I am a subcontractor working for a general contractor that is contracted through a city. We are currently owned for work completed in January and have sent the second month notice. What is the next step to protect our money?

3 replies

Apr 4, 2023

what kind of notice in particular have you sent? I specialize in getting contractors paid, feel free to call or email me with questions. I may be able to help.

Joshua@wolfgangandrhodes.com

(214) 518-9595

2 people found this helpful
Helpful
Apr 4, 2023

If it is a Texas City, there may be a Government Code payment bond involved. The notice requirements are a little different under the Government Code for a bond claim than for a lien claim under the Property Code. You should consult someone who knows the difference well before April 15.

0 people found this helpful
Helpful
Apr 20, 2023

Do you need any further help with this?