The deadline to file a mechanics lien in Washington is 90 days after the last date when labor or materials were provided to the project, so if your last day on the job was only 15 days ago, the lien deadline should be much further out than 13 days. Note, though, that Washington's deadline to make a payment bond claim is only 30 days after the completion of the contract/ acceptance of the entire project. And, that timeframe sounds like it's more in line with the information given above. If you have any questions about a Levelset order or project, feel free to contact the Levelset support team or your account manager. But, unfortunately, we won't be able to help you with your orders or projects at the Expert Center. Regardless - I hope this information was useful!
0 people found this helpful
Helpful