not yet 100% complete with project but I have not been paid for work completed and not yet paid. im about to file a mechanics lien but wondering if I should still work on project and finish??>...Read More
Good Morning, I have a question regarding a lien we would like to file against a customer. The document number for the preliminary is 3289136. My question is, there is material and install on the job- it’s a gym. We delivered the material back in March, but then never were able to do the instal...Read More...Read More
We supplied equipment and training and are completely done on the project, but it is on-going and will be for another year. Do we need to file a claim before the notice of completion?...Read More
I am a homeowner who had a major renovation project done. The contractor never completed the bucket list. Do I have to pay him the residual amount. Much of the work was unsatisfactory...Read More
I am the homeowner and am withholding final payment on a renovation project because the bucket list wasn't completed. Can the contractor put a lien on my home...Read More
I am a home owner in Morton Grove, IL who contracted for renovation - supposed to be completed in 6-8 weeks - 7 months later the contractor sends me notification that in his opinion the job is complete (inspections and occupancy permit is not completed. He advises me that he still owes subs $17...Read More...Read More
The job was never finished but there has been no work or materials to the site for about a year. No demand for payment and no lien rights notices have been given. Have the lien rights expired? And do I have to formally finalize the job in any way?...Read More
I was contracted to do a job and perform many of the required items on the punch list final day of work customer refused to let us finish and then said would not pay the balance due which is 40% of the entire project retaining all materials and basically refuses to pay is that any way shape or form OK l...Read More...Read More
The situation is as follows: My company is both a manufacturer and subcontractor for custom cabinetry & woodwork projects. We were hired to produce a custom cabinetry/woodwork project around October 2019 or so for a NYC based Contractor who's client is also a NYC resident. We performed th...Read More...Read More
The organization is in need to finish this project for several reasons. 1. The staff members are without a home as of right now, and desperately need to have us finish this project, so they can move in. 2. Financially we only have a certain amount of time to finish this project. Is it possible that we can pro...Read More...Read More
Hello - question; we are a general contractor, who contracted a cabinet subcontractor for a residential project. Have been trying to for 6-8 weeks to get sub back onsite to finish cabinets, as not complete/onsite and many outstanding corrections. Sub has placed a lien and stop notice and is demanding...Read More...Read More
I'm filing a lien on your website and it's asking for the date of substantial completion. My company left the project in September but I know they were still on the job in December. If I'm no longer in contact with the GC how should I proceed?...Read More
In CA, a private commercial Work (Apartments) has received Temporary Certificate of Occupancy (TCO) from the City, and the owner's clients moved in on 11/11/2019. Our scope of work was complete on 01/30/2020, but the owner has not completed his requirements to receive a full Certificate of O...Read More...Read More
My contractor wrote, “one year warranty” under Change Orders on the contract for my home and he also dated and signed this, “one year warranty” statement. In addition, I paid him the final draw that day with an Officers check from my bank and I have a copy of the Officers Check along with ...Read More...Read More