started work in 5/26/2020, client paid $5200 to start work but hasn't a paid 2021 or 2022 invoices. Last invoice was on 2/28/22 and is due upon receipt. Balance is now $17k.

3 replies

Apr 6, 2022

There are two deadlines for liens, the first is 90 days after last date of work. This determines whether you are legally within the timeframe to record a lien. The second is the 150 day "lookback" from either last date of work or recording of lien whichever is earlier. You can only capture money owed for work performed within the 150 day window. In otherwords, take the last work date and go back 150 days. Any work performed in that time frame can be liened. Any work performed before that earliest date cannot.

0 people found this helpful
Helpful
Jun 27, 2022

Can you help with enforcing a recorded lien in Stafford County, VA?

0
Report Spam
Jun 27, 2022

Without more information, I can't make that assessment, but please feel free to contact me by phone.

0 people found this helpful