Lien Deadlines Questions

All Status
Lien Deadlines
All States
I hope this question isn't confusing. We have a client that we have worked for for years and they are having financial difficulty. We have about 4 open
projects we are currently working on for them. Can I file a lien for the total amount due now even though some of the work will be performed in ...Read More
...Read More
Anonymous Contractor
1 answerAdd commentSep 21, 2017
TexasBankruptcyLien DeadlinesMechanics LienPayment Disputes
We have a job where the customer has unpaid balances outside of the contract amount. Can I file separate pre liens for those items? If I send out a pre lien
at one amount, and it changes, how can I update a pre lien?
...Read More
Anonymous Subcontractor
1 answerAdd commentSep 20, 2017
CaliforniaLien DeadlinesPreliminary Notice
Probably not a question you can answer, but we had a contractor take material from a job site, and use it on another job, that he was not authorized to use it
on. Then he started buying product for the new job, and we would like to file a notice of furnishings on it. We are well within the 21 days to file th...Read More
...Read More
Anonymous Subcontractor
1 answerAdd commentSep 14, 2017
OhioLien DeadlinesPreliminary Notice
Delivery of equipment was on a Friday, began work on following Tuesday and completed the job 20 days after work began or would it be 24 days from
equipment delivery. I did not file a NTO, and GC is not paying me for work performed. Can I still file a NTO?
...Read More
Anonymous Subcontractor
1 answerAdd commentSep 14, 2017
FloridaLien DeadlinesPreliminary Notice
Due to the fact that Oregon has the shortest preliminary notice deadline in the country, it causes issues on the time necessary to complete the processing of
shipment/invoicing and then give enough time to enter the project, allow for research, and file a preliminary notice. I keep seeing that to "be safe...Read More
...Read More
Anonymous Subcontractor
1 answerAdd commentSep 12, 2017
OregonLien DeadlinesMechanics LienPreliminary Notice
I have sent a notice of intent to lien to all parties as required by Illinois law. What I didn't do, was send the 60 day preliminary notice for an owner occupied
project (which this was). My question is do I still have to/ or should I send the 60 day preliminary notice even though I have a ready sent a notice of intent ?
...Read More
Anonymous Contractor
1 answerAdd commentSep 11, 2017
IllinoisLien DeadlinesPreliminary Notice
I recently placed an order for a NOI to lien. When I was hired as a sub-contractor the house was completely gutted(so no one lived there). Would I still need to
do a 60 day preliminary notice when the owners moved out temporarily while construction was going on and only moved back in when the certifi...Read More
...Read More
Anonymous Contractor
2 answersAdd commentSep 8, 2017
IllinoisLien DeadlinesPreliminary Notice
We have multiple jobs where we file a 2nd, then 3rd, then its time for the 4th. We currently do not aggregate all outstanding debt for that job to the fourth
month notice we file the fourth, and then any subsequent filings for the additional 2nd and 3rd months notices as required. Our concern is what ...Read More
...Read More
Anonymous Subcontractor
1 answerAdd commentSep 7, 2017
TexasLien DeadlinesMechanics LienPreliminary Notice
I have an LLC in MO and contracted with a large General Contractor also in Missouri to complete a half done project in Louisville, KY. The owner of the
Louisville property pre-funded my payroll and materials with cash which was to be paid back as my invoives were paid through the monthly draw...Read More
...Read More
Anonymous Subcontractor
1 answerAdd commentSep 7, 2017
KentuckyLien DeadlinesMechanics LienPayment DisputesPreliminary Notice