  • Last known event: 11/15/2023
  • First known event: 03/29/2021
LevelsetProjectsTexasGrapevine2149 Anderson Gibson Rd

Property Details


PROJECT TYPE

Commercial

PROPERTY OWNER

Unknown

CITY

Grapevine

Key Facts

The project located at 2149 Anderson Gibson Rd, Grapevine, Texas 76051 has had 14 companies do work over the last 4 years.

Lien History

There has been 2 liens at this address with a reported total value of $207,349.34.

Project History


On this project at 2149 Anderson Gibson Rd, Grapevine, TX 76051 there have been 0 permits filed, 1 preliminary notice exchanged, 0 lien waivers exchanged between companies and 2 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.

Overview

0

PERMITS FILED

1

PRELIMINARY NOTICES

0

LIEN WAIVERS

2

LIEN HISTORY

Payment Timeline

11/15/2023

Slow Payment Reported


Source: Levelset Data

10/13/2023

Slow Payment Reported


Source: Levelset Data

10/13/2023

Slow Payment Reported

Slow Payment Reported Against Fields Painting LLC, Integrated Construction and Development Lp

Over $5,000


Source: Levelset Data

09/15/2023

Slow Payment Reported


Source: Levelset Data

09/15/2023

Slow Payment Reported


Source: Levelset Data

08/15/2023

Slow Payment Reported


Source: Levelset Data

06/15/2023

Slow Payment Reported


Source: Levelset Data

05/15/2023

Slow Payment Reported


Source: Levelset Data

02/15/2023

Slow Payment Reported


Source: Levelset Data

01/13/2023

Slow Payment Reported


Source: Levelset Data

12/15/2022

Slow Payment Reported


Source: Levelset Data

11/15/2022

Slow Payment Reported


Source: Levelset Data

10/14/2022

Mechanics Lien Filed

Lien filed by Idaho Pacific Lumber | Claimant directly hired by GC

Lien filed against Enclave Carter Lp, Integrated Construction and Development Lp

GC listed on lien: Integrated Construction and Development Lp

$137,523


Source: Levelset Data

09/15/2022

Slow Payment Reported


Source: Levelset Data

09/14/2022

Mechanics Lien Filed

Lien filed by Idaho Pacific Lumber | Claimant directly hired by GC

Lien filed against Enclave Carter Lp, Integrated Construction and Development Lp

GC listed on lien: Integrated Construction and Development Lp

$69,826


Source: Levelset Data

05/13/2022

Slow Payment Reported


Source: Levelset Data

04/15/2022

Slow Payment Reported

Slow Payment Reported Against Maxim Fire Systems, Multicon Services LLC

Over $60,000


Source: Levelset Data

03/15/2022

Slow Payment Reported

Slow Payment Reported Against Maxim Fire Systems, Multicon Services LLC

Over $10,000


Source: Levelset Data

Full Project Job Tree14

Companies


In this section, you can find all 14 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.

Lender

Unknown Company

Property Owner

Unknown Company

General Contractor (1)

Bonded by Federal Insurance Company (a Chubb Company)

Subcontractor (9)

Underground Utility Contractors
Integrated Automation Contractors
Fire Suppression Companies

Supplier (3)

AG
Action Gypsum Supply
FE
Ferguson Enterprises, LLC

Surety Companies (1)

FI
Federal Insurance Company (a Chubb Company)

Job Hierarchy


Lender

Unknown Company

Property Owner

Unknown Company

General Contractor (1)

Bonded by Federal Insurance Company (a Chubb Company)

Subcontractor (9)

View All
Underground Utility Contractors

Supplier (3)

View All

Need cash to buy materials for this job?

Levelset will pay for your materials.

You pay us back up to 120 days later.

Apply Now