We completed work on an apartment pool. The work was done well but client came back with multiple punch lists. We addressed all of there concerns and went above and beyond to ensure they were satisfied. After having outside corporate trainer visit and address concerns they notified corporate that they did not wish to continue to work with us and would only talk with product manufacturer. After making multiple efforts to move forward we eventually opted to file a lien. When we where gathering information for the lien I visited there website and found 11 pictures of completed project being used to market the apartments while they claim work was unsatisfactory.
After filing a lien you have one year to foreclose on the lien. If you do not foreclose on the lien it becomes unenforceable. The time limit on liens dose not effect the applicable statute of limitations for contracts.
I would be happy to answer some basic questions to help you decide how to proceed.
Call me, I'll get your money.