What is the deadline in Florida to File a Lien or Bond claim?

FloridaLien DeadlinesMechanics LienMiller ActRight to Lien

No response from the contractor after completing the project and multiple notices were sent.

1 reply

Jan 21, 2023

Since you are listed as "anonymous sub-subcontractor", I will assume for purposes of your question you are a second-tier subcontractor. If so, you would have had to serve a Notice to Owner (or Notice to Contractor if it's a bonded job) within 45 days of when you first started work and then record a lien/submit a bond claim within 90 days of when you completed your work. You have to meet both deadlines to have a valid lien/bond claim.

0 people found this helpful