On this project at 7400 N LAMAR BLVD, Austin, TX 78752 there have been 3 permits filed, 1 preliminary notice exchanged, 0 lien waivers exchanged between companies and 2 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.
3
PERMITS FILED
1
PRELIMINARY NOTICES
0
LIEN WAIVERS
2
LIEN HISTORY
09/23/2020
Slow Payment Reported Against ANDRES Construction, Trammell Crow Company (TCC)
Over $60,000
Source: Levelset Data
06/02/2020
Lien filed by Metal Construction Materials LLC Dba Paramount Steel | Claimant directly hired by GC
Lien filed against ANDRES Construction, Hsp Crestview Commons Phase 2, Trammell Crow Company (TCC)
GC listed on lien: ANDRES Construction
Property Owner: Trammell Crow Company (TCC)
$36,737
Source: Levelset Data
05/29/2020
Slow Payment Reported Against Trammell Crow Company (TCC)
Over $10,000
Source: Levelset Data
05/15/2020
Slow Payment Reported Against ANDRES Construction, Masram Mechanical
Less than $1,000
Source: Levelset Data
03/13/2020
Slow Payment Reported Against ANDRES Construction, Masram Mechanical
Less than $1,000
Source: Levelset Data
02/14/2020
Slow Payment Reported Against ANDRES Construction, Unlimited Sprinkler Fire Protection, Inc.
Over $5,000
Source: Levelset Data
02/14/2020
Slow Payment Reported Against ANDRES Construction, Masram Mechanical
Less than $1,000
Source: Levelset Data
12/13/2019
Slow Payment Reported Against ANDRES Construction, Masram Mechanical
Less than $1,000
Source: Levelset Data
12/13/2019
Slow Payment Reported Against ANDRES Construction, Unlimited Sprinkler Fire Protection, Inc.
Over $10,000
Source: Levelset Data
11/15/2019
Slow Payment Reported Against ANDRES Construction, Masram Mechanical
Less than $1,000
Source: Levelset Data
11/15/2019
Slow Payment Reported Against ANDRES Construction, Unlimited Sprinkler Fire Protection, Inc.
Over $10,000
Source: Levelset Data
10/15/2019
Slow Payment Reported Against ANDRES Construction, Masram Mechanical
Less than $1,000
Source: Levelset Data
09/13/2019
Slow Payment Reported Against ANDRES Construction, Unlimited Sprinkler Fire Protection, Inc.
Over $10,000
Source: Levelset Data
06/21/2019
Source: ConstructionMonitor
12/10/2018
Lien filed by Gibson Plumbing Co. | Claimant directly hired by GC
Lien filed against ANDRES Construction, Crestview Station Phase Iv, Trammell Crow Company (TCC)
GC listed on lien: ANDRES Construction
Property Owner: Trammell Crow Company (TCC)
$105,324
Source: Levelset Data
Companies
In this section, you can find all 12 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.
Lender
Unknown Company
Property Owner
General Contractor (1)
Subcontractor (9)
View AllSupplier (1)