On this project at 99 W Paces Ferry Rd NW, Atlanta, GA 30305 there have been 7 permits filed, 10 preliminary notices exchanged, 0 lien waivers exchanged between companies and 2 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.
7
PERMITS FILED
10
PRELIMINARY NOTICES
0
LIEN WAIVERS
2
LIEN HISTORY
04/11/2023
Lien filed by Alpha Insulation & Waterproofing Co | Claimant directly hired by GC
Lien filed against Development Authority of Fulton County (GA), JLB Builders LLC, Jlb 99 West Paces Ferry
GC listed on lien: JLB Partners
Property Owner: Development Authority of Fulton County (GA)
$295,535
Source: Levelset Data
11/02/2022
Lien filed by Ideal Building Solutions | Claimant directly hired by GC
Lien filed against Development Authority of Fulton County (GA), JLB Builders LLC, Jlb West Paces Phase 1 Lp
GC listed on lien: JLB Builders LLC
Property Owner: Development Authority of Fulton County (GA)
$25,834
Source: Levelset Data
04/22/2022
Contractors listed on Permit: Ziegler Cooper Architects
# BB-202202874
$5,000
Source: ConstructionMonitor
04/22/2022
Contractors listed on Permit: Ziegler Cooper Architects
# BB-202202873
$5,000
Source: ConstructionMonitor
04/22/2022
Contractors listed on Permit: Ziegler Cooper Architects
# BB-202202872
$5,000
Source: ConstructionMonitor
04/22/2022
Contractors listed on Permit: Ziegler Cooper Architects
# BB-202202871
$5,000
Source: ConstructionMonitor
04/22/2022
Contractors listed on Permit: Ziegler Cooper Architects
# BB-202202870
$5,000
Source: ConstructionMonitor
04/22/2022
Contractors listed on Permit: Ziegler Cooper Architects
# BB-202202869
$5,000
Source: ConstructionMonitor
04/22/2022
Contractors listed on Permit: Ziegler Cooper Architects
# BB-202202862
$5,000
Source: ConstructionMonitor
Companies
In this section, you can find all 30 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.