Menu
A map for the project located in El Paso, Texas.
Commercial Construction Project at

2001 N Oregon St

El Paso, TX 79902

  • Last known event: 06/14/2024
  • First known event: 04/24/2018

Property Details


PROJECT TYPE

Commercial

PROPERTY OWNER

Tenet Healthcare

CITY

El Paso

Key Facts

The project located at 2001 N Oregon St, El Paso, Texas 79902 has had 33 companies do work over the last 7 years.

Lien History

There has been 0 liens at this address with a reported total value of $0.

Project History


On this project at 2001 N Oregon St, El Paso, TX 79902 there have been 1 permit filed, 5 preliminary notices exchanged, 1 lien waiver exchanged between companies and 0 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.

Overview

1

PERMITS FILED

5

PRELIMINARY NOTICES

1

LIEN WAIVERS

0

LIEN HISTORY

Payment Timeline

06/14/2024

Slow Payment Reported

Slow Payment Reported Against FPG Mechanical Contractors Inc., Robins & Morton

Over $1,000


Source: Levelset Data

01/12/2024

Slow Payment Reported

Slow Payment Reported Against FPG Mechanical Contractors Inc., J. E. Dunn Construction Group

Less than $1,000


Source: Levelset Data

01/12/2024

Slow Payment Reported

Slow Payment Reported Against FPG Mechanical Contractors Inc., Hospitals of Providence The, Robins & Morton, Sierra Providence Physical Rehabilitation Hospital

Over $1,000


Source: Levelset Data

12/15/2023

Slow Payment Reported

Slow Payment Reported Against FPG Mechanical Contractors Inc., Robins & Morton

Over $1,000


Source: Levelset Data

08/15/2023

Slow Payment Reported

Slow Payment Reported Against FPG Mechanical Contractors Inc., J. E. Dunn Construction Group, Sierra Providence Physical Rehabilitation Hospital, Tenet Healthcare

Over $1,000


Source: Levelset Data

08/15/2023

Slow Payment Reported

Slow Payment Reported Against Macneill & Sons General Contractors

Over $1,000


Source: Levelset Data

08/15/2023

Slow Payment Reported

Slow Payment Reported Against FPG Mechanical Contractors Inc., Robins & Morton

Over $5,000


Source: Levelset Data

07/14/2023

Slow Payment Reported

Slow Payment Reported Against FPG Mechanical Contractors Inc., Robins & Morton

Over $10,000


Source: Levelset Data

07/14/2023

Slow Payment Reported

Slow Payment Reported Against FPG Mechanical Contractors Inc., J. E. Dunn Construction Group

Over $1,000


Source: Levelset Data

05/15/2023

Slow Payment Reported

Slow Payment Reported Against FPG Mechanical Contractors Inc., J. E. Dunn Construction Group

Over $1,000


Source: Levelset Data

05/15/2023

Slow Payment Reported

Slow Payment Reported Against FPG Mechanical Contractors Inc., J. E. Dunn Construction Group, Sierra Providence Physical Rehabilitation Hospital, Tenet Healthcare

Over $1,000


Source: Levelset Data

05/15/2023

Slow Payment Reported

Slow Payment Reported Against FPG Mechanical Contractors Inc., Robins & Morton

Less than $1,000


Source: Levelset Data

04/14/2023

Slow Payment Reported

Slow Payment Reported Against FPG Mechanical Contractors Inc., Robins & Morton

Less than $1,000


Source: Levelset Data

04/14/2023

Slow Payment Reported

Slow Payment Reported Against FPG Mechanical Contractors Inc., J. E. Dunn Construction Group

Over $1,000


Source: Levelset Data

03/15/2023

Slow Payment Reported

Slow Payment Reported Against FPG Mechanical Contractors Inc., Robins & Morton

Less than $1,000


Source: Levelset Data

02/15/2023

Slow Payment Reported

Slow Payment Reported Against FPG Mechanical Contractors Inc., J. E. Dunn Construction Group

Over $5,000


Source: Levelset Data

02/15/2023

Slow Payment Reported

Slow Payment Reported Against FPG Mechanical Contractors Inc., J. E. Dunn Construction Group, Sierra Providence Physical Rehabilitation Hospital, Tenet Healthcare

Over $5,000


Source: Levelset Data

01/13/2023

Slow Payment Reported

Slow Payment Reported Against FPG Mechanical Contractors Inc., J. E. Dunn Construction Group

Over $1,000


Source: Levelset Data

03/15/2022

Slow Payment Reported

Slow Payment Reported Against FPG Mechanical Contractors Inc., J. E. Dunn Construction Group

Over $1,000


Source: Levelset Data

02/15/2022

Slow Payment Reported

Slow Payment Reported Against FPG Mechanical Contractors Inc., Sierra Providence Physical Rehabilitation Hospital

Over $5,000


Source: Levelset Data

05/15/2020

Slow Payment Reported

Slow Payment Reported Against Macneill & Sons General Contractors, Sierra Providence Physical Rehabilitation Hospital

Over $10,000


Source: Levelset Data

04/15/2020

Slow Payment Reported

Slow Payment Reported Against Macneill & Sons General Contractors

Over $10,000


Source: Levelset Data

03/13/2020

Slow Payment Reported

Slow Payment Reported Against Macneill & Sons General Contractors, Sierra Providence Physical Rehabilitation Hospital

