On this project at 6414 CR 1612, Gregory, TX 78359 there have been 0 permits filed, 2 preliminary notices exchanged, 0 lien waivers exchanged between companies and 1 lien filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.
0
PERMITS FILED
2
PRELIMINARY NOTICES
0
LIEN WAIVERS
1
LIEN HISTORY
12/15/2022
Slow Payment Reported Against Bay LTD, GCGV Asset Holding LLC, Zachry Group
Over $60,000
Source: Levelset Data
04/15/2022
Slow Payment Reported Against Coastal LLC, GCGV Asset Holding LLC
Over $1,000
Source: Levelset Data
03/15/2022
Slow Payment Reported Against Coastal LLC, GCGV Asset Holding LLC
Over $1,000
Source: Levelset Data
03/15/2022
Slow Payment Reported Against Coastal LLC
Over $1,000
Source: Levelset Data
02/15/2022
Slow Payment Reported Against Coastal LLC
Over $1,000
Source: Levelset Data
11/15/2021
Slow Payment Reported Against GCGV Asset Holding LLC, Turner Industries
Over $10,000
Source: Levelset Data
10/12/2021
Slow Payment Reported Against Baker Concrete Construction, GCGV Asset Holding LLC
Over $60,000
Source: Levelset Data
10/12/2021
Lien threat sent to Baker Concrete Construction, GCGV Asset Holding LLC
Over $60,000
Source: Levelset Data
07/21/2021
Slow Payment Reported Against Baker Concrete Construction, GCGV Asset Holding LLC
Over $60,000
Source: Levelset Data
07/19/2021
Lien threat sent to ATS Industrial dba ATS Construction
Over $1,000
Source: Levelset Data
09/15/2020
Slow Payment Reported Against Amec Foster Wheeler, Exxon Mobil, GCGV Asset Holding LLC, Wood Plc
Over $1,000
Source: Levelset Data
09/15/2020
Slow Payment Reported Against Turner Industries, Wood Plc
Over $60,000
Source: Levelset Data
09/15/2020
Slow Payment Reported Against Caldwell Tanks Inc., GCGV Asset Holding LLC, Specialty Industrial, Wood Plc
Over $10,000
Source: Levelset Data
08/14/2020
Slow Payment Reported Against Amec Foster Wheeler, Wood Plc
Over $1,000
Source: Levelset Data
08/14/2020
Slow Payment Reported Against Caldwell Tanks Inc., GCGV Asset Holding LLC, Specialty Industrial, Wood Plc
Over $10,000
Source: Levelset Data
08/14/2020
Slow Payment Reported Against Caldwell Tanks Inc., Specialty Industrial, Wood Plc
Over $10,000
Source: Levelset Data
07/15/2020
Slow Payment Reported Against Caldwell Tanks Inc., Specialty Industrial, Wood Plc
Over $10,000
Source: Levelset Data
07/15/2020
Slow Payment Reported Against Caldwell Tanks Inc., GCGV Asset Holding LLC, Specialty Industrial, Wood Plc
Over $10,000
Source: Levelset Data
06/15/2020
Slow Payment Reported Against Caldwell Tanks Inc., Specialty Industrial, Wood Plc
Over $10,000
Source: Levelset Data
06/15/2020
Slow Payment Reported Against Caldwell Tanks Inc., GCGV Asset Holding LLC, Specialty Industrial, Wood Plc
Over $10,000
Source: Levelset Data
06/15/2020
Slow Payment Reported Against Amec Foster Wheeler, Wood Plc
Over $1,000
Source: Levelset Data
05/15/2020
Slow Payment Reported Against Caldwell Tanks Inc., GCGV Asset Holding LLC, Specialty Industrial, Wood Plc
Over $10,000
Source: Levelset Data
05/15/2020
Slow Payment Reported Against Caldwell Tanks Inc., Specialty Industrial, Wood Plc
Over $10,000
Source: Levelset Data
03/13/2020
Slow Payment Reported Against Amec Foster Wheeler, Wood Plc
Over $5,000
Source: Levelset Data
