On this project at 5401 E Parmer Ln, Austin, TX 78754 there have been 1 permit filed, 1 preliminary notice exchanged, 0 lien waivers exchanged between companies and 3 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.
1
PERMITS FILED
1
PRELIMINARY NOTICES
0
LIEN WAIVERS
3
LIEN HISTORY
10/28/2024
Lien filed by Morsco
Lien filed against Cadence McShane Construction, Gw Creekside Austin
GC listed on lien: Cadence McShane Construction
$30,167
Source: Levelset Data
10/15/2024
Slow Payment Reported Against Cadence McShane Construction, Gw Creekside Austin
Over $10,000
Source: Levelset Data
10/15/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction, Gw Creekside Austin
Over $10,000
Source: Levelset Data
09/13/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction
Over $10,000
Source: Levelset Data
09/13/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction, Gw Creekside Austin
Less than $1,000
Source: Levelset Data
09/13/2024
Slow Payment Reported Against Cadence McShane Construction, Gw Hillside Austin Qozb, Longhorn Mechanical Inc
Less than $1,000
Source: Levelset Data
09/13/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction, Gw Creekside Austin
Over $10,000
Source: Levelset Data
08/15/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction, Gw Creekside Austin
Over $10,000
Source: Levelset Data
08/15/2024
Slow Payment Reported Against Cadence McShane Construction, Gw Creekside Austin, Whitestone Civil Construction
Over $10,000
Source: Levelset Data
08/15/2024
Slow Payment Reported Against Cadence McShane Construction, Gw Creekside Austin, Gw Hillside Austin Qozb, Longhorn Mechanical Inc
Over $10,000
Source: Levelset Data
08/15/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction
Over $10,000
Source: Levelset Data
08/15/2024
Slow Payment Reported Against Cadence McShane Construction, Gw Hillside Austin Qozb, Longhorn Mechanical Inc
Less than $1,000
Source: Levelset Data
08/15/2024
Slow Payment Reported Against Cadence McShane Construction, Longhorn Mechanical Inc
Less than $1,000
Source: Levelset Data
08/15/2024
Slow Payment Reported Against Cadence McShane Construction, Gw Creekside Austin
Over $60,000
Source: Levelset Data
08/15/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction, Gw Creekside Austin
Less than $1,000
Source: Levelset Data
08/15/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction
Less than $1,000
Source: Levelset Data
07/15/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction, Gw Creekside Austin
Less than $1,000
Source: Levelset Data
07/15/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction
Less than $1,000
Source: Levelset Data
07/15/2024
Slow Payment Reported Against Cadence McShane Construction, Longhorn Mechanical Inc
Less than $1,000
Source: Levelset Data
07/15/2024
Slow Payment Reported Against Cadence McShane Construction, Whitestone Civil Construction
Over $10,000
Source: Levelset Data
07/15/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction
Over $10,000
Source: Levelset Data
07/15/2024
Slow Payment Reported Against Cadence McShane Construction, Longhorn Mechanical Inc
Over $60,000
Source: Levelset Data
07/15/2024
Slow Payment Reported Against Cadence McShane Construction, Gw Creekside Austin
Over $60,000
Source: Levelset Data
07/15/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction, Gw Creekside Austin
Over $10,000
Source: Levelset Data
07/15/2024
Slow Payment Reported Against Cadence McShane Construction, Gw Creekside Austin, Gw Hillside Austin Qozb, Longhorn Mechanical Inc
Over $60,000
Source: Levelset Data
06/14/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction, Gw Creekside Austin
Less than $1,000
Source: Levelset Data
06/14/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction, Gw Creekside Austin
Over $10,000
Source: Levelset Data
06/14/2024
Slow Payment Reported Against Cadence McShane Construction, Longhorn Mechanical Inc
Over $60,000
