On this project at 3815 S Franklin St, Dallas, TX 75233 there have been 3 permits filed, 1 preliminary notice exchanged, 0 lien waivers exchanged between companies and 3 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.
3
PERMITS FILED
1
PRELIMINARY NOTICES
0
LIEN WAIVERS
3
LIEN HISTORY
10/11/2023
Lien filed by Ferguson Enterprises, LLC
Lien filed against Construction Zone International, Federal Insurance Company (a Chubb Company), Hartford Fire Insurance Company
GC listed on lien: 3i Contracting
Property Owner: Dallas Independent School District
$5,018
Source: Levelset Data
09/15/2023
Slow Payment Reported Against Construction Zone International, Federal Insurance Company (a Chubb Company), Hartford Fire Insurance Company, IBARRA UNDERGROUND LLC
Over $5,000
Source: Levelset Data
08/15/2023
Slow Payment Reported Against Construction Zone International, Federal Insurance Company (a Chubb Company), Hartford Fire Insurance Company, IBARRA UNDERGROUND LLC
Over $5,000
Source: Levelset Data
08/15/2023
Slow Payment Reported Against Construction Zone International, IBARRA UNDERGROUND LLC
Over $5,000
Source: Levelset Data
07/14/2023
Slow Payment Reported Against Construction Zone International, Federal Insurance Company (a Chubb Company), Hartford Fire Insurance Company
Over $10,000
Source: Levelset Data
07/14/2023
Slow Payment Reported Against Construction Zone International, IBARRA UNDERGROUND LLC
Over $5,000
Source: Levelset Data
07/12/2023
Lien threat sent to Construction Zone International, Dallas Independent School District, Federal Insurance Company (a Chubb Company), Hartford Fire Insurance Company
Over $10,000
Source: Levelset Data
06/15/2023
Slow Payment Reported Against Federal Insurance Company (a Chubb Company), Hartford Fire Insurance Company, IBARRA UNDERGROUND LLC
Over $1,000
Source: Levelset Data
06/15/2023
Slow Payment Reported Against Construction Zone International, Dallas Independent School District
Over $10,000
Source: Levelset Data
05/15/2023
Slow Payment Reported Against Construction Zone International
Over $10,000
Source: Levelset Data
05/15/2023
Slow Payment Reported Against IBARRA UNDERGROUND LLC
Over $5,000
Source: Levelset Data
01/12/2023
Lien filed by Perfect Finish Landscape | Claimant directly hired by GC
Lien filed against Construction Zone International, Hartford Fire Insurance Company
GC listed on lien: Construction Zone International
Property Owner: Dallas Independent School District
$4,760
Source: Levelset Data
11/15/2022
Slow Payment Reported Against IBARRA UNDERGROUND LLC
Over $5,000
Source: Levelset Data
11/15/2022
Slow Payment Reported Against Construction Zone International, Dallas Independent School District
Over $10,000
Source: Levelset Data
11/15/2022
Slow Payment Reported Against Construction Zone International
Over $10,000
Source: Levelset Data
11/15/2022
Slow Payment Reported Against Construction Zone International, Hartford Fire Insurance Company
Over $5,000
Source: Levelset Data
11/15/2022
Slow Payment Reported Against Federal Insurance Company (a Chubb Company), Hartford Fire Insurance Company, IBARRA UNDERGROUND LLC
Over $5,000
Source: Levelset Data
10/19/2022
Lien threat sent to Construction Zone International
Over $10,000
Source: Levelset Data
10/14/2022
Slow Payment Reported Against IBARRA UNDERGROUND LLC
Over $5,000
Source: Levelset Data
09/15/2022
Slow Payment Reported Against Construction Zone International, Hartford Fire Insurance Company
Over $60,000
Source: Levelset Data
09/15/2022
Slow Payment Reported Against Construction Zone International, Dallas Independent School District
Over $10,000
Source: Levelset Data
08/15/2022
Slow Payment Reported Against Avid Electrical Contracting , Construction Zone International
Over $1,000
Source: Levelset Data
02/10/2022
Lien filed by Poolcorp
Lien filed against Construction Zone International, Hartford Fire Insurance Company
GC listed on lien: Construction Zone International
