I am a GC and I have paid my subcontractors per our subcontractor agreements. I have 1 subcontractor that is wanted more than what was agreed do and is threatening a lien. As a GC if I provide a lien waiver to the property owner with proof of payment to each of my subcontractors. Do I as the GC still need to collect a conditional lien waiver from each subcontractor?...Read More
I have a contractor requesting an conditional waiver with application for payment and then requesting an unconditional waiver on the same amount after payment. Is this normal? Couldn't they come back and state that they paid that same amount twice?...Read More