  • Last known event: 11/15/2021
  • First known event: 12/10/2019

Property Details


PROJECT TYPE

Residential

PROPERTY OWNER

Unknown

CITY

Dallas

Key Facts

The project located at 405 E Overton Rd, Dallas, Texas 75216 has had 23 companies do work over the last 6 years.

Lien History

There has been 11 liens at this address with a reported total value of $421,551.01.

Project History


On this project at 405 E Overton Rd, Dallas, TX 75216 there have been 0 permits filed, 1 preliminary notice exchanged, 0 lien waivers exchanged between companies and 11 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.

Overview

0

PERMITS FILED

1

PRELIMINARY NOTICES

0

LIEN WAIVERS

11

LIEN HISTORY

Payment Timeline

11/15/2021

Slow Payment Reported

Slow Payment Reported Against CIP Paving, Hill & Wilkinson

Over $5,000


Source: Levelset Data

10/15/2021

Slow Payment Reported

Slow Payment Reported Against CIP Paving, Hill & Wilkinson

Over $10,000


Source: Levelset Data

05/19/2021

Mechanics Lien Filed

Lien filed by Integra Fire Protection, LLC | Claimant directly hired by GC

Lien filed against Crimson Building Company, Emdev Fund

GC listed on lien: Crimson Building Company

$2,950


Source: Levelset Data

05/14/2021

Mechanics Lien Filed

Lien filed by BMC West, LLC | Claimant directly hired by GC

Lien filed against Crimson Building Company, Emdev Fund

GC listed on lien: Crimson Building Company

$2,178


Source: Levelset Data

04/15/2021

Mechanics Lien Filed

Lien filed by BMC West, LLC | Claimant directly hired by GC

Lien filed against Crimson Building Company, Last

GC listed on lien: Crimson Building Company

$1,970


Source: Levelset Data

05/04/2020

Lien Threatened

Lien threat sent to Marquis Construction

Less than $1,000


Source: Levelset Data

04/15/2020

Slow Payment Reported

Slow Payment Reported Against Crimson Building Company, Overton Plaza

Less than $1,000


Source: Levelset Data

03/13/2020

Mechanics Lien Filed

Lien filed by Big D Concrete, LLC | Claimant directly hired by GC

Lien filed against Crimson Building Company, Emdev Fund, Marquis Group

GC listed on lien: Marquis Group

$53,683


Source: Levelset Data

03/12/2020

Mechanics Lien Filed

Lien filed by Redi-Mix Concrete (US Concrete) | Claimant directly hired by GC

Lien filed against Emdev Fund, Marquis Group

GC listed on lien: Marquis Group

$1,487


Source: Levelset Data

03/11/2020

Mechanics Lien Filed

Lien filed by Pioneer Longhorn Concrete Pumping | Claimant directly hired by GC

Lien filed against Crimson Building Company, Emdev Fund, Marquis Construction

GC listed on lien: Marquis Construction

$3,697


Source: Levelset Data

03/04/2020

Lien Threatened

Lien threat sent to Crimson Building Company, Emdev Fund, Marquis Construction

Over $10,000


Source: Levelset Data

02/14/2020

Mechanics Lien Filed

Lien filed by Ready Cable Inc. | Claimant directly hired by GC

Lien filed against Crimson Building Company, Emdev Fund, Marquis Construction

GC listed on lien: Marquis Construction

$10,969


Source: Levelset Data

02/14/2020

Mechanics Lien Filed

Lien filed by Ferguson Enterprises, LLC | Claimant directly hired by GC

Lien filed against Crimson Building Company, Emdev Fund, Marquis Construction

GC listed on lien: Marquis Construction

$42,313


Source: Levelset Data

02/13/2020

Mechanics Lien Filed

Lien filed by Pyle & Nagel Development | Claimant directly hired by GC

Lien filed against Crimson Building Company, Emdev Fund

GC listed on lien: Crimson Building Company

$87,750


Source: Levelset Data

02/11/2020

Mechanics Lien Filed

Lien filed by Pioneer Longhorn Concrete Pumping | Claimant directly hired by GC

Lien filed against Crimson Building Company, Emdev Fund, Marquis Construction

GC listed on lien: Marquis Construction

$2,903


Source: Levelset Data

02/11/2020

Slow Payment Reported

Slow Payment Reported Against Crimson Building Company, Emdev Fund, Marquis Construction

Over $10,000


Source: Levelset Data

01/15/2020

Slow Payment Reported

Slow Payment Reported Against Crimson Building Company, Emdev Fund, Marquis Construction

Over $10,000


Source: Levelset Data

01/15/2020

Mechanics Lien Filed

Lien filed by Valistra Group | Claimant directly hired by GC

Lien filed against Crimson Building Company, Land At Last

GC listed on lien: Crimson Building Company

$211,650


Source: Levelset Data

01/07/2020

Slow Payment Reported

Slow Payment Reported Against Crimson Building Company, Marquis Construction

Over $10,000


Source: Levelset Data

12/10/2019

Slow Payment Reported

Slow Payment Reported Against Crimson Building Company, Marquis Construction

Over $10,000


Source: Levelset Data

Full Project Job Tree23

Companies


In this section, you can find all 23 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.

Lender

Unknown Company

Property Owner

Unknown Company

General Contractor (4)

Bonded by Unknown
Bonded by Business Alliance Insurance Company
Bonded by Unknown
Bonded by Unknown

Subcontractor (13)

Exterior Improvement Contractors
Subcontractor
Subcontractor
Subcontractor
Subcontractor
Subcontractor

Supplier (5)

BI
Barnsco, Inc. (TX)
AR
Ahern Rentals, Inc.
FE
Ferguson Enterprises, LLC
BD
Big D Concrete, LLC

Surety Companies

Unknown Company

Job Hierarchy


Lender

Unknown Company

Property Owner

Unknown Company

General Contractor (4)

View All
Bonded by Unknown

Subcontractor (13)

View All
Exterior Improvement Contractors

Supplier (5)

View All

Need cash to buy materials for this job?

Levelset will pay for your materials.

You pay us back up to 120 days later.

Apply Now