Source: Levelset Data
06/14/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction
Over $10,000
Source: Levelset Data
06/14/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction
Less than $1,000
Source: Levelset Data
06/14/2024
Slow Payment Reported Against Cadence McShane Construction, Gw Creekside Austin, Gw Hillside Austin Qozb, Longhorn Mechanical Inc
Over $60,000
Source: Levelset Data
05/28/2024
Lien filed by Reinforcing Steel Supply
Lien filed against Cadence McShane Construction, Gw Creekside Austin, Whitestone Civil Construction
GC listed on lien: Cadence McShane Construction
$36,250
Source: Levelset Data
05/15/2024
Slow Payment Reported Against Cadence McShane Construction, Whitestone Civil Construction
Over $10,000
Source: Levelset Data
05/15/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction
Less than $1,000
Source: Levelset Data
05/15/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction, Gw Creekside Austin
Less than $1,000
Source: Levelset Data
05/15/2024
Slow Payment Reported Against Cadence McShane Construction, Gw Creekside Austin
Over $60,000
Source: Levelset Data
05/15/2024
Slow Payment Reported Against Cadence McShane Construction, Gw Hillside Austin Qozb, Longhorn Mechanical Inc
Less than $1,000
Source: Levelset Data
05/15/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction
Over $10,000
Source: Levelset Data
05/15/2024
Slow Payment Reported Against Cadence McShane Construction, Longhorn Mechanical Inc
Over $60,000
Source: Levelset Data
05/15/2024
Slow Payment Reported Against Cadence McShane Construction, Gw Creekside Austin, Gw Hillside Austin Qozb, Longhorn Mechanical Inc
Over $60,000
Source: Levelset Data
04/15/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction
Less than $1,000
Source: Levelset Data
04/15/2024
Slow Payment Reported Against Cadence McShane Construction, Longhorn Mechanical Inc
Less than $1,000
Source: Levelset Data
04/15/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction
Over $10,000
Source: Levelset Data
04/15/2024
Slow Payment Reported Against Cadence McShane Construction, Gw Creekside Austin, Gw Hillside Austin Qozb, Longhorn Mechanical Inc
Over $60,000
Source: Levelset Data
04/15/2024
Slow Payment Reported Against Cadence McShane Construction, Whitestone Civil Construction
Over $10,000
Source: Levelset Data
04/15/2024
Slow Payment Reported Against Cadence McShane Construction, Gw Creekside Austin, Whitestone Civil Construction
Over $10,000
Source: Levelset Data
04/15/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction, Gw Creekside Austin
Less than $1,000
Source: Levelset Data
04/15/2024
Slow Payment Reported Against Cadence McShane Construction, Longhorn Mechanical Inc
Over $60,000
Source: Levelset Data
04/15/2024
Slow Payment Reported Against Cadence McShane Construction, Whitestone Civil Construction
Over $10,000
Source: Levelset Data
03/15/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction
Less than $1,000
Source: Levelset Data
03/15/2024
Slow Payment Reported Against Cadence McShane Construction, Gw Creekside Austin, Whitestone Civil Construction
Over $10,000
Source: Levelset Data
03/15/2024
Slow Payment Reported Against Cadence McShane Construction, Gw Creekside Austin
Over $60,000
Source: Levelset Data
03/15/2024
Slow Payment Reported Against Longhorn Mechanical Inc
Over $60,000
Source: Levelset Data
03/15/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction
Over $10,000
Source: Levelset Data
03/15/2024
Slow Payment Reported Against Gw Creekside Austin, Gw Hillside Austin Qozb, Longhorn Mechanical Inc
Over $60,000
Source: Levelset Data
03/15/2024
Slow Payment Reported Against Cadence McShane Construction, Whitestone Civil Construction
Over $10,000
Source: Levelset Data
02/15/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction
Over $60,000
Source: Levelset Data
02/15/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction, Gw Creekside Austin
Over $60,000
