Menu
Home>Levelset Community>Legal Help>Revision to progress payment schedule

Revision to progress payment schedule

California

We need to revise our remaining payment schedule because of schedule changes to the remaining work. No change order to final project total. Do we need to update our contract to reflect these changes (much like we do on a change order)? Thanks!

3 replies

Jun 22, 2022

This would still technically be a considered a change order. Best practice would be to submit a wirtten change order outling the new payment schedule and the reason for the changes. 

2 people found this helpful
Helpful
Jun 23, 2022
paper minecraft According to the contract, if you don't pay the fine, it's too horrible
0
Report Spam
Aug 16, 2023

I hope this message finds you well. I am writing to inform you about
some adjustments needed in our remaining payment schedule due to recent
changes in the project's work schedule. I'd like to emphasize that these
modifications will not impact the final project total, and there won't
be any alteration to the agreed-upon amount. [aarp mahjongg solitaire](https://aarpmahjonggsolitaire.com)

0
Report Spam