Menu
A map for the project located in Austin, Texas.
Commercial Construction Project at

7701 Metropolis Dr Bldg 12

Austin, TX 78744

  • Last known event: 07/11/2022
  • First known event: 04/23/2018
LevelsetProjectsTexasAustin7701 Metropolis Dr Bldg 12

Property Details


PROJECT TYPE

Commercial

CITY

Austin

Key Facts

The project located at 7701 Metropolis Dr Bldg 12, Austin, Texas 78744 has had 17 companies do work over the last 7 years.

Lien History

There has been 0 liens at this address with a reported total value of $0.

Project History


On this project at 7701 Metropolis Dr Bldg 12, Austin, TX 78744 there have been 3 permits filed, 1 preliminary notice exchanged, 0 lien waivers exchanged between companies and 0 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.

Overview

3

PERMITS FILED

1

PRELIMINARY NOTICES

0

LIEN WAIVERS

0

LIEN HISTORY

Payment Timeline

07/11/2022

Slow Payment Reported

Slow Payment Reported Against ARCO/Murray National Construction Co. Inc., Kapsch, Mohr Met Center

Over $10,000


Source: Levelset Data

07/01/2022

Lien Threatened

Lien threat sent to ARCO/Murray National Construction Co. Inc., Kapsch, Mohr Met Center

Over $10,000


Source: Levelset Data

06/22/2022

Slow Payment Reported

Slow Payment Reported Against ARCO/Murray National Construction Co. Inc., Kapsch, Mohr Met Center

Over $10,000


Source: Levelset Data

06/15/2022

Slow Payment Reported

Slow Payment Reported Against ARCO/Murray National Construction Co. Inc., D3 Mechanical, Kapsch

Over $1,000


Source: Levelset Data

06/15/2022

Slow Payment Reported

Slow Payment Reported Against ARCO/Murray National Construction Co. Inc., D3 Mechanical

Over $1,000


Source: Levelset Data

05/13/2022

Slow Payment Reported

Slow Payment Reported Against ARCO/Murray National Construction Co. Inc., D3 Mechanical

Over $1,000


Source: Levelset Data

04/15/2022

Slow Payment Reported

Slow Payment Reported Against ARCO/Murray National Construction Co. Inc., D3 Mechanical, Kapsch

Over $1,000


Source: Levelset Data

03/15/2022

Slow Payment Reported

Slow Payment Reported Against ARCO/Murray National Construction Co. Inc., D3 Mechanical, Kapsch

Over $1,000


Source: Levelset Data

03/15/2022

Slow Payment Reported

Slow Payment Reported Against ARCO/Murray National Construction Co. Inc., D3 Mechanical

Over $1,000


Source: Levelset Data

02/15/2022

Slow Payment Reported

Slow Payment Reported Against ARCO/Murray National Construction Co. Inc., D3 Mechanical

Over $1,000


Source: Levelset Data

04/23/2018

Slow Payment Reported

Slow Payment Reported Against Met Center Partners-12, Ltd.

Less than $1,000


Source: Levelset Data

04/23/2018

Slow Payment Reported

Slow Payment Reported Against Rhino Interiors Inc.

Less than $1,000


Source: Levelset Data

Full Project Job Tree17

Companies


In this section, you can find all 17 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.

Lender

Unknown Company

Property Owner

General Contractor (3)

Bonded by Hudson Insurance Company
A1
A&A 1st Choice LLC

Subcontractor (10)

Subcontractor
Fire Suppression Companies
Subcontractor
Electrical Power Generation (EPC) Contractors
Subcontractor

Supplier (3)

AR
Ahern Rentals, Inc.
FE
Ferguson Enterprises, LLC
LS
L&W Supply

Surety Companies

Unknown Company

Job Hierarchy


Lender

Unknown Company

Property Owner

General Contractor (3)

View All
Bonded by Hudson Insurance Company

Subcontractor (10)

View All
Subcontractor

Supplier (3)

View All
AR
Ahern Rentals, Inc.

Need cash to buy materials for this job?

Levelset will pay for your materials.

You pay us back up to 120 days later.

Apply Now