PROJECT TYPE
Commercial
PROPERTY OWNER
Unknown
CITY
El Paso
On this project at 8725 Gateway Blvd S, El Paso, TX 79904 there have been 0 permits filed, 0 preliminary notices exchanged, 0 lien waivers exchanged between companies and 1 lien filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.
0
PERMITS FILED
0
PRELIMINARY NOTICES
0
LIEN WAIVERS
1
LIEN HISTORY
02/05/2021
Lien filed by Ahern Rentals, Inc. | Claimant directly hired by GC
Lien filed against Del Sol Hotel, PC Builders
GC listed on lien: PC Builders
$24,097
Source: Levelset Data
01/15/2021
Slow Payment Reported Against Del Sol Hotel, PC Builders
Over $10,000
Source: Levelset Data
12/15/2020
Slow Payment Reported Against Del Sol Hotel, PC Builders
Over $10,000
Source: Levelset Data
12/15/2020
Slow Payment Reported Against PC Builders
Over $10,000
Source: Levelset Data
11/19/2020
Lien threat sent to Del Sol Hotel, PC Builders
Over $10,000
Source: Levelset Data
11/13/2020
Slow Payment Reported Against Del Sol Hotel, PC Builders
Over $10,000
Source: Levelset Data
11/13/2020
Slow Payment Reported Against PC Builders
Over $10,000
Source: Levelset Data
10/15/2020
Slow Payment Reported Against PC Builders
Over $10,000
Source: Levelset Data
10/15/2020
Slow Payment Reported Against Del Sol Hotel, PC Builders
Over $10,000
Source: Levelset Data
09/15/2020
Slow Payment Reported Against Del Sol Hotel, PC Builders
Over $10,000
Source: Levelset Data
09/15/2020
Slow Payment Reported Against PC Builders
Over $10,000
Source: Levelset Data
08/14/2020
Slow Payment Reported Against Del Sol Hotel, PC Builders
Over $10,000
Source: Levelset Data
08/14/2020
Slow Payment Reported Against PC Builders
Over $10,000
Source: Levelset Data
07/15/2020
Slow Payment Reported Against Del Sol Hotel, PC Builders
Over $10,000
Source: Levelset Data
07/15/2020
Slow Payment Reported Against PC Builders
Over $10,000
Source: Levelset Data
06/15/2020
Slow Payment Reported Against PC Builders
Over $5,000
Source: Levelset Data
03/13/2020
Slow Payment Reported Against PC Builders
Over $10,000
Source: Levelset Data
03/13/2020
Slow Payment Reported Against Del Sol Hotel, PC Builders
Over $10,000
Source: Levelset Data
02/14/2020
Slow Payment Reported Against PC Builders
Over $10,000
Source: Levelset Data
Companies
In this section, you can find all 4 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.
Lender
Unknown Company
Property Owner
Unknown Company
General Contractor (2)
View AllSubcontractor (0)
Unknown Company
Supplier (1)
Levelset will pay for your materials.
You pay us back up to 120 days later.