Menu
Home>Levelset Community>Legal Help>Should sales tax be applied to change order?

Should sales tax be applied to change order?

WashingtonChange OrdersConstruction Contract

Hi. I would like to learn that when preparing a change order should a sales tax be applied to the total amount of the line items in the change order? Or the total amount of the change order should be added to the original contract price which already included sales tax when signed.

3 replies

May 26, 2022

The base subcontract only included sales tax on the base amount. A change order is an add to that amount and would need to have its own sales tax.

 

1 person found this helpful
Helpful
May 27, 2022
Thank you very much for clarification
0
Report Spam
Apr 17, 2023
Yes, sales tax should be applied to the change order.
0 people found this helpful
Helpful