On this project at 110 E 9th St, Los Angeles, CA 90015 there have been 28 permits filed, 35 preliminary notices exchanged, 18 lien waivers exchanged between companies and 4 liens filed. Below you can find when the various project and payment events occurred over the last several years of data where available. You can also report a payment event if you’re on this project.
28
PERMITS FILED
35
PRELIMINARY NOTICES
18
LIEN WAIVERS
4
LIEN HISTORY
03/29/2024
Contractors listed on Permit: Calmart Sub I, Colin Mckay Thompson, Clune Construction Company
# 23016-10000-42200
$2,374,190
Source: ConstructionMonitor
02/13/2023
Lien threat sent to All Pro Communications Technologies, Inc., Calmart Sub I, Clune Construction Company
Over $10,000
Source: Levelset Data
10/24/2022
Lien filed by IMAC Construction, Inc. | Claimant directly hired by GC
Lien filed against Calmart Sub I, Turner Construction
GC listed on lien: Turner Construction
$108,957
Source: Levelset Data
10/17/2022
Source: ConstructionMonitor
08/01/2022
Lien filed by Schindler Elevator Corporation | Claimant directly hired by GC
Lien filed against Calmart Sub I, Turner Construction
GC listed on lien: Turner Construction
$1,763
Source: Levelset Data
03/01/2022
Lien filed by Intermountain Lock & Security Supply Company
Lien filed against Calmart Sub I, Retrolock Corporation (CA)
$8,202
Source: Levelset Data
02/04/2022
Contractors listed on Permit: Brookfield Properties, Clune Construction Company
# 21016-10000-58692
$190,000
Source: ConstructionMonitor
01/31/2022
Lien filed by Door Components Inc.
Lien filed against Calmart Sub I, Retrolock Corporation (CA)
$20,953
Source: Levelset Data
04/22/2021
Source: ConstructionMonitor
12/16/2020
Lien threat sent to Calmart Sub I, J J Environmental
Over $10,000
Source: Levelset Data
Companies
In this section, you can find all 59 known companies who have worked on projects at this address at each level. You'll be able to browse companies, find the information you need to get paid, or search for your next project partner.
Lender
Property Owner
General Contractor (6)
View AllSubcontractor (41)
View AllSupplier (10)
View AllLevelset will pay for your materials.
You pay us back up to 120 days later.
Apply Now