Slow Payment Reported Against Zodega Landscape Service, Zodega Landscaping

Over $10,000


Source: Levelset Data

11/15/2023

Slow Payment Reported

Slow Payment Reported Against Gilbert Co, Hudson Construction Company

Less than $1,000


Source: Levelset Data

11/15/2023

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Masram Mechanical, Txznh

Over $60,000


Source: Levelset Data

11/14/2023

Slow Payment Reported

Slow Payment Reported Against Masram Mechanical

Over $10,000


Source: Levelset Data

10/13/2023

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Masram Mechanical

Less than $1,000


Source: Levelset Data

10/13/2023

Slow Payment Reported

Slow Payment Reported Against Masram Mechanical

Over $10,000


Source: Levelset Data

10/13/2023

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Masram Mechanical, Txznh

Over $60,000


Source: Levelset Data

10/13/2023

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Masram Mechanical

Over $60,000


Source: Levelset Data

10/13/2023

Slow Payment Reported

Slow Payment Reported Against Gilbert Co, Hudson Construction Company

Less than $1,000


Source: Levelset Data

09/21/2023

Mechanics Lien Filed

Lien filed by Mickie Service Compny

Lien filed against Hudson Construction Company

GC listed on lien: Hudson Construction Company

$12,500


Source: Levelset Data

09/15/2023

Slow Payment Reported

Slow Payment Reported Against Gilbert Co, Hudson Construction Company

Less than $1,000


Source: Levelset Data

09/15/2023

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Masram Mechanical, Txznh

Less than $1,000


Source: Levelset Data

09/15/2023

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Masram Mechanical

Less than $1,000


Source: Levelset Data

09/15/2023

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Masram Mechanical

Over $60,000


Source: Levelset Data

08/15/2023

Slow Payment Reported

Slow Payment Reported Against Gilbert Co, Hudson Construction Company

Less than $1,000


Source: Levelset Data

08/15/2023

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Masram Mechanical

Less than $1,000


Source: Levelset Data

05/15/2023

Slow Payment Reported

Slow Payment Reported Against Gilbert Co, Hudson Construction Company

Less than $1,000


Source: Levelset Data

05/15/2023

Slow Payment Reported

Slow Payment Reported Against Hudson Construction Company, Masram Mechanical

Less than $1,000


Source: Levelset Data

04/17/2023

Slow Payment Reported

Slow Payment Reported Against Masram Mechanical

Over $10,000


Source: Levelset Data

04/14/2023

Slow Payment Reported

Slow Payment Reported Against Gilbert Co, Hudson Construction Company

Less than $1,000


Source: Levelset Data

03/15/2023

Slow Payment Reported

Slow Payment Reported Against Gilbert Co, Hudson Construction Company

Less than $1,000


Source: Levelset Data

08/15/2022

Slow Payment Reported

Slow Payment Reported Against Gilbert Co, Hudson Construction Company

Less than $1,000


Source: Levelset Data

07/15/2022

Slow Payment Reported

Slow Payment Reported Against Gilbert Co, Hudson Construction Company

Less than $1,000


Source: Levelset Data

07/21/2021

Permit Filed

Permit Approved 

Contractors listed on Permit: Lee Zieben

# 21069543

$65,932


Source: ConstructionMonitor

07/21/2021

Permit Filed

Permit Approved 

Contractors listed on Permit: Lee Zieben, Txznh

# 21043866

$1,278,050


Source: ConstructionMonitor

Full Project Job Tree34

Companies


In this section, you can find all 34 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.

Lender

Unknown Company

Property Owner

Unknown Company

General Contractor (3)

Bonded by Berkeley Insurance Company
Bonded by Berkeley Insurance Company
Bonded by Berkeley Insurance Company

Subcontractor (17)

Concrete Contractors
Subcontractor

Surety Companies (1)

Job Hierarchy


Lender

Unknown Company

Property Owner

Unknown Company

General Contractor (3)

View All
Bonded by Berkeley Insurance Company

Subcontractor (17)

View All

Supplier (13)

View All

Need cash to buy materials for this job?

Levelset will pay for your materials.

You pay us back up to 120 days later.

Apply Now