Source: Levelset Data
02/15/2024
Slow Payment Reported Against Gw Hillside Austin Qozb, Longhorn Mechanical Inc
Over $60,000
Source: Levelset Data
02/15/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction
Less than $1,000
Source: Levelset Data
02/15/2024
Slow Payment Reported Against Longhorn Mechanical Inc
Over $60,000
Source: Levelset Data
02/15/2024
Slow Payment Reported Against Cadence McShane Construction, Gw Creekside Austin, Whitestone Civil Construction
Over $10,000
Source: Levelset Data
02/15/2024
Slow Payment Reported Against Cadence McShane Construction, Whitestone Civil Construction
Over $10,000
Source: Levelset Data
01/12/2024
Slow Payment Reported Against Cadence McShane Construction, Gw Creekside Austin, Whitestone Civil Construction
Over $10,000
Source: Levelset Data
01/12/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction, Gw Creekside Austin
Over $10,000
Source: Levelset Data
01/12/2024
Slow Payment Reported Against Basey Plumbing, Cadence McShane Construction
Over $10,000
Source: Levelset Data
01/12/2024
Slow Payment Reported Against Cadence McShane Construction, Whitestone Civil Construction
Over $10,000
Source: Levelset Data
01/12/2024
Slow Payment Reported Against Longhorn Mechanical Inc
Over $10,000
Source: Levelset Data
12/15/2023
Slow Payment Reported Against Cadence McShane Construction, Whitestone Civil Construction
Over $5,000
Source: Levelset Data
12/15/2023
Slow Payment Reported Against Basey Plumbing, Gw Creekside Austin
Over $60,000
Source: Levelset Data
12/15/2023
Slow Payment Reported Against Basey Plumbing
Over $60,000
Source: Levelset Data
12/15/2023
Slow Payment Reported Against Longhorn Mechanical Inc
Over $60,000
Source: Levelset Data
11/15/2023
Slow Payment Reported Against Basey Plumbing
Over $60,000
Source: Levelset Data
11/15/2023
Slow Payment Reported Against Longhorn Mechanical Inc
Over $60,000
Source: Levelset Data
11/15/2023
Slow Payment Reported Against Cadence McShane Construction, Whitestone Civil Construction
Over $10,000
Source: Levelset Data
11/15/2023
Slow Payment Reported Against Cadence McShane Construction, Gw Hillside Austin Qozb, Longhorn Mechanical Inc
Less than $1,000
Source: Levelset Data
11/15/2023
Slow Payment Reported Against Cadence McShane Construction, Whitestone Civil Construction
Over $10,000
Source: Levelset Data
10/13/2023
Slow Payment Reported Against Cadence McShane Construction, Whitestone Civil Construction
Over $10,000
Source: Levelset Data
10/13/2023
Slow Payment Reported Against Basey Plumbing
Over $10,000
Source: Levelset Data
10/13/2023
Slow Payment Reported Against Longhorn Mechanical Inc
Over $60,000
Source: Levelset Data
10/13/2023
Slow Payment Reported Against Cadence McShane Construction, Whitestone Civil Construction
Over $60,000
Source: Levelset Data
10/13/2023
Slow Payment Reported Against Cadence McShane Construction, Longhorn Mechanical Inc
Less than $1,000
Source: Levelset Data
09/15/2023
Slow Payment Reported Against Cadence McShane Construction, Central Texas Outdoor Living LLC
Over $5,000
Source: Levelset Data
09/15/2023
Slow Payment Reported Against Cadence McShane Construction, Whitestone Civil Construction
Over $10,000
Source: Levelset Data
09/15/2023
Slow Payment Reported Against Longhorn Mechanical Inc
Over $60,000
Source: Levelset Data
08/15/2023
Slow Payment Reported Against Basey Plumbing
Over $10,000
Source: Levelset Data
08/15/2023
Slow Payment Reported Against Longhorn Mechanical Inc
Over $60,000
Source: Levelset Data
08/15/2023
Slow Payment Reported Against Cadence McShane Construction, Central Texas Outdoor Living LLC
Over $10,000
Source: Levelset Data
03/03/2023
Lien filed by Ferguson Enterprises, LLC
Lien filed against Cadence McShane Construction, Gw Creekside Austin, Gw Hillside Austin Qozb, Whitestone Civil Construction
GC listed on lien: Cadence McShane Construction
$3,839
Source: Levelset Data
01/13/2023