03/03/2020
Lien filed by PPI Engineering And Construction Services
Lien filed against GCGV Asset Holding LLC, Wood Plc
GC listed on lien: Wood Plc
Property Owner: GCGV Asset Holding LLC
$132,829
Source: Levelset Data
02/18/2020
Slow Payment Reported Against Baker Concrete Construction, GCGV Asset Holding LLC, Wood Plc
Over $60,000
Source: Levelset Data
02/14/2020
Slow Payment Reported Against Amec Foster Wheeler, Exxon Mobil, Wood Plc
Over $5,000
Source: Levelset Data
02/14/2020
Slow Payment Reported Against Amec Foster Wheeler, Wood Plc
Over $5,000
Source: Levelset Data
01/15/2020
Slow Payment Reported Against Amec Foster Wheeler, Exxon Mobil, Wood Plc
Over $5,000
Source: Levelset Data
01/15/2020
Slow Payment Reported Against Amec Foster Wheeler, Wood Plc
Over $5,000
Source: Levelset Data
12/13/2019
Slow Payment Reported Against Amec Foster Wheeler, Wood Plc
Over $5,000
Source: Levelset Data
12/11/2019
Lien threat sent to Baker Concrete Construction
Over $60,000
Source: Levelset Data
12/09/2019
Slow Payment Reported Against Baker Concrete Construction, Wood Plc
Over $60,000
Source: Levelset Data
10/15/2019
Slow Payment Reported Against Amec Foster Wheeler, Wood Plc
Over $5,000
Source: Levelset Data
09/13/2019
Slow Payment Reported Against Amec Foster Wheeler, Wood Plc
Over $5,000
Source: Levelset Data
08/15/2019
Slow Payment Reported Against Amec Foster Wheeler, Wood Plc
Over $5,000
Source: Levelset Data
08/15/2019
Slow Payment Reported Against Exxon Mobil, Turner Industries
Over $60,000
Source: Levelset Data
07/15/2019
Slow Payment Reported Against Amec Foster Wheeler, Exxon Mobil, Wood Plc
Over $10,000
Source: Levelset Data
07/15/2019
Slow Payment Reported Against Amec Foster Wheeler, Wood Plc
Over $10,000
Source: Levelset Data
06/14/2019
Slow Payment Reported Against Amec Foster Wheeler, Exxon Mobil, Wood Plc
Over $5,000
Source: Levelset Data
06/14/2019
Slow Payment Reported Against Amec Foster Wheeler, Wood Plc
Over $5,000
Source: Levelset Data
05/15/2019
Slow Payment Reported Against Exxon Mobil, Wood Plc
Over $5,000
Source: Levelset Data
05/15/2019
Slow Payment Reported Against Wood Plc
Over $5,000
Source: Levelset Data
04/15/2019
Slow Payment Reported Against Exxon Mobil, Morris-Shea Bridge Co., Zachry Industrial
Over $5,000
Source: Levelset Data
04/15/2019
Slow Payment Reported Against Morris-Shea Bridge Co., Zachry Industrial
Over $5,000
Source: Levelset Data
04/15/2019
Slow Payment Reported Against Exxon Mobil, Wood Plc
Over $5,000
Source: Levelset Data
04/15/2019
Slow Payment Reported Against Wood Plc
Over $5,000
Source: Levelset Data
03/15/2019
Slow Payment Reported Against Exxon Mobil, Morris-Shea Bridge Co., Zachry Industrial
Over $10,000
Source: Levelset Data
03/15/2019
Slow Payment Reported Against Exxon Mobil, Wood Plc
Over $1,000
Source: Levelset Data
03/15/2019
Slow Payment Reported Against Morris-Shea Bridge Co., Zachry Industrial
Over $10,000
Source: Levelset Data
02/15/2019
Slow Payment Reported Against Morris-Shea Bridge Co., Zachry Industrial
Over $10,000
Source: Levelset Data
Companies
In this section, you can find all 24 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.
Levelset will pay for your materials.
You pay us back up to 120 days later.
Apply Now