Over $10,000


Source: Levelset Data

03/13/2020

Slow Payment Reported

Slow Payment Reported Against Macneill & Sons General Contractors

Over $10,000


Source: Levelset Data

02/14/2020

Slow Payment Reported

Slow Payment Reported Against Macneill & Sons General Contractors

Over $1,000


Source: Levelset Data

04/26/2018

Slow Payment Reported

Slow Payment Reported Against ACO Remodeling & Construction, Sierra Providence Health Network, Sierra Providence Physical Rehabilitation Hospital

Less than $1,000


Source: Levelset Data

04/26/2018

Slow Payment Reported

Slow Payment Reported Against ACO Remodeling & Construction, FPG Mechanical Contractors Inc., Sierra Providence Health Network, Sierra Providence Physical Rehabilitation Hospital

Less than $1,000


Source: Levelset Data

04/26/2018

Slow Payment Reported

Slow Payment Reported Against Hospitals of Providence The, Sierra Providence Physical Rehabilitation Hospital, Tenet Healthcare

Less than $1,000


Source: Levelset Data

04/26/2018

Slow Payment Reported

Slow Payment Reported Against ACO Remodeling & Construction, FPG Mechanical Contractors Inc., Sierra Providence Health Network, Sierra Providence Physical Rehabilitation Hospital

Less than $1,000


Source: Levelset Data

04/26/2018

Slow Payment Reported

Slow Payment Reported Against J. E. Dunn Construction Group, Sierra Providence Physical Rehabilitation Hospital

Less than $1,000


Source: Levelset Data

04/25/2018

Slow Payment Reported

Slow Payment Reported Against ACO Remodeling & Construction, FPG Mechanical Contractors Inc., Sierra Providence Health Network, Sierra Providence Physical Rehabilitation Hospital

Less than $1,000


Source: Levelset Data

04/25/2018

Slow Payment Reported

Slow Payment Reported Against ACO Remodeling & Construction, FPG Mechanical Contractors Inc.

Less than $1,000


Source: Levelset Data

04/25/2018

Slow Payment Reported

Slow Payment Reported Against ACO Remodeling & Construction, Sierra Providence Health Network, Sierra Providence Physical Rehabilitation Hospital

Less than $1,000


Source: Levelset Data

04/25/2018

Slow Payment Reported

Slow Payment Reported Against R & R Metal Erectors

Less than $1,000


Source: Levelset Data

04/25/2018

Slow Payment Reported

Slow Payment Reported Against FPG Mechanical Contractors Inc., J. E. Dunn Construction Group, Sierra Providence Physical Rehabilitation Hospital

Less than $1,000


Source: Levelset Data

04/25/2018

Slow Payment Reported

Slow Payment Reported Against FPG Mechanical Contractors Inc., J. E. Dunn Construction Group, Sierra Medical Center, Sierra Providence Physical Rehabilitation Hospital

Less than $1,000


Source: Levelset Data

04/25/2018

Slow Payment Reported

Slow Payment Reported Against Hospitals of Providence The, Sierra Providence Physical Rehabilitation Hospital, Tenet Healthcare

Less than $1,000


Source: Levelset Data

04/25/2018

Slow Payment Reported

Slow Payment Reported Against Hospitals of Providence The, R & R Metal Erectors

Less than $1,000


Source: Levelset Data

04/25/2018

Slow Payment Reported

Slow Payment Reported Against FPG Mechanical Contractors Inc.

Less than $1,000


Source: Levelset Data

04/25/2018

Slow Payment Reported

Slow Payment Reported Against ACO Remodeling & Construction, FPG Mechanical Contractors Inc., Sierra Providence Health Network, Sierra Providence Physical Rehabilitation Hospital

Less than $1,000


Source: Levelset Data

04/24/2018

Slow Payment Reported

Slow Payment Reported Against J. E. Dunn Construction Group, R & R Metal Erectors

Less than $1,000


Source: Levelset Data

04/24/2018

Slow Payment Reported

Slow Payment Reported Against Hospitals of Providence The, J. E. Dunn Construction Group, R & R Metal Erectors, Sierra Providence Physical Rehabilitation Hospital

Less than $1,000


Source: Levelset Data

Full Project Job Tree33

Companies


In this section, you can find all 33 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.

Lender

Unknown Company

Property Owner

Bonded by Unknown

General Contractor (4)

Bonded by Federal Insurance Company (a Chubb Company)
Bonded by Federal Insurance Company (a Chubb Company)
Bonded by Federal Insurance Company (a Chubb Company)
Bonded by Federal Insurance Company (a Chubb Company)

Subcontractor (22)

Supplier (6)

FE
Ferguson Enterprises, LLC
KR
KKH Rentals Dba National Structures Events & Services
LS
L&W Supply
AR
Ahern Rentals, Inc.

Surety Companies (1)

FI
Federal Insurance Company (a Chubb Company)

Job Hierarchy


Lender

Unknown Company

Property Owner

Bonded by Unknown

General Contractor (4)

View All
Bonded by Federal Insurance Company (a Chubb Company)