On this project at 13101 Tesla Rd, Austin, TX 78725 there have been 1 permit filed, 20 preliminary notices exchanged, 2 lien waivers exchanged between companies and 14 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.
1
PERMITS FILED
20
PRELIMINARY NOTICES
2
LIEN WAIVERS
14
LIEN HISTORY
10/15/2024
Slow Payment Reported Against A A Welders & Fabricators, Colorado River Project LLC
Over $10,000
Source: Levelset Data
10/15/2024
Slow Payment Reported Against Colorado River Project LLC, Miller Integrated
Over $60,000
Source: Levelset Data
09/13/2024
Slow Payment Reported Against A A Welders & Fabricators, Colorado River Project LLC
Over $10,000
Source: Levelset Data
09/13/2024
Slow Payment Reported Against Tesla , W.G. Yates & Sons Construction Co.
Less than $1,000
Source: Levelset Data
09/13/2024
Slow Payment Reported Against Colorado River Project LLC, Miller Integrated
Over $60,000
Source: Levelset Data
09/11/2024
Slow Payment Reported Against Tesla , W.G. Yates & Sons Construction Co.
Less than $1,000
Source: Levelset Data
08/15/2024
Slow Payment Reported Against A A Welders & Fabricators
Over $10,000
Source: Levelset Data
07/15/2024
Slow Payment Reported Against A A Welders & Fabricators
Over $10,000
Source: Levelset Data
07/15/2024
Slow Payment Reported Against Colorado River Project LLC
Over $60,000
Source: Levelset Data
06/14/2024
Slow Payment Reported Against Corval Group, Tesla
Over $10,000
Source: Levelset Data
06/14/2024
Slow Payment Reported Against A A Welders & Fabricators
Over $10,000
Source: Levelset Data
06/14/2024
Slow Payment Reported Against Colorado River Project LLC
Over $60,000
Source: Levelset Data
06/14/2024
Slow Payment Reported Against Colorado River Project LLC, The Burt Group
Over $60,000
Source: Levelset Data
05/15/2024
Slow Payment Reported Against The Burt Group
Over $60,000
Source: Levelset Data
04/15/2024
Slow Payment Reported Against The Burt Group
Over $60,000
Source: Levelset Data
04/15/2024
Slow Payment Reported Against Colorado River Project LLC, Polk Mechanical Co, Tesla , W.G. Yates & Sons Construction Co.
Over $10,000
Source: Levelset Data
04/10/2024
Slow Payment Reported Against The Burt Group
Over $60,000
Source: Levelset Data
03/15/2024
Slow Payment Reported Against Polk Mechanical Co, W.G. Yates & Sons Construction Co.
Over $10,000
Source: Levelset Data
03/15/2024
Slow Payment Reported Against Stewart Builders Dba Keystone Concrete Placement, W.G. Yates & Sons Construction Co.
Over $60,000
Source: Levelset Data
02/15/2024
Slow Payment Reported Against Capital Excavation
Over $60,000
Source: Levelset Data
02/15/2024
Slow Payment Reported Against Blanco Electric Co. (BELCO)
Over $1,000
Source: Levelset Data
02/15/2024
Slow Payment Reported Against Capital Excavation, Tesla
Over $60,000
Source: Levelset Data
02/15/2024
Slow Payment Reported Against LITHKO CONTRACTING LLC, The Yates Companies, Inc.(Yates Construction)
Over $60,000
Source: Levelset Data
02/15/2024
Lien filed by FE MORAN SPECIAL HAZARD SYSTMS
Lien filed against Tesla, W.G. Yates & Sons Construction Co.
$1,967,927
Source: Levelset Data
02/15/2024
Lien filed by A. H. Beck Foundation Co Inc.
Lien filed against Tesla , Tesla Colorado River Projects
Property Owner: Tesla
$1,814,876
Source: Levelset Data
02/15/2024
Slow Payment Reported Against Tesla , The Burt Group
Over $5,000
Source: Levelset Data
02/14/2024
Lien filed by Miner Corp
Lien filed against Colorado River Project LLC, W.G. Yates & Sons Construction Co.
Property Owner: Colorado River Project LLC
$16,745
Source: Levelset Data
02/12/2024
Lien filed by Brandsafway Solutions
Lien filed against Tesla Colorado River Projects, W.G. Yates & Sons Construction Co.
