We gave the contractor foot print and ask for a bid. He redrew he own foot print just like the one we send him and gave us a bid to built . we rejected his bid and send him a note that we went we someone else. He is threatening to put a lien on the property. Requesting $500.00 for the foot print....Read More
We currently have a customer that owes us balances on a job in TX from Septemeber, October, and Nov. We did our letters for 2nd month and 3rd month but January was 4th month from supply on the September invs. Did miss our lien rights on this job since we did not lien by 1/15?...Read More
I'm acting as a sub in Texas. 1. When does retainage accrue? 2. Can I file a lien on retainage before it accrues? 3. How does timing come into play in regards to filing a lien on retainage? Is it based on the last day we provided labor or materials or when retainage accrues?...Read More
I have been in contact with the legal representative for Pumpco and he raised a concern that an individual was named on the lien. I need to know if this is going to potentially create a bigger mess than the remedy. He certainly thinks so, but I have no idea because I am not a lawyer. Is naming g an in...Read More...Read More
We filed a lien on a property for a company that now has power of attorney. Is that property still lienable? Or do we have to release the lien?...Read More
I have sent over monthly notices and intent to lien documents to the following construction company: Sage Construction LLC Houston, TX For the following project: Penske Truck Leasing 3206 East Abram Street Arlington, TX Sage Construction is refusing to pay me since I worked as a sub-subcontract...Read More...Read More
A subcontractor contacted us for electrical upgrades he needed for a residential remodel he was working on. I dispatched our licensed electricians to meet with the GC. The GC explained what he needed done and our electricians discussed time and material pricing and the GC agreed and our techs st...Read More...Read More
We are a steel fabricator who hired a steel erector and is attempting to file a lien on extra work for which he does not have a change order or written authorization. Is this legal?...Read More
Iam a lighting supplier, we provide the lighting fixtures 9 month ago and we have no get paid, I was contract by the owner, but the property is not owned by the builder, the porperty is now owned by the bank. I will like to know if filling a Lien in this case is correct. Thank you....Read More
The job is complete and we are trying to collect funds on additional work performed. The owners are now saying that they will not pay for the additional work performed. What can we do to demand payment? Lien? We are the GC and bond holder on the job. What is our recourse for payment here?...Read More
I am a California Contractor and I sent my guys to do work under a Texas Contractor at given rates. We payed my guys. We billed the Texas Contractor the negotiated rates. He is a Subcontractor of a Subcontractor and we are a Subcontractor under the Texas Contractor. We have invoiced him and h...Read More...Read More
I funded general contractor specifically to provide funds for him to pay supplier of concrete. General did not pay supplier and supplier is now threatening to lien my property. There was no signed contract between myself and anyone involved and therefore, no contract put on file at county recorders o...Read More...Read More