Wisconsin

We filed an intent to lien and need to file a lien today. The last date worked was 8.26.2021. I ordered the Intent to File a Lien on 1.21.2022, it looks like it has my electronic signature on 1.28.2022. i know i have to wait 30 days. With the above information, do I order it today or do I have to wait until Monday (30 days)?

1 reply

Mar 21, 2022
It looks like the initial deadlines may have been quite tight or may have been missed here. However, even if there is not a valid lien, there are many ways to protect your legal rights as a contractor. Feel free to reach out via my website, michaeljohnsonlegal.com, to evaluate your lien rights and potentially explore other ways to get you paid for your work.