$1,181,401
Source: Levelset Data
01/12/2024
Slow Payment Reported Against Tesla , W.G. Yates & Sons Construction Co.
Over $5,000
Source: Levelset Data
01/12/2024
Slow Payment Reported Against Miller Integrated
Over $1,000
Source: Levelset Data
01/12/2024
Slow Payment Reported Against Blanco Electric Co. (BELCO)
Over $1,000
Source: Levelset Data
01/12/2024
Slow Payment Reported Against The Burt Group
Over $60,000
Source: Levelset Data
01/12/2024
Slow Payment Reported Against LITHKO CONTRACTING LLC, The Yates Companies, Inc.(Yates Construction)
Over $60,000
Source: Levelset Data
01/12/2024
Slow Payment Reported Against Miller Integrated
Over $10,000
Source: Levelset Data
01/12/2024
Slow Payment Reported Against Miller Integrated
Over $1,000
Source: Levelset Data
01/12/2024
Slow Payment Reported Against Capital Excavation
Over $60,000
Source: Levelset Data
01/12/2024
Slow Payment Reported Against Miller Integrated
Over $1,000
Source: Levelset Data
01/12/2024
Slow Payment Reported Against Corval Group
Over $10,000
Source: Levelset Data
12/15/2023
Slow Payment Reported Against Tesla , The Burt Group
Over $60,000
Source: Levelset Data
12/15/2023
Slow Payment Reported Against Colorado River Project LLC, Tesla
Less than $1,000
Source: Levelset Data
12/15/2023
Slow Payment Reported Against Colorado River Project LLC, Tesla , W.G. Yates & Sons Construction Co.
Less than $1,000
Source: Levelset Data
11/22/2023
Lien threat sent to W.G. Yates & Sons Construction Co.
Over $60,000
Source: Levelset Data
11/15/2023
Slow Payment Reported Against Colorado River Project LLC, Integrated Systems
Over $10,000
Source: Levelset Data
11/15/2023
Slow Payment Reported Against CECO Environmental, Colorado River Project LLC
Over $60,000
Source: Levelset Data
11/15/2023
Slow Payment Reported Against DYNAMIC SYSTEMS INC, Tesla
Over $10,000
Source: Levelset Data
11/15/2023
Lien filed by Martin Marietta | Claimant directly hired by GC
Lien filed against C.C. Carlton Industries, Ltd., Tesla
GC listed on lien: C.C. Carlton Industries, Ltd.
Property Owner: Tesla
$6,233
Source: Levelset Data
11/14/2023
Lien filed by Martin Marietta | Claimant directly hired by GC
Lien filed against Colorado River Project LLC, Rosendin Electric
GC listed on lien: Rosendin Electric
Property Owner: Tesla
$6,369
Source: Levelset Data
11/14/2023
Slow Payment Reported Against Colorado River Project LLC, Tesla , W.G. Yates & Sons Construction Co.
Less than $1,000
Source: Levelset Data
10/13/2023
Slow Payment Reported Against Tesla
Over $60,000
Source: Levelset Data
10/13/2023
Slow Payment Reported Against DYNAMIC SYSTEMS INC
Over $60,000
Source: Levelset Data
10/13/2023
Slow Payment Reported Against Environmental Safety Services, Environmental Safety Services Inc., Tesla
Over $10,000
Source: Levelset Data
10/13/2023
Slow Payment Reported Against Integrated Systems
Over $10,000
Source: Levelset Data
10/13/2023
Slow Payment Reported Against Colorado River Project LLC, Integrated Systems
Over $10,000
Source: Levelset Data
10/13/2023
Slow Payment Reported Against Tesla
Over $60,000
Source: Levelset Data
09/15/2023
Slow Payment Reported Against Tesla
Over $60,000
Source: Levelset Data
09/15/2023
Slow Payment Reported Against Environmental Safety Services Inc.
Over $10,000
Source: Levelset Data
09/15/2023
Slow Payment Reported Against Colorado River Project LLC, W.G. Yates & Sons Construction Co.
