I am the owner of a project, and my GC wants to get a bond on one of their subs that is asking for a large materials payment upfront. Who would be responsible for paying for that bond? Me, the GC, or do we split the cost?
You should require that the GC cover the cost of the Bond; however, that is usually negotiable and can be a part of the contract sum between owner and GC.