I am a subcontractor working for a general contractor that is contracted through a city. We are currently owned for work completed in January and have sent the second month notice. What is the next step to protect our money?
what kind of notice in particular have you sent? I specialize in getting contractors paid, feel free to call or email me with questions. I may be able to help.
Joshua@wolfgangandrhodes.com
(214) 518-9595
If it is a Texas City, there may be a Government Code payment bond involved. The notice requirements are a little different under the Government Code for a bond claim than for a lien claim under the Property Code. You should consult someone who knows the difference well before April 15.
Do you need any further help with this?