Less than $1,000
Source: Levelset Data
09/15/2023
Slow Payment Reported Against Corval Group
Over $10,000
Source: Levelset Data
09/15/2023
Slow Payment Reported Against Tesla
Over $60,000
Source: Levelset Data
09/15/2023
Slow Payment Reported Against Colorado River Project LLC, Integrated Systems
Over $10,000
Source: Levelset Data
09/15/2023
Slow Payment Reported Against Integrated Systems
Over $10,000
Source: Levelset Data
09/15/2023
Slow Payment Reported Against DYNAMIC SYSTEMS INC, Tesla
Over $60,000
Source: Levelset Data
08/15/2023
Slow Payment Reported Against Colorado River Project LLC, W.G. Yates & Sons Construction Co.
Less than $1,000
Source: Levelset Data
08/15/2023
Slow Payment Reported Against Five Star Civil Construction, The Yates Companies, Inc.(Yates Construction)
Over $10,000
Source: Levelset Data
08/15/2023
Slow Payment Reported Against DYNAMIC SYSTEMS INC
Over $60,000
Source: Levelset Data
08/15/2023
Slow Payment Reported Against Colorado River Project LLC, Tesla , W.G. Yates & Sons Construction Co.
Less than $1,000
Source: Levelset Data
08/15/2023
Slow Payment Reported Against Integrated Systems
Over $10,000
Source: Levelset Data
08/15/2023
Slow Payment Reported Against A. H. Beck Foundation Co Inc., Tesla
Over $60,000
Source: Levelset Data
08/01/2023
Lien filed by Five Star Civil Construction
Lien filed against Tesla, W.G. Yates & Sons Construction Co.
$324,740
Source: Levelset Data
07/14/2023
Slow Payment Reported Against Champion Site Prep, Inc., Tesla
Over $10,000
Source: Levelset Data
07/14/2023
Slow Payment Reported Against Pdn Group
Over $10,000
Source: Levelset Data
07/14/2023
Slow Payment Reported Against Five Star Civil Construction
Over $10,000
Source: Levelset Data
07/14/2023
Slow Payment Reported Against Colorado River Project LLC, GFCS, Inc., Tesla , The Yates Companies, Inc.(Yates Construction)
Over $60,000
Source: Levelset Data
07/14/2023
Slow Payment Reported Against Colorado River Project LLC, Tesla , W.G. Yates & Sons Construction Co.
Less than $1,000
Source: Levelset Data
07/14/2023
Slow Payment Reported Against DYNAMIC SYSTEMS INC
Over $60,000
Source: Levelset Data
07/14/2023
Slow Payment Reported Against DYNAMIC SYSTEMS INC, Tesla
Over $60,000
Source: Levelset Data
06/15/2023
Slow Payment Reported Against Clean Scapes, Colorado River Project LLC
Over $10,000
Source: Levelset Data
06/15/2023
Slow Payment Reported Against A. H. Beck Foundation Co Inc., Tesla
Over $60,000
Source: Levelset Data
06/15/2023
Slow Payment Reported Against GFCS, Inc., Tesla , The Yates Companies, Inc.(Yates Construction)
Over $60,000
Source: Levelset Data
05/15/2023
Slow Payment Reported Against Arroyo Seco Construction , Five Star Civil Construction
Over $10,000
Source: Levelset Data
05/12/2023
Lien filed by Polk Mechanical Co
Lien filed against Colorado River Project LLC
Property Owner: Colorado River Project LLC
$28,926
Source: Levelset Data
04/14/2023
Slow Payment Reported Against Tesla
Less than $1,000
Source: Levelset Data
04/14/2023
Slow Payment Reported Against Bobcat Heavy Civil, LLC
Over $10,000
Source: Levelset Data
04/14/2023
Slow Payment Reported Against Tesla
Over $60,000
Source: Levelset Data
04/14/2023
Slow Payment Reported Against Five Star Civil Construction
Over $5,000
Source: Levelset Data
03/15/2023
Slow Payment Reported Against Tesla
Over $60,000
Source: Levelset Data
03/15/2023
Slow Payment Reported Against Five Star Civil Construction
Over $10,000
Source: Levelset Data
02/15/2023
Slow Payment Reported Against Colorado River Project LLC, W.G. Yates & Sons Construction Co.