Slow Payment Reported Against Cadence McShane Construction, Gw Creekside Austin, Gw Hillside Austin Qozb, Whitestone Civil Construction
Over $10,000
Source: Levelset Data
01/13/2023
Slow Payment Reported Against Cadence McShane Construction, Whitestone Civil Construction
Over $10,000
Source: Levelset Data
12/15/2022
Slow Payment Reported Against Cadence McShane Construction, Whitestone Civil Construction
Over $10,000
Source: Levelset Data
12/15/2022
Slow Payment Reported Against Cadence McShane Construction, Gw Creekside Austin, Gw Hillside Austin Qozb, Whitestone Civil Construction
Over $10,000
Source: Levelset Data
11/15/2022
Slow Payment Reported Against Cadence McShane Construction, Gw Creekside Austin, Whitestone Civil Construction
Over $1,000
Source: Levelset Data
11/15/2022
Slow Payment Reported Against Longhorn Mechanical Inc
Less than $1,000
Source: Levelset Data
11/15/2022
Slow Payment Reported Against Cadence McShane Construction, Whitestone Civil Construction
Over $10,000
Source: Levelset Data
11/15/2022
Slow Payment Reported Against Cadence McShane Construction, Whitestone Civil Construction
Over $1,000
Source: Levelset Data
09/15/2022
Slow Payment Reported Against Whitestone Civil Construction
Over $1,000
Source: Levelset Data
09/15/2022
Slow Payment Reported Against Cadence McShane Construction, Gw Creekside Austin, Gw Hillside Austin Qozb, Whitestone Civil Construction
Over $60,000
Source: Levelset Data
09/15/2022
Slow Payment Reported Against Cadence McShane Construction, Whitestone Civil Construction
Over $60,000
Source: Levelset Data
08/15/2022
Slow Payment Reported Against Cadence McShane Construction, Gw Creekside Austin, Gw Hillside Austin Qozb, Whitestone Civil Construction
Over $60,000
Source: Levelset Data
08/15/2022
Slow Payment Reported Against Cadence McShane Construction, Whitestone Civil Construction
Over $60,000
Source: Levelset Data
07/15/2022
Slow Payment Reported Against Cadence McShane Construction, Whitestone Civil Construction
Over $60,000
Source: Levelset Data
07/15/2022
Slow Payment Reported Against Cadence McShane Construction, Gw Creekside Austin, Gw Hillside Austin Qozb, Whitestone Civil Construction
Over $60,000
Source: Levelset Data
06/15/2022
Slow Payment Reported Against Cadence McShane Construction, Whitestone Civil Construction
Over $60,000
Source: Levelset Data
05/13/2022
Slow Payment Reported Against Cadence McShane Construction, Gw Creekside Austin, Gw Hillside Austin Qozb, Whitestone Civil Construction
Over $60,000
Source: Levelset Data
04/15/2022
Slow Payment Reported Against Cadence McShane Construction, Gw Creekside Austin, Gw Hillside Austin Qozb, Whitestone Civil Construction
Over $60,000
Source: Levelset Data
04/15/2022
Slow Payment Reported Against Cadence McShane Construction, Whitestone Civil Construction
Over $60,000
Source: Levelset Data
03/15/2022
Slow Payment Reported Against Cadence McShane Construction, Whitestone Civil Construction
Over $60,000
Source: Levelset Data
06/15/2020
Slow Payment Reported Against Gw Creekside Austin, LMS Lonestar Masonry
Less than $1,000
Source: Levelset Data
05/15/2020
Slow Payment Reported Against LMS Lonestar Masonry
Less than $1,000
Source: Levelset Data
04/25/2018
Slow Payment Reported Against Schmid Construction (FL)
Less than $1,000
Source: Levelset Data
04/24/2018
Slow Payment Reported Against Schmid Construction (FL)
Less than $1,000
Source: Levelset Data
04/24/2018
Slow Payment Reported Against Oden Hughes Taylor Construction LLC
Less than $1,000
Source: Levelset Data
08/15/2017
Slow Payment Reported Against Gw Creekside Austin, Schmid Construction (FL)
Over $60,000
Source: Levelset Data
07/14/2017
Slow Payment Reported Against Gw Creekside Austin, Schmid Construction (FL)
Over $10,000
Source: Levelset Data
Companies
In this section, you can find all 26 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.
Levelset will pay for your materials.
You pay us back up to 120 days later.
Apply Now