what are the legal provisions and requirements related to mechanics' liens and their filing deadlines? Can a subcontractor file a mechanics lien after 90 days?

1 reply

Jun 6, 2023
NO, if you do not file within 90 days of when you ceased providing labor, then you have no lien rights. But you can still sue for what is owed.