Less than $1,000
Source: Levelset Data
02/15/2023
Slow Payment Reported Against A. H. Beck Foundation Co Inc., Tesla
Over $10,000
Source: Levelset Data
02/15/2023
Slow Payment Reported Against Champion Site Prep, Inc., Tesla
Over $60,000
Source: Levelset Data
02/06/2023
Lien filed by All Tex Pipe & Supply
Lien filed against DYNAMIC SYSTEMS INC, Tesla Colorado River Projects
$196,287
Source: Levelset Data
01/13/2023
Slow Payment Reported Against Bobcat Heavy Civil, LLC
Over $60,000
Source: Levelset Data
01/13/2023
Slow Payment Reported Against Five Star Civil Construction
Over $60,000
Source: Levelset Data
12/15/2022
Slow Payment Reported Against Clean Scapes
Over $60,000
Source: Levelset Data
12/15/2022
Slow Payment Reported Against C.C. Carlton Industries, Ltd.
Over $10,000
Source: Levelset Data
12/15/2022
Slow Payment Reported Against Colorado River Project LLC, W.G. Yates & Sons Construction Co.
Less than $1,000
Source: Levelset Data
12/13/2022
Lien filed by Birch Manufacturing
Lien filed against Miner Corp, Tesla Colorado River Projects
$74,753
Source: Levelset Data
11/14/2022
Lien filed by Cable Com, Inc. (TX)
Lien filed against Colorado River Project LLC, Full Circle Technologies LLC
Property Owner: Colorado River Project LLC
$84,681
Source: Levelset Data
11/14/2022
Lien filed by Cable Com, Inc. (TX)
Lien filed against Colorado River Project LLC, Full Circle Technologies LLC
Property Owner: Colorado River Project LLC
$30,647
Source: Levelset Data
09/15/2022
Slow Payment Reported Against Clean Scapes
Over $60,000
Source: Levelset Data
05/13/2022
Slow Payment Reported Against Oscar Orduno
Over $10,000
Source: Levelset Data
04/15/2022
Slow Payment Reported Against Oscar Orduno
Over $10,000
Source: Levelset Data
03/23/2022
Source: ConstructionMonitor
03/15/2022
Slow Payment Reported Against Oscar Orduno
Over $10,000
Source: Levelset Data
02/17/2022
Slow Payment Reported Against MMR Constructors, Tesla
Over $10,000
Source: Levelset Data
02/16/2022
Slow Payment Reported Against Polk Mechanical Co, Tesla
Over $10,000
Source: Levelset Data
02/15/2022
Slow Payment Reported Against Colorado River Project LLC, Tesla
Over $60,000
Source: Levelset Data
02/15/2022
Slow Payment Reported Against Austin Commercial LP, Omega Contracting LLC (KS), Tesla , The Yates Companies, Inc.(Yates Construction)
Over $10,000
Source: Levelset Data
02/15/2022
Slow Payment Reported Against Austin Commercial LP, Scivic Engineering America Inc. (SC), Tesla , The Yates Companies, Inc.(Yates Construction)
Over $5,000
Source: Levelset Data
02/15/2022
Slow Payment Reported Against Austin Commercial LP, Colorado River Project LLC, Scivic Engineering America Inc. (SC), Tesla , The Yates Companies, Inc.(Yates Construction), Txi Operations L P
Over $5,000
Source: Levelset Data
02/15/2022
Slow Payment Reported Against PSC Crane & Rigging
Over $10,000
Source: Levelset Data
02/15/2022
Slow Payment Reported Against Tesla
Over $60,000
Source: Levelset Data
02/14/2022
Slow Payment Reported Against Tesla
Over $60,000
Source: Levelset Data
02/14/2022
Slow Payment Reported Against Colorado River Project LLC, Tesla
Over $60,000
Source: Levelset Data
01/14/2022
Slow Payment Reported Against Austin Commercial LP, Colorado River Project LLC, Scivic Engineering America Inc. (SC), Tesla , The Yates Companies, Inc.(Yates Construction), Txi Operations L P
Over $5,000
Source: Levelset Data
01/14/2022
Slow Payment Reported Against Austin Commercial LP, IPME CORP, Tesla , The Yates Companies, Inc.(Yates Construction)
Over $10,000
Source: Levelset Data
01/14/2022
Slow Payment Reported Against Austin Commercial LP, Colorado River Project LLC, IPME CORP, Tesla , The Yates Companies, Inc.(Yates Construction), Txi Operations L P
Over $10,000
Source: Levelset Data
01/14/2022
