Miller Act Claim

CaliforniaMiller Act
Anonymous Subcontractor

I'm a subcontractor that worked on a federal building project. Our last day on the project was 10/4/2019 but we still have not been fully paid. I used Levelset to send in a Miller Act Claim on 9/24/2020. What are the next steps we need to take to enforce our Miller Act Lien Rights?

1 reply

You should consult with a construction attorney, but you may have just missed your window to file suit on the bond (1 year from the date of last funishing) --- see https://www.levelset.com/blog/miller-act/ 

 You may still have a contract right against the prime contractor, of course. Again, I would consult an attorney as soon as possible!

NOTE: The information presented here is general in nature and is not intended nor should be construed as legal advice for any particular case or client. The
content contained herein is published online for informational purposes only, may not reflect the most current legal developments, verdicts or settSee More...
See More...
1 person found this helpful
Helpful