Property Owner: Dallas Independent School District
$1,649
Source: Levelset Data
01/18/2022
Slow Payment Reported Against Construction Zone International
Over $1,000
Source: Levelset Data
01/18/2022
Lien threat sent to Construction Zone International, Dallas Independent School District, Hartford Fire Insurance Company, Perfect Finish Landscape
Over $1,000
Source: Levelset Data
01/14/2022
Slow Payment Reported Against Construction Zone International
Over $10,000
Source: Levelset Data
12/15/2021
Slow Payment Reported Against Construction Zone International
Less than $1,000
Source: Levelset Data
12/15/2021
Slow Payment Reported Against Construction Zone International, Contract Bond Agency, Paramount Plumbing
Over $5,000
Source: Levelset Data
12/15/2021
Slow Payment Reported Against Construction Zone International, IBARRA UNDERGROUND LLC
Over $5,000
Source: Levelset Data
12/15/2021
Slow Payment Reported Against Construction Zone International, Dallas Independent School District, Hartford Fire Insurance Company, Perfect Finish Landscape
Over $1,000
Source: Levelset Data
11/15/2021
Slow Payment Reported Against Construction Zone International, Contract Bond Agency, Paramount Plumbing
Over $5,000
Source: Levelset Data
11/15/2021
Slow Payment Reported Against Construction Zone International, Paramount Plumbing
Over $5,000
Source: Levelset Data
11/15/2021
Slow Payment Reported Against Construction Zone International, Dallas Independent School District, Hartford Fire Insurance Company, Perfect Finish Landscape
Over $1,000
Source: Levelset Data
11/15/2021
Slow Payment Reported Against Construction Zone International, Dallas Independent School District, Perfect Finish Landscape
Over $1,000
Source: Levelset Data
10/18/2021
Lien threat sent to Construction Zone International
Over $10,000
Source: Levelset Data
10/15/2021
Slow Payment Reported Against Construction Zone International
Over $1,000
Source: Levelset Data
10/15/2021
Slow Payment Reported Against Construction Zone International, Contract Bond Agency, Paramount Plumbing
Over $5,000
Source: Levelset Data
10/15/2021
Slow Payment Reported Against Construction Zone International, Paramount Plumbing
Over $5,000
Source: Levelset Data
10/15/2021
Slow Payment Reported Against Construction Zone International, Hartford Fire Insurance Company, IBARRA UNDERGROUND LLC
Over $1,000
Source: Levelset Data
10/15/2021
Slow Payment Reported Against Construction Zone International, IBARRA UNDERGROUND LLC
Over $1,000
Source: Levelset Data
10/15/2021
Slow Payment Reported Against Construction Zone International, Dallas Independent School District, Perfect Finish Landscape
Over $1,000
Source: Levelset Data
10/01/2021
Slow Payment Reported Against Construction Zone International
Over $10,000
Source: Levelset Data
09/15/2021
Slow Payment Reported Against Construction Zone International, Contract Bond Agency, Paramount Plumbing
Over $5,000
Source: Levelset Data
09/15/2021
Slow Payment Reported Against Construction Zone International, Paramount Plumbing
Over $5,000
Source: Levelset Data
09/15/2021
Slow Payment Reported Against Construction Zone International, Hartford Fire Insurance Company, Paramount Plumbing
Over $1,000
Source: Levelset Data
08/13/2021
Slow Payment Reported Against Construction Zone International, Paramount Plumbing
Over $10,000
Source: Levelset Data
07/15/2021
Slow Payment Reported Against Construction Zone International, Contract Bond Agency, Paramount Plumbing
Over $5,000
Source: Levelset Data
07/15/2021
Slow Payment Reported Against Construction Zone International, Dallas Independent School District
Over $10,000
Source: Levelset Data
06/15/2021
Slow Payment Reported Against Construction Zone International, Paramount Plumbing
Over $5,000
Source: Levelset Data
07/22/2020
Source: ConstructionMonitor
07/22/2020
Source: ConstructionMonitor
07/22/2020
Source: ConstructionMonitor
Companies
In this section, you can find all 30 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.