Hi there. Can you connect me to somebody in marketing regarding an opportunity for your company to join our upcoming innovation summit for small to mid-sized businesses? SMBWorld 2022 is the largest fully-digital event specifically dedicated to technology solutions for small to mid-sized business owners & executives. It's taking place digitally on June 22-23, and the event has tracks dedicated to marketing, sales, operations, HR, and finance. We're expecting 1500+ SMB founders and execs to attend. Would your company be interested in exploring a sponsored speaking role, roundtable discussion, or virtual booth? See the full details in the link below. I can also send sample attendee snapshots. https://smbworld.io/ -Thanks, Glenn
...Read More
I am a flooring company that installed, sanded and coated a 3,000 sq ft house. New construction, first contract was for install, second was for sanding and finishing the wood. I was paid full for first and only half for second contract. Work is completed, and homeowners want more finished coats. They were told once they pay the rest of contract I will then buy more poly and do how ever many coats they want. Not putting any more of my own money into a job that I haven't been paid for. (When theres been many issues with money along the way. ) My question is, If I put a lien on the house/owners does that stop them from being able to move in until I am paid fully for completed contract? If not then what are my options this house isn't going to be sold probably past my days. Its just about finished built for Owners I am doing work for.
...Read More
I worked on a big project for a College and the General Contractor and I are disputing some deductive change orders. Can I do a stop notice so I can make sure I get paid. I am under the impression I cannot do a Mechanic's Lien because it is a federally funded job right? They are holding all my retention at the moment. ...Read More
Ownership has decided to utilize a new General Contractor on a project already under construction. Looking for advice for a smooth transition....Read More
We are GC on a public works project. We hired a subcontractor, and they subbed out their work to a contractor. We received a stop payment notice from the local electricians union that their subcontractor did not pay the monthly dues. What do we do? We would like to pay the union the dues and subtractor that from our subcontractor's payment, however, we aren't familiar with this process. ...Read More
a stop notice was filed and we need to pay and get a release of stop notice. What is process.? do we need to meet a trade check for release?...Read More
Is there a way that we can amend a stop payment notice or send in a new one for the difference owed?
We sent a stop notice for a portion of our work, the general says they have our money but wont release it until we come to their office with a signed release. Can they do that? From my understanding, you don't sign a release until money has cleared the bank. (Just like in Conditional Waivers) So we now have completed our contracted work so the full amount of the contract is now owed. So that is why I am asking if we can amend the original for the full amount of what is now owed? Please advise....Read More
Please answer ASAP, I am losing time to initiate a Stop Notice. I need to know if the 30 days cover the completion of the whole project or just my portion of the project?...Read More
I am the subcontractor and was informed by a Levelset representative to file a Stop Notice to initiate a Lien on a project. The representative stated that a Notice of Completion must be filed as well. I did not record the Notice of Completion within 30 days, was informed about the 90 days from actual completion and do not know if the 90 days entitles the whole project or just the portion I worked on....Read More
What if we filed a top Notice on a GC and they were over 90 days late, They paid but did not pay the retention owed. Do we then file another stop notice with the retention amount not paid?...Read More