On this project at 1404 Park Center Dr, Austin, TX 78753 there have been 8 permits filed, 3 preliminary notices exchanged, 0 lien waivers exchanged between companies and 0 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.
8
PERMITS FILED
3
PRELIMINARY NOTICES
0
LIEN WAIVERS
0
LIEN HISTORY
12/13/2024
Slow Payment Reported Against Dell Inc., Spider Wall Systems, Whiting-Turner
Over $1,000
Source: Levelset Data
11/15/2024
Slow Payment Reported Against Spider Wall Systems, Whiting-Turner
Over $1,000
Source: Levelset Data
12/15/2023
Slow Payment Reported Against Dell Inc., Whiting-Turner
Over $10,000
Source: Levelset Data
08/21/2023
Contractors listed on Permit: Great Basin Industrial
# 2023-043090 EP
$553,600
Source: ConstructionMonitor
10/14/2022
Slow Payment Reported Against Dell Inc., Whiting-Turner
Over $10,000
Source: Levelset Data
09/15/2021
Slow Payment Reported Against SI Mechanical, Whiting-Turner
Over $60,000
Source: Levelset Data
08/13/2021
Slow Payment Reported Against SI Mechanical, Whiting-Turner
Over $10,000
Source: Levelset Data
08/13/2021
Slow Payment Reported Against Dell Inc., SI Mechanical, Whiting-Turner
Over $10,000
Source: Levelset Data
08/13/2021
Slow Payment Reported Against SI Mechanical, Whiting-Turner
Over $1,000
Source: Levelset Data
07/15/2021
Slow Payment Reported Against SI Mechanical, Whiting-Turner
Over $10,000
Source: Levelset Data
05/14/2021
Slow Payment Reported Against Dell Inc., Whiting-Turner
Over $10,000
Source: Levelset Data
10/15/2020
Slow Payment Reported Against Dell Inc., Whiting-Turner
Over $1,000
Source: Levelset Data
07/15/2020
Slow Payment Reported Against Central Texas Hot Works, Whiting-Turner
Over $1,000
Source: Levelset Data
Companies
In this section, you can find all 18 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.