Menu
Home>Levelset Community>Legal Help>When is our lien deadline when we are the General Contractor?

When is our lien deadline when we are the General Contractor?

Florida

We have a large project in FL, which has several completion dates. Our contract and billing are for the entire project work. Is our 90 day lien deadline based on 90 days from the last completion date or would each have a 90 day deadline?

1 reply

Nov 10, 2019
If you have one contract, it would be 90 days from your final furnishing date exclusive of punch list and warranty work.  You different completion dates may be tied to different milestones (such as buildings) you are required to complete per your contract.
0 people found this helpful
Helpful