I submitted an NTO for a project that started 12/7/22 - 12/27/22. However, through change orders, the project has continued through 4/24/23. My last payment was through 3/2/23. do I need to submit a new NTO or file a lien?
Change orders are by statute part of the contract. Only one NTO is required under those circumstances. Your next step is to file a construction lien within 90 days of completing your work. File sooner rather than later.
No need to refile an NTO. It is time to record a claim of lien. Contact a construction attorney to prepare the lien for you.