On this project at 6611 Boeing Dr, El Paso, TX 79925 there have been 0 permits filed, 0 preliminary notices exchanged, 0 lien waivers exchanged between companies and 0 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.
0
PERMITS FILED
0
PRELIMINARY NOTICES
0
LIEN WAIVERS
0
LIEN HISTORY
11/15/2022
Slow Payment Reported Against ACO Remodeling & Construction, CGC Group, Region 19 Education
Over $1,000
Source: Levelset Data
10/14/2022
Slow Payment Reported Against ACO Remodeling & Construction, CGC Group
Over $5,000
Source: Levelset Data
02/15/2022
Slow Payment Reported Against Buford-Thompson Co, Five Star Automatic Fire Protection
Over $10,000
Source: Levelset Data
01/14/2022
Slow Payment Reported Against Buford-Thompson Co, Five Star Automatic Fire Protection, Granite Re
Over $10,000
Source: Levelset Data
01/14/2022
Slow Payment Reported Against Buford-Thompson Co, Five Star Automatic Fire Protection
Over $10,000
Source: Levelset Data
11/15/2021
Slow Payment Reported Against Buford-Thompson Co, Five Star Automatic Fire Protection, Granite Re
Over $1,000
Source: Levelset Data
11/15/2021
Slow Payment Reported Against Buford-Thompson Co, Contractors Tiles Plus, Inc.
Over $10,000
Source: Levelset Data
10/15/2021
Slow Payment Reported Against Buford-Thompson Co, Five Star Automatic Fire Protection
Over $10,000
Source: Levelset Data
10/15/2021
Slow Payment Reported Against Buford-Thompson Co, Five Star Automatic Fire Protection, Granite Re
Over $10,000
Source: Levelset Data
09/15/2021
Slow Payment Reported Against Buford-Thompson Co, Five Star Automatic Fire Protection
Over $10,000
Source: Levelset Data
08/16/2021
Slow Payment Reported Against Aguilar Forming Rebar Construction, Cambro Construction, El Paso Independent School District
Over $60,000
Source: Levelset Data
07/16/2021
Slow Payment Reported Against Aguilar Forming Rebar Construction, Cambro Construction, Granite Re
Over $60,000
Source: Levelset Data
06/22/2021
Lien threat sent to Aguilar Forming Rebar Construction, Cambro Construction, El Paso Independent School District
Over $60,000
Source: Levelset Data
06/15/2021
Slow Payment Reported Against Aguilar Forming Rebar Construction, Cambro Construction
Over $60,000
Source: Levelset Data
05/14/2021
Slow Payment Reported Against Aguilar Forming Rebar Construction, Cambro Construction, El Paso Independent School District
Over $60,000
Source: Levelset Data
04/15/2021
Slow Payment Reported Against Aguilar Forming Rebar Construction, Cambro Construction
Over $10,000
Source: Levelset Data
04/15/2021
Slow Payment Reported Against Aguilar Forming Rebar Construction, Cambro Construction
Over $10,000
Source: Levelset Data
03/15/2021
Slow Payment Reported Against Aguilar Forming Rebar Construction, Cambro Construction
Over $10,000
Source: Levelset Data
03/15/2021
Slow Payment Reported Against Aguilar Forming Rebar Construction, Cambro Construction
Over $10,000
Source: Levelset Data
02/22/2021
Slow Payment Reported Against Aguilar Forming Rebar Construction, Cambro Construction
Over $60,000
Source: Levelset Data
Companies
In this section, you can find all 33 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.