Slow Payment Reported Against Austin Commercial LP, Scivic Engineering America Inc. (SC), Tesla , The Yates Companies, Inc.(Yates Construction)
Over $5,000
Source: Levelset Data
12/15/2021
Slow Payment Reported Against Austin Commercial LP, Scivic Engineering America Inc. (SC), Tesla , The Yates Companies, Inc.(Yates Construction)
Over $5,000
Source: Levelset Data
12/15/2021
Slow Payment Reported Against Austin Commercial LP, IPME CORP, Tesla , The Yates Companies, Inc.(Yates Construction)
Over $10,000
Source: Levelset Data
12/15/2021
Slow Payment Reported Against Austin Commercial LP, Colorado River Project LLC, Omega Contracting LLC (KS), Tesla , The Yates Companies, Inc.(Yates Construction), Txi Operations L P
Over $5,000
Source: Levelset Data
11/15/2021
Slow Payment Reported Against Austin Commercial LP, Omega Contracting LLC (KS), Tesla , The Yates Companies, Inc.(Yates Construction)
Over $5,000
Source: Levelset Data
11/15/2021
Slow Payment Reported Against Austin Commercial LP, IPME CORP, Tesla , The Yates Companies, Inc.(Yates Construction)
Over $10,000
Source: Levelset Data
10/15/2021
Slow Payment Reported Against Austin Commercial LP, Omega Contracting LLC (KS), Tesla , The Yates Companies, Inc.(Yates Construction)
Over $10,000
Source: Levelset Data
10/15/2021
Slow Payment Reported Against Austin Commercial LP, Scivic Engineering America Inc. (SC), Tesla , The Yates Companies, Inc.(Yates Construction)
Over $5,000
Source: Levelset Data
09/15/2021
Slow Payment Reported Against Austin Commercial LP, Colorado River Project LLC, Scivic Engineering America Inc. (SC), Tesla , The Yates Companies, Inc.(Yates Construction), Txi Operations L P
Over $5,000
Source: Levelset Data
09/15/2021
Slow Payment Reported Against Austin Commercial LP, Omega Contracting LLC (KS), Tesla , The Yates Companies, Inc.(Yates Construction)
Over $10,000
Source: Levelset Data
09/15/2021
Slow Payment Reported Against Austin Commercial LP, Scivic Engineering America Inc. (SC), Tesla , The Yates Companies, Inc.(Yates Construction)
Over $5,000
Source: Levelset Data
09/15/2021
Slow Payment Reported Against Austin Commercial LP, Parsons Roofing, Tesla , The Yates Companies, Inc.(Yates Construction)
Over $10,000
Source: Levelset Data
08/13/2021
Slow Payment Reported Against Austin Commercial LP, Colorado River Project LLC, Omega Contracting LLC (KS), Tesla , The Yates Companies, Inc.(Yates Construction), Txi Operations L P
Over $10,000
Source: Levelset Data
08/13/2021
Slow Payment Reported Against Austin Commercial LP, Omega Contracting LLC (KS), Tesla , The Yates Companies, Inc.(Yates Construction)
Over $10,000
Source: Levelset Data
08/13/2021
Slow Payment Reported Against Austin Commercial LP, Colorado River Project LLC, Scivic Engineering America Inc. (SC), Tesla , The Yates Companies, Inc.(Yates Construction), Txi Operations L P
Over $1,000
Source: Levelset Data
08/13/2021
Slow Payment Reported Against Austin Commercial LP, Scivic Engineering America Inc. (SC), Tesla , The Yates Companies, Inc.(Yates Construction)
Over $1,000
Source: Levelset Data
07/15/2021
Slow Payment Reported Against Austin Commercial LP, Colorado River Project LLC, Omega Contracting LLC (KS), Tesla , The Yates Companies, Inc.(Yates Construction), Txi Operations L P
Over $10,000
Source: Levelset Data
07/15/2021
Slow Payment Reported Against Austin Commercial LP, Colorado River Project LLC, Parsons Roofing, Tesla , The Yates Companies, Inc.(Yates Construction), Txi Operations L P
Over $10,000
Source: Levelset Data
06/15/2021
Slow Payment Reported Against Parsons Roofing
Over $10,000
Source: Levelset Data
Companies
In this section, you can find all 85 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.
Levelset will pay for your materials.
You pay us back up to 120 days